Skip to content

Neoen and Engie Await Government Approval to Relaunch Giant Solar Plant

The 800 MW Horizeo photovoltaic project spanning 680 hectares in Gironde awaits governmental authorization linked to France’s Zero Net Artificialization (ZAN) objective to advance permits submitted in early 2024.

Neoen and Engie Await Government Approval to Relaunch Giant Solar Plant

Sectors Solar Energy, Photovoltaic
Themes Project Development, Permits & Authorizations
Companies RTE, Banque des Territoires, Engie, Neoen
Countries France

French energy groups Neoen and Engie filed permit applications in late February 2024 to build the Horizeo solar power plant, a project planned to generate 800 megawatts (MW) over approximately 680 hectares of forestland in the Gironde department. Costing an estimated €600 million, Horizeo is primarily financed by Engie, which holds a 60% share—90% funded directly by Engie, and 10% contributed by Banque des Territoires—while Neoen holds the remaining 40%. The project’s economic model is based chiefly on Power Purchase Agreements (PPAs), without public subsidies. The initial schedule anticipates commissioning by 2028, pending the resolution of current administrative obstacles.

Regulatory Constraints Linked to ZAN

The Horizeo project, conceived prior to the enforcement of new regulations restricting solar farms to a maximum surface area of 25 hectares in forested areas, faces challenges posed by France’s Zero Net Artificialization (ZAN) national policy, effective since August 2021. This policy aims to limit the impact of new developments on natural land, currently slowing the final approval of the project. To proceed, project developers now await clarification or explicit exemption from national authorities.

Public Debate and Project Revision

Between September 2021 and January 2022, an extensive public consultation organized by the French National Commission for Public Debate (CNDP) led to adjustments in the original project scope. Initially planned to span up to 1,000 hectares with a capacity of one gigawatt (GW), Horizeo was scaled down to its current size of 680 hectares and 800 MW. These adjustments also led to the abandonment of complementary components initially planned, such as a data center, an electrolyzer for green hydrogen production, and electrical storage facilities.

Agricultural Development and Fire Risk Management

The project includes an agrivoltaic component over eight hectares, enabling coexistence between agricultural production and solar panels. Additionally, a reforestation plan is scheduled for abandoned agricultural plots to offset forest loss. In response to local concerns, the project developers have conducted specific studies on fire prevention, incorporating safety measures like cleared buffer zones to mitigate fire risks.

Local Opposition and Environmental Concerns

Despite these measures, the Horizeo project faces strong local opposition, particularly from agricultural and forestry unions, hunting groups, and environmental associations. These stakeholders primarily cite heightened risks of fire and flooding, as well as potential appropriation of forest land. The municipality of Saucats, located at the center of the project area, has also expressed uncertainty about the precise ecological impacts of deforestation.

The finalization of the Horizeo project thus remains contingent upon a governmental decision regarding the ZAN. This situation may prompt economic actors to carefully consider the implications of land-use regulation on major energy projects in France.

Also read

Saudi Arabia Set to Fall Short of Its 130 GW Renewable Energy Target

The kingdom had reached only 13 GW of renewable capacity by 2025. Experts now project 74.2 GW by 2030, well below target, as rising domestic demand weighs on oil export revenues.

Saudi Arabia Set to Fall Short of Its 130 GW Renewable Energy Target

Boralex raises 350,000 euros via Enerfip for an agrivoltaic plant in Ardèche

Boralex and Enerfip launch on April 2 a citizen fundraising campaign of 350,000 euros to finance the Le Bosquet agrivoltaic plant in Saint-Didier-sous-Aubenas, Ardèche, offering a

Boralex raises 350,000 euros via Enerfip for an agrivoltaic plant in Ardèche

Cherry Valley Solar I closes financing for 135 MW photovoltaic project in Arkansas

In Cross County, Arkansas, the 135 MW photovoltaic plant closed its non-recourse financing on February 21, 2025 through U.S. Bank, following its acquisition by Adapture Renewables.

Cherry Valley Solar I closes financing for 135 MW photovoltaic project in Arkansas