QatarEnergy and ExxonMobil request termination of Texas LNG project

QatarEnergy and ExxonMobil are seeking to oust Zachry Industrial from the Golden Pass LNG project, citing the bankruptcy of the main contractor and costly delays.

Share:

Faillite contractor projet LNG Texas

Subscribe for unlimited access to all energy sector news.

Over 150 multisector articles and analyses every week.

Your 1st year at 99 $*

then 199 $/year

*renews at 199$/year, cancel anytime before renewal.

QatarEnergy and ExxonMobil, co-owners of the Golden Pass liquefied natural gas (LNG) project in Texas, have filed a motion with a US court to terminate Zachry Industrial’s contract. This action follows the bankruptcy of Zachry, the main contractor, and major delays caused by cost overruns. For its part, QatarEnergy continues to invest in the gas sector, as illustrated by the acquisition of 104 LNG vessels.

Background and implications

The $10 billion Golden Pass LNG project is a joint venture between QatarEnergy and ExxonMobil. This project, crucial to increasing liquefied natural gas production capacity in the United States, is currently 75% complete. However, Zachry’s Chapter 11 bankruptcy last month has halted work and laid off thousands of workers.
The project owners have asked the court to terminate Zachry’s $5.8 billion contract within five days or allow possession and control of the facilities to prevent further deterioration.

Financial and legal challenges

Zachry said project costs had increased by $2.4 billion due to pandemic-related challenges, changes in orders and billing schedules. Unable to resolve these differences with the owners, Zachry opted for a “structured exit”. The company hopes to receive fair compensation for its role in the construction, while continuing to work on other projects nationwide.
Golden Pass LNG representatives pointed out that Zachry’s abandonment of the project had left costly and complex infrastructure components partially completed and exposed to the elements, posing additional risks to the project.

Outlook and next steps

Golden Pass LNG has stressed the urgency of resuming work to limit damage and delays. The project, originally scheduled to start processing gas this year, has not yet announced a new completion schedule.
The implications of this situation are far-reaching, affecting not only the contracting parties but also local workers and suppliers. Rapid resolution of this conflict is crucial to minimize financial and operational losses.
The request to terminate the contract is a decisive step for QatarEnergy and ExxonMobil in their efforts to regain control of the project and continue its development. This situation also highlights the challenges and risks inherent in large-scale energy infrastructure projects.

CTCI strengthens its position in Taiwan with a new EPC contract for a regasification unit at the Kaohsiung LNG terminal, with a capacity of 1,600 tonnes per hour.
Exxon Mobil forecasts sustained growth in global natural gas demand by 2050, driven by industrial use and rising energy needs in developing economies.
Capstone Green Energy received a 5.8-megawatt order for its natural gas microturbines, to be deployed across multiple food production facilities in Mexico through regional distributor DTC Machinery.
Private firm Harvest Midstream has signed a $1 billion acquisition deal with MPLX for gas processing and transport infrastructure across three western US states.
Sempra Infrastructure and EQT Corporation have signed a 20-year liquefied natural gas purchase agreement, consolidating Phase 2 of the Port Arthur LNG project in Texas and strengthening the United States’ position in the global LNG market.
Subsea7 was selected to lead phase 3 of the Sakarya gas field, a strategic contract for Türkiye’s energy supply valued between $750mn and $1.25bn.
Tokyo protests against Chinese installations deemed unilateral in a disputed maritime zone, despite a bilateral agreement stalled since 2010.
Bp has awarded Baker Hughes a long-term service agreement for the Tangguh liquefied natural gas plant, covering spare parts, maintenance and technical support for its turbomachinery equipment.
Chinese group Sinopec has launched a large-scale seismic imaging campaign across 3,000 km² in Mexico using nodal technology from Sercel, owned by Viridien, delivered in August to map areas with complex terrain.
CNOOC Limited has signed two production sharing contracts with SKK Migas to explore the Gaea and Gaea II blocks in West Papua, alongside EnQuest and Agra.
A consortium led by ONEOK is developing a 450-mile pipeline to transport up to 2.5 billion cubic feet of gas per day from the Permian Basin to the Gulf Coast.
AMIGO LNG has awarded Drydocks World a major EPC contract to build the world’s largest floating LNG liquefaction terminal, aimed at strengthening exports to Asia and Latin America.
The Alberta Utilities Commission approves the Need Assessment Application for the Yellowhead Pipeline, marking a key step for Canadian Utilities, a subsidiary of ATCO. The project foresees significant economic benefits for the province.
Nigeria LNG signs major deals with oil groups to ensure gas supply to its liquefaction infrastructure over two decades.
The European Union and Washington have finalized an agreement setting $750 billion in U.S. gas, oil and nuclear purchases, complemented by $600 billion in European investments in the United States by 2028.
Sempra Infrastructure and ConocoPhillips signed a 20-year LNG sales agreement for 4 Mtpa, confirming their joint commitment to expanding the Port Arthur LNG liquefaction terminal in Texas.
Russian pipeline gas exports to China rose by 21.3% over seven months, contrasting with a 7.6% drop in oil shipments during the same period.
MCF Energy continues operations at the Kinsau-1A drilling site, targeting a promising Jurassic formation first tested by Mobil in 1983.
The group announces an interim dividend of 53 cps, production of 548 Mboe/d, a unit cost of $7.7/boe and major milestones on Scarborough, Trion, Beaumont and Louisiana LNG, while strengthening liquidity and financial discipline.
Norway’s combined oil and gas production exceeded official forecasts by 3.9% in July, according to preliminary data from the regulator.