The nuclear power plant of Saint-Laurent-des-Eaux, a titanic construction site for a second youth

The Saint-Laurent-des-Eaux nuclear power plant is undergoing a "complete check-up" to extend its life by ten years, with an investment five times higher than at the last review in 2013. This program is part of the Grand Carénage, EDF's largest industrial program since its creation in 1946, aimed at modernizing and extending the life of power plants beyond 40 years to cope with climate change.

Share:

On the banks of the Loire River, reactor No. 2 at the Saint-Laurent-des-Eaux nuclear power plant has stopped delivering megawatt-hours to accommodate an army of workers at the service of a gigantic construction site: the time has come for a “complete check-up” to enable it to produce for another ten years, with climate change in its sights.

In the engine room, a large cathedral where electricity gushes out of the steam at the end of the turbo-alternator, the operators are busy amidst scaffolding and monumental boneless parts. For this giant “technical control”, the plant will host up to 2,700 employees simultaneously, instead of the usual 1,000.

“Right now, the plant has a higher level of safety than when it was commissioned” in 1983, assures Sylvie Richard, director of the “Grand Carénage”, the vast program launched in 2015 by EDF to modernize and extend the life of the plants beyond 40 years. Ten of EDF’s 900 MW reactors have successfully completed their fourth 10-yearly inspections. The one in Saint-Laurent, on the same level, began on January 21 and will last 7 months.

The stakes are high for these 40-year-old power plants, the oldest in the 56-reactor fleet: obtaining an operating license from the French Nuclear Safety Authority for another ten years. To achieve this, 17,000 operations are planned, for an investment “five times higher than during the last periodic review” in 2013, emphasizes the site director, Nicolas André.

The reactor first undergoes three regulatory tests: in addition to the inspection of the stainless steel vessel from every angle, a hydraulic test of the primary circuit and a test of the concrete containment, which prevents the escape of radioactive products to the outside in case of an accident, are planned. “The enclosure is inflated with pressurized air to check its tightness,” explains Arnaud Besnard, maintenance coordinator in the reactor building.

Also on the agenda: major maintenance work such as the replacement of the turbo-generator rotors and the addition of additional cooling systems and a corium stabilizer, to recover an accidental leak of molten fuel under the reactor.

Next project, the climate

The vast construction site of the extension is at the heart of the Grand Carénage, whose cumulative cost of the first (2015-2021) and second (2022-2028) phases amounts to 66 billion euros. “It’s the biggest industrial program since the creation of EDF in 1946,” summarizes Sylvie Richard.

In its first phase, 800 modifications were made, based on national and international feedback, in particular from the Fukushima disaster in Japan in 2011. They include the construction of backup water and power capabilities to deal with a power failure that would threaten the cooling of the facility. “It’s a great asset for continued operation,” says Sylvie Richard.

The government has decided that, in addition to the construction of at least six new EPR2 reactors, the reactors will have to be extended beyond 50 years if possible. “It’s no longer a taboo, other countries are doing it,” says Sylvie Richard, referring to the United States. EDF is already working on the program for the fifth ten-yearly outage for the plants that will reach 50 years of age in 2029. “We have called it a ten-year visit to the climate change” because “it will include important scenarios that will have to demonstrate the performance of our equipment”, emphasizes the Director of the Grand Carénage.

EDF assures that it is not starting “from scratch”: “all the power plants have undergone significant changes to resist aggression – floods, snowstorms, tornadoes”, it adds. “We are also improving the performance of the cooling systems of the plants”, which represents the third largest water consumption in the country (12%) and the major issue posed by global warming in nuclear power.

In a report dated March 21, the Cour des Comptes called on EDF to “strengthen its research” on these systems to make them more “water-efficient”, noting that “no innovation” had been implemented on the existing fleet and, even more, “the absence of any marked evolution” for future EPRs.

On Thursday, President Emmanuel Macron promised investments in nuclear power “to save water,” without putting a figure on them.

American companies SHINE Technologies and Standard Nuclear partner to recycle uranium and plutonium, supplying advanced fuel to the nuclear reactor sector and enhancing the national energy security of the United States.
The American Bureau of Shipping and two nuclear sector companies are studying the potential deployment of floating nuclear power plants to meet the energy needs of island and coastal regions in the Mediterranean, notably via electricity and desalination.
Lithuania establishes a working group tasked with assessing the feasibility of modular nuclear reactors to meet electricity demand estimated at 74 TWh by 2050.
Framatome has secured two significant contracts from Electrabel covering modernisation and technical support for the Tihange 3 and Doel 4 nuclear reactors, as part of their extension agreed upon between Engie and the Belgian government.
Cairo is stepping up connection works for the planned 4,800 MW El-Dabaa nuclear plant, developed with Rosatom, to feed the grid from 2026 with output equal to about seven % of national electricity.
EDF extends Flamanville EPR's shutdown to August 13 to conduct technical checks on three valves of the reactor's primary circuit, initially scheduled to resume production this week.
The US Department of Energy has selected Westinghouse and Radiant Nuclear to conduct the first nuclear microreactor tests at the DOME experimental centre located in Idaho, with operational start expected in spring 2026.
GE Vernova Hitachi Nuclear Energy and Fortum announce partnership aimed at preparing for the potential deployment of small modular reactors in Finland and Sweden, with commissioning scheduled for the 2030s.
Energy Fuels Inc. announced record production of 638,700 pounds of uranium during the second quarter of 2025 at its Pinyon Plain mine in Arizona, significantly surpassing initial site performance forecasts.
Argentina and Peru have signed an agreement expanding their scientific and technological cooperation in the civil nuclear field, including joint research projects and specialised training programmes for future development.
After several decades without funding nuclear projects, the World Bank has formed a strategic partnership with the IAEA to provide technical and financial support to countries integrating nuclear energy into their energy strategies.
South Korea's Nuclear Safety and Security Commission officially validates the decommissioning of reactor number one at the Kori plant, initiating an unprecedented project for the national industry scheduled to last until 2037.
Uranium producer enCore Energy surpasses three thousand pounds per day at its Alta Mesa ISR complex and sees three new Texas laws as a strong signal for faster nuclear production permits.
The International Atomic Energy Agency expresses concerns over Iran’s enriched uranium stockpiles following the abrupt suspension of inspections at key sites disrupted by recent attacks whose consequences remain uncertain.
NPCIL has announced an extension until September 30 for industrial proposals concerning Bharat Small Reactors (BSR), following increased interest from the Indian private sector.
A regional court has upheld the award of two new reactors in the Czech Republic to Korea Hydro & Nuclear Power, dismissing Électricité de France’s challenge to the €16bn contract in a decisive step for the national energy programme.
Facing rising temperatures, EDF anticipates cuts in nuclear production starting early July, primarily due to thermal constraints on rivers used for cooling the power plants.
The preliminary agreement launches planning and site assessment for a tailored AP1000 reactor, following two years of feasibility study, and enlists Westinghouse and Hyundai to support Fortum’s regional nuclear expansion.
Donald Trump's unprecedented decision to dismiss Christopher Hanson, a member of the NRC, provokes outrage among former federal officials and raises concerns over the regulatory independence of the U.S. nuclear sector.
Uranium Energy Corp strengthens its position in Anfield Energy Inc., now holding approximately 32.4% of the company’s shares following an investment of CAD19.55mn ($14.82mn), significantly expanding its strategic influence in the uranium market.