Flamanville EPR reactor reconnected to grid two days ahead of schedule

EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.

Share:

The European Pressurised Reactor (EPR) located in Flamanville, Manche, was reconnected to the French power grid on Saturday 19 April at 8:30 p.m., according to information released by Électricité de France (EDF) the following day. This step marks progress in the power-up phase of the reactor, which had been offline since 15 February due to unplanned maintenance operations. The early return to the grid follows several successive delays related to safety inspections.

The reactor, which has a maximum output capacity of 1,620 megawatts, resumed operation at a limited level of 90 megawatts. EDF confirmed that power variation tests are scheduled until the following Wednesday. This gradual increase in output is part of the initial startup process for a third-generation nuclear reactor, which spans several months to comply with safety protocols. Full power output, equating to 100% of nominal capacity, remains scheduled for summer 2025.

Extended maintenance on cooling system components

The reactor’s shutdown, initially intended as temporary, was extended twice in February. EDF carried out work on a cooling system using seawater, on the turbo-alternator unit, and on other elements considered necessary to ensure safe progression through the power-up sequence. The group also noted that further adjustments had been made to the bearings guiding the turbine rotors.

These technical operations are part of the standard procedures for a new-generation reactor, particularly during the system validation phase. EDF highlighted that more than 1,500 safety criteria are assessed during the initial startup, which can require several planned stoppages or unexpected adjustments.

A restart following multiple delays since late March

The reactor’s recommissioning was originally scheduled for 30 March but was postponed several times. The latest timeline indicated a return to the grid on Monday 21 April. This recent progress in the Flamanville EPR project comes as EDF aims to stabilise availability across its national nuclear fleet, comprising 57 reactors.

The Flamanville reactor was connected to the grid for the first time on 21 December 2024, twelve years behind the original schedule. Since then, it has undergone two scheduled stoppages. EDF considers this gradual load increase a standard procedure for a first startup, requiring in-depth testing at each operational stage.

SE Ignalina, the Lithuanian nuclear operator, has signed a memorandum of understanding with French firm Newcleo to explore the integration of small modular reactors (SMRs) using lead-cooled fast reactor (LFR) technology in Lithuania.
Egyptian President Abdel Fattah al-Sisi oversaw the signing of new agreements for the construction of the El Dabaa nuclear power plant, thus strengthening the strategic cooperation between Egypt and Russia.
Vistra Corp receives green light to extend Perry nuclear plant operations in Ohio by 20 years, securing regional electricity supply until 2046 and ensuring operational continuity for all its nuclear reactors in the United States.
EDF will hold a 12.5% stake in the Sizewell C nuclear project in the UK, a €1.3 billion investment announced during Emmanuel Macron’s official visit to London, confirming the strategic nuclear energy alignment between the two countries.
The French Cigéo project, designed to bury the most hazardous radioactive waste deep underground, obtains a crucial technical validation before its final authorization, expected by the end of 2027.
EDF confirms the continuation of its industrial project in Fessenheim for recycling very low-level radioactive metals, a first in France requiring specific regulatory authorizations, following a public debate concluded last February.
NANO Nuclear Energy Inc. formalizes its collaboration with UrAmerica Ltd. to strengthen Argentina’s uranium supply, aiming to secure future nuclear fuel supply chains for the U.S. market.
American companies SHINE Technologies and Standard Nuclear partner to recycle uranium and plutonium, supplying advanced fuel to the nuclear reactor sector and enhancing the national energy security of the United States.
The American Bureau of Shipping and two nuclear sector companies are studying the potential deployment of floating nuclear power plants to meet the energy needs of island and coastal regions in the Mediterranean, notably via electricity and desalination.
Lithuania establishes a working group tasked with assessing the feasibility of modular nuclear reactors to meet electricity demand estimated at 74 TWh by 2050.
Framatome has secured two significant contracts from Electrabel covering modernisation and technical support for the Tihange 3 and Doel 4 nuclear reactors, as part of their extension agreed upon between Engie and the Belgian government.
Cairo is stepping up connection works for the planned 4,800 MW El-Dabaa nuclear plant, developed with Rosatom, to feed the grid from 2026 with output equal to about seven % of national electricity.
EDF extends Flamanville EPR's shutdown to August 13 to conduct technical checks on three valves of the reactor's primary circuit, initially scheduled to resume production this week.
GE Vernova Hitachi Nuclear Energy and Fortum announce partnership aimed at preparing for the potential deployment of small modular reactors in Finland and Sweden, with commissioning scheduled for the 2030s.
Energy Fuels Inc. announced record production of 638,700 pounds of uranium during the second quarter of 2025 at its Pinyon Plain mine in Arizona, significantly surpassing initial site performance forecasts.
Argentina and Peru have signed an agreement expanding their scientific and technological cooperation in the civil nuclear field, including joint research projects and specialised training programmes for future development.
After several decades without funding nuclear projects, the World Bank has formed a strategic partnership with the IAEA to provide technical and financial support to countries integrating nuclear energy into their energy strategies.
South Korea's Nuclear Safety and Security Commission officially validates the decommissioning of reactor number one at the Kori plant, initiating an unprecedented project for the national industry scheduled to last until 2037.
Uranium producer enCore Energy surpasses three thousand pounds per day at its Alta Mesa ISR complex and sees three new Texas laws as a strong signal for faster nuclear production permits.
The International Atomic Energy Agency expresses concerns over Iran’s enriched uranium stockpiles following the abrupt suspension of inspections at key sites disrupted by recent attacks whose consequences remain uncertain.