Advertising

EDF requests ASN authorization to start up the Flamanville EPR

EDF has applied to the ASN to launch the Flamanville EPR, a complex project whose costs have quadrupled and which is twelve years behind schedule. The divergence authorization is awaited before production can begin.
EPR de Flamanville

Please share:

EDF has officially applied to the French Nuclear Safety Authority (ASN) to authorize the first divergence of the Flamanville EPR (European Pressurized Reactor), a decisive step for the start-up of this new-generation reactor.
In May 2024, the company completed the loading of 60,000 nuclear fuel rods into the reactor vessel, a process that continued with cold tests until July, followed by hot tests where the reactor pressure was raised to 155 bars and the temperature to 303 degrees.
These tests are the final stage in a project that began seventeen years ago and has been plagued by a series of technical problems, including cracks in the concrete slab and welding defects in the containment vessel.
These technical difficulties not only delayed the reactor’s commissioning by twelve years compared to the original 2012 schedule, but also quadrupled the budget, from 3.3 billion euros to 13.2 billion euros.
In 2020, the French Cour des Comptes estimated that the total cost of the project, including additional financing costs, could reach 19 billion euros.

Technical and financial challenges: Management under pressure

The Flamanville EPR, located in the French department of Manche, is set to be the fourth reactor of its type installed worldwide, and the most powerful in France, with a capacity of 1,600 MW.
This long-term project has raised numerous management and supervision challenges.
EDF claims that no changes to the schedule are currently planned for the connection to the electricity grid, also known as “coupling”, and is aiming to produce the first electrons by September 21, 2024.
When the reactor reaches full capacity, it will be able to supply around three million French households.
EDF hopes to reach full production before the end of the year, although the reactor is already scheduled to operate at 25% of capacity when it is initially commissioned.
The start-up of the Flamanville EPR is of strategic importance as France seeks to revitalize its nuclear industry.
The government has ordered six new EPR2 reactors, with an additional eight as an option, a strong sign of its determination to support this technology despite the delays and extra costs observed.

Symbolism and implications for the nuclear industry

The Flamanville project comes at a key moment in French energy policy.
The last nuclear reactors commissioned in France were Chooz in 2000 and Civaux in 2002.
The start-up of the Flamanville EPR, although initiated well before the government’s recent decision to revive nuclear power, takes on a highly symbolic dimension for the future of the industry.
EDF has the opportunity to demonstrate that the technical difficulties encountered on this project can be overcome, and to set a positive precedent for future EPR2s.
As for the ASN, it plays a key role in ensuring that the reactor complies with all safety standards before giving its go-ahead for commissioning.
This vigilance is all the more crucial given the project’s track record.
For EDF, the stakes are high: restoring confidence in its ability to manage projects of this scale, while respecting safety and cost constraints.

Impact on energy and industrial strategy

The commissioning of the Flamanville EPR will have significant implications for the French nuclear industry and for EDF, which remains wholly state-owned.
The ability to meet the deadlines and costs for this reactor will influence perceptions of the feasibility of future nuclear projects, particularly in a changing European energy market.
The evolution of this project could also serve as a benchmark for other nations considering modernizing or strengthening their nuclear capabilities.
Industry professionals are keeping a close eye on developments surrounding the Flamanville EPR.
Its commissioning could either strengthen the position of EPR technology on the international stage, or, in the event of further delays or difficulties, raise questions about the economic viability of these new-generation reactors.
The next few months will therefore be crucial for EDF and the French nuclear industry.

Register free of charge for uninterrupted access.

popular articles

Advertising

Recently published in

Japan adopts measures to facilitate the restart of Tepco's Kashiwazaki-Kariwa nuclear power plant, strengthening safety and governance to secure the necessary local support.
The Italian government is planning legislation by 2025 to lift the ban on nuclear power, paving the way for SMR and other cutting-edge technologies.
The Italian government is planning legislation by 2025 to lift the ban on nuclear power, paving the way for SMR and other cutting-edge technologies.
The Barakah nuclear power plant in the United Arab Emirates is now fully operational with its four reactors, providing 25% of the country's electricity supply.
The Barakah nuclear power plant in the United Arab Emirates is now fully operational with its four reactors, providing 25% of the country's electricity supply.
Tohoku Electric Power begins loading nuclear fuel at Onagawa 2, after a decade of modernization to comply with Japan's new safety requirements.
Tohoku Electric Power begins loading nuclear fuel at Onagawa 2, after a decade of modernization to comply with Japan's new safety requirements.
Tokamak Energy launches TE Magnetics to develop and market high-temperature superconducting (HTS) magnets for fusion reactors and other industrial applications.
The EPR reactor at Flamanville is experiencing an automatic shutdown after its first nuclear fission. EDF teams are carrying out technical checks to identify the cause and restart the divergence process.
The EPR reactor at Flamanville is experiencing an automatic shutdown after its first nuclear fission. EDF teams are carrying out technical checks to identify the cause and restart the divergence process.
The NRC authorizes Kairos Power's Hermes 2 project in Oak Ridge, Tennessee, by issuing a final environmental assessment, without requiring a new environmental impact statement.
The NRC authorizes Kairos Power's Hermes 2 project in Oak Ridge, Tennessee, by issuing a final environmental assessment, without requiring a new environmental impact statement.
The IAEA expresses its concerns about the safety of the Kursk and Zaporizhia nuclear power plants, threatened by armed conflict in Ukraine, during a meeting between Rafael Grossi and Volodymyr Zelensky.
The IAEA expresses its concerns about the safety of the Kursk and Zaporizhia nuclear power plants, threatened by armed conflict in Ukraine, during a meeting between Rafael Grossi and Volodymyr Zelensky.
Orano, a leader in the French nuclear sector, chooses Tennessee to develop a uranium enrichment plant, strengthening the United States' energy autonomy in the face of geopolitical risks linked to Russia.
The Czech Competition Office (UOHS) is analyzing the appeals lodged by Westinghouse and EDF against the selection of Korea Hydro & Nuclear Power Company to build two reactors.
The Czech Competition Office (UOHS) is analyzing the appeals lodged by Westinghouse and EDF against the selection of Korea Hydro & Nuclear Power Company to build two reactors.
The Flamanville EPR achieves its first nuclear reaction, marking a key point in its commissioning. EDF CEO Luc Rémont highlights the importance of this milestone for France's energy future.
The Flamanville EPR achieves its first nuclear reaction, marking a key point in its commissioning. EDF CEO Luc Rémont highlights the importance of this milestone for France's energy future.
Fortum now uses fuel from Westinghouse Electric Company for its Loviisa reactors, a strategic move to diversify supplies and strengthen Finland's energy security.
Fortum now uses fuel from Westinghouse Electric Company for its Loviisa reactors, a strategic move to diversify supplies and strengthen Finland's energy security.
EDF announces a further delay to the connection of the Flamanville EPR to the electricity grid. Start-up has been pushed back to late autumn 2024, adding to a long series of delays in this strategic nuclear project.
Helical Fusion aims to develop a stable nuclear fusion reactor by 2034, marking an important step towards emission-free energy production and reinforcing Japan's energy strategy.
Helical Fusion aims to develop a stable nuclear fusion reactor by 2034, marking an important step towards emission-free energy production and reinforcing Japan's energy strategy.
London proposes a £5.5 billion subsidy for EDF's Sizewell C nuclear power station, aimed at securing energy supply and meeting energy policy objectives.
London proposes a £5.5 billion subsidy for EDF's Sizewell C nuclear power station, aimed at securing energy supply and meeting energy policy objectives.
The Nuclear Regulatory Commission (NRC) authorizes Framatome to transport fuel enriched up to 8% in U-235 to light water reactor power plants in the United States.
The Nuclear Regulatory Commission (NRC) authorizes Framatome to transport fuel enriched up to 8% in U-235 to light water reactor power plants in the United States.
Beijing approves four Westinghouse AP1000 reactors for the Bailong and Lufeng sites, marking a key step in the integration of American nuclear technologies.
Iran continues to enrich uranium at high levels without improving its cooperation with the International Atomic Energy Agency (IAEA), despite resolutions demanding greater transparency.
Iran continues to enrich uranium at high levels without improving its cooperation with the International Atomic Energy Agency (IAEA), despite resolutions demanding greater transparency.
The UK government authorizes Westinghouse's AP300 to begin the generic design assessment process, reinforcing its nuclear strategy.
The UK government authorizes Westinghouse's AP300 to begin the generic design assessment process, reinforcing its nuclear strategy.
Norsk Kjernekraft and DL Group start a study for modular nuclear reactors in Mongstad, to meet Norway's energy needs and emissions reduction targets.
Norsk Kjernekraft and DL Group start a study for modular nuclear reactors in Mongstad, to meet Norway's energy needs and emissions reduction targets.
ČEZ and the Czech government reach an agreement to move forward on the strategic Modular Reactors (SMRs) project, guaranteeing national energy security.
The International Atomic Energy Agency (IAEA) is monitoring the Kursk nuclear power plant as Ukraine steps up its offensive in the Russian border region.
The International Atomic Energy Agency (IAEA) is monitoring the Kursk nuclear power plant as Ukraine steps up its offensive in the Russian border region.
Japan plans to restart the Kashiwazaki-Kariwa nuclear power plant. The project, crucial to the country's energy supply, faces safety challenges and complex political considerations.
Japan plans to restart the Kashiwazaki-Kariwa nuclear power plant. The project, crucial to the country's energy supply, faces safety challenges and complex political considerations.
EDF and Westinghouse lodge appeals against the Czech Republic's award of the nuclear reactor project to Korea Hydro & Nuclear Power (KHNP), citing intellectual property violations and procedural irregularities.
EDF and Westinghouse lodge appeals against the Czech Republic's award of the nuclear reactor project to Korea Hydro & Nuclear Power (KHNP), citing intellectual property violations and procedural irregularities.

Welcome

Your subscription

Included in this subscription: