French Guiana: the construction permit for a thermal power plant validated on appeal

The administrative court of appeal of Bordeaux has overturned the decision of the administrative court of Guyana which had cancelled the building permit for a thermal power plant near Cayenne. This decision puts an end to an arm wrestling match between environmentalists and EDF, who were contesting the project.

Partagez:

The administrative court of appeal of Bordeaux validated on Tuesday the building permit issued by the State for the construction of a thermal power plant in Larivot, near Cayenne, the object of an intense battle between environmentalists and EDF.

This permit was cancelled in July by the administrative court of French Guiana on the grounds of a risk of flooding for the installation and an attack on an area classified as a remarkable coastal space. But the Bordeaux court in turn overturned this ruling, validating as in February the analysis of the prefecture of French Guiana, according to which there is no “satisfactory solution other than the one chosen for the implementation of the new thermal power plant”. The administrative court of appeal of Bordeaux had also confirmed, in February, the environmental authorization of the plan.

The Larivot power plant, in the commune of Matoury, is to replace the aging oil-fired plant in Degrad-des-Cannes and run on liquid biofuels, which would require the construction of a 14-kilometer pipeline to transport them. The local prefect had granted a building permit for a large seaside power plant in October 2020, as Guyana’s electricity supply is fragile.

The project “does not take advantage of the resources of Guyana but imports fuels that pollute,” denounced to AFP Garance Lecocq, coordinator of Guyane nature environment, an association plaintiff in the case.

In a statement on Tuesday, the EDF subsidiary in charge of the project, EDF-PEI, said that construction of the plant would resume “as soon as the rainy season ends”.

On the side of the opponents, an “appeal to the Council of State will be discussed in the coming days”, explained Ms. Lecocq, both on the environmental authorization and the building permit.

The Aix-Marseille-Provence metropolis entrusts Waga Energy with the digital management of biogas generated from waste at the Arbois facility using the eLandfill platform, to enhance technical efficiency and operational monitoring at the site.
Minéraux Stratégiques Abitibi has signed a non-disclosure agreement paving the way for talks with the Abitibiwinni First Nation and the City of Amos to develop a biomass plant on the former Résolu industrial site.
Due to insufficient industrial backing, Global Bioenergies has launched a pre-pack sale process amid high bank debt and limited liquidity. Offers must be submitted by 9 July.
Waga Energy has commissioned a biomethane facility in British Columbia, in partnership with FortisBC and Capital Regional District, marking the first unit of its kind on Vancouver Island.
A new report by the International Energy Agency identifies significant untapped potential in biogas and biomethane, hindered by regulatory and economic barriers.
Joint venture between Airex Énergie, Groupe Rémabec and SUEZ begins industrial biochar production in Port-Cartier, targeting 30,000 tonnes annually by 2026.
TotalEnergies sold 50% of Polska Grupa Biogazowa to HitecVision for €190mn to accelerate biogas development in Poland and reach 2 TWh of biomethane by 2030.
Project Avance aims to build a pilot plant in Québec to produce Sustainable Aviation Fuel (SAF) from sawmill residues, contributing to the decarbonisation of the aviation sector.
A public inquiry on Gardanne’s biomass sourcing begins as GazelEnergie resumes operations at 4,000 hours per year.
Aemetis Biogas recorded $1.6mn in revenue in April from California LCFS and federal D3 RIN credit sales, pending capacity expansion with seven new digesters.
Facing supply fluctuations, integrated biorefineries are emerging as an effective industrial solution, combining diverse feedstocks to optimize operating costs and secure renewable fuel supplies, crucial to achieving carbon neutrality goals.
Rennes Métropole and ENGIE Solutions are launching a EUR156mn project to extend a 78-kilometre district heating network powered entirely by renewable and recovered energy sources.
German group EnviTec Biogas inaugurated its largest US plant earlier this year in South Dakota, reinforcing its industrial partnership with SJI Renewable Energy Ventures.
Aemetis Biogas recorded a 55% increase in renewable natural gas production in March, supported by favourable weather conditions and the expansion of its digester project in California.
The National Assembly approved legislation enabling the conversion of the Saint-Avold coal-fired power plant to biogas, fulfilling a government pledge and impacting approximately 500 jobs.
The French renewable gas sector recorded a 27% rise in output in 2024, reaching 11.6 TWh, although new unit commissioning fell back to 2019 levels.
Urbaser will operate the Étoile verte incinerator in Saint-Ouen-sur-Seine from January 2026 under a €700mn, twelve-year agreement signed with Syctom, the public operator for the Paris region.
Stockholm Exergi approves investment in an industrial BECCS project using Capsol’s CO₂ capture technology, backed by Microsoft and Frontier Group, targeting 800,000 tonnes of CO₂ removed annually from 2028.
Several air transport groups believe the renewable fuel levels set by the European Union for 2030 are unattainable given current production capacities.
The French Senate passed a bill supporting the conversion of the Saint-Avold coal-fired power plant into a biogas facility, a pivotal decision affecting nearly 650 jobs.