Rosatom claims USD 2.9 billion from Finland’s Fortum and Outokumpu

The Moscow Arbitration Court postpones by nine months the trial initiated by Rosatom against Fortum and Outokumpu, seeking nearly three billion dollars following the controversial cancellation of a nuclear project in Finland.

Share:

The legal battle between the Russian group Rosatom and Finnish companies Fortum and Outokumpu has reached a significant new judicial turning point. Originally scheduled for June, the hearing before the Moscow Arbitration Court has been postponed until March 16, 2026, according to official court documents. The dispute involves a substantial sum of 227.8 billion rubles, approximately USD 2.9 billion. Rosatom is demanding compensation following the termination of the EPC (Engineering, Procurement and Construction) contract signed in 2013 for the construction of Finland’s Hanhikivi-1 nuclear power plant.

Origins of the Conflict

The construction project of the Hanhikivi-1 nuclear plant, estimated at between EUR 6.5 and 7 billion, was canceled in May 2022 by the Finnish parties, citing persistent delays and geopolitical risks heightened by the international context. The cancellation occurred shortly after the outbreak of the conflict in Ukraine, adding a sensitive geopolitical dimension to the case. Since then, Rosatom has accused Finnish companies of breaching contractual and shareholder agreements, resulting in significant financial losses.

Outokumpu, a Finnish steel industry specialist, has maintained that it was never directly involved in the construction contract, thus denying any contractual responsibility towards Rosatom. Meanwhile, Fortum, a leading Finnish energy company, argues that a previous ruling by the International Court of Arbitration has already excluded its liability in this matter—a stance it intends to uphold throughout future judicial proceedings.

Major Financial and Legal Stakes

The financial stakes in this dispute are considerable. Rosatom is seeking nearly USD 3 billion as compensation for damages incurred from the contract’s cancellation. Conversely, Fortum and other parties associated with the project, notably Fennovoima, are attempting to recover approximately EUR 1.7 billion already invested before construction was halted. This complex legal battle extends beyond Russian borders, involving multiple international arbitration bodies, notably the International Chamber of Commerce (ICC).

The postponement of the hearing could have significant implications, substantially delaying the judicial process in Russia while potentially impacting the schedule of international arbitrations. The Moscow Arbitration Court did not specify the exact reasons for the delay, but this additional period may allow all parties to further refine their legal and financial arguments given the complexity and magnitude of the case.

Potential Sectoral Implications

Beyond legal considerations, the outcome of this case could influence future commercial and energy relations between Russia and European countries, especially in the nuclear sector. The international energy sector will closely follow developments in this dispute, which could set legal and contractual precedents for major international nuclear projects. Additionally, this conflict could indirectly impact national energy policies, particularly regarding international partnerships and the management of geopolitical risks in large-scale energy investments.

The prolonged judicial process might prompt industry observers and stakeholders to reassess terms and conditions in future major contracts, especially within an uncertain and shifting international context.

Slovenské elektrárne has signed an agreement with Urenco for the purchase of enriched uranium for the Bohunice and Mochovce nuclear power plants, strengthening the diversification of its supply sources until the mid-2030s.
Emirates Nuclear Energy Company signs two major agreements with Hyundai Engineering & Construction and Westinghouse, strengthening its position in the global civil nuclear market and paving the way for new international industrial opportunities.
First Hydrogen expands its collaboration with the University of Alberta to optimise small modular nuclear reactor design and support green hydrogen development amid the growth of artificial intelligence data centres.
The French and Belgian energy ministers have signed a declaration of intent to strengthen ties between Paris and Brussels on nuclear energy, as Belgium has abandoned its 2003 nuclear phase-out plan.
The United States Nuclear Regulatory Commission has authorised the restart of the Palisades power plant, marking a key milestone for Holtec in reintegrating this reactor into the US energy mix. —
The Genkai nuclear power plant detected the intrusion of three unidentified drones, prompting an immediate investigation by Japanese authorities into this unusual incident with potential national security implications.
KATCO, a joint venture between Orano and Kazatomprom, has started operations at the South Tortkuduk site, backed by a $190mn investment, targeting a production capacity of 4,000 tonnes per year by 2026.
Tehran agrees to host experts from the International Atomic Energy Agency in the coming weeks, excluding any visit to sensitive sites as diplomatic tensions persist with European nations and the United States.
Standard Uranium announces the results of a high-resolution electromagnetic survey at the Corvo project, confirming 29 kilometres of conductive corridors and launching the planning of an inaugural drilling programme for 2026.
NANO Nuclear Energy assembles and tests its annular induction pump prototype, marking progress for its microreactor programmes and paving the way for potential commercialisation of the technology.
Arabelle Solutions, a subsidiary of EDF, will provide turbine island equipment for the first BWRX-300 small modular reactor project in Canada, marking a milestone for the industrialisation of SMRs in North America.
Framatome will supply nuclear fuel and technical services to ENEC, strengthening the United Arab Emirates’ energy supply chain for the Barakah nuclear plant.
French start-up Stellaria secures €23mn ($25.2mn) in funding to accelerate the design of its fast neutron nuclear reactor, with first fission expected in 2029 and commercial deployment targeted for 2035.
The Bulgarian National Audit Office report highlights persistent delays and contractual irregularities in the implementation of the national repository for low- and intermediate-level radioactive waste.
Bahrain has concluded a civil nuclear agreement with the United States and formalised a commitment of $17bn in public investments in the US market, further strengthening bilateral cooperation.
Kairos Power has installed the vessel for its third test prototype in Oak Ridge, aiming to validate manufacturing methods for its future Hermes reactor supported by the US Department of Energy.
London and Prague formalise a strategic partnership to develop the nuclear sector, focusing on small modular reactors and industrial cooperation on supply chains.
Experts have broadly approved France’s Cigéo deep nuclear waste repository project, highlighting technical uncertainties that demand stronger guarantees for long-term safety.
Uzbekistan advances its nuclear project by signing a protocol with Hungary for the supply and local assembly of dry cooling systems, expanding its industrial partnerships in the region.
Polskie Elektrownie Jądrowe is asking the European Commission to review its $49bn investment to build Poland’s first nuclear power plant, a step required under the Euratom Treaty before any construction permit can be issued.