Restarting the Palisades nuclear power plant between hope and financial uncertainty

The restart of the Palisades nuclear power plant in Michigan, after a two-year shutdown, raises technical and financial concerns. The challenges encountered could influence the future of nuclear power in the United States and public confidence in the sector.

Share:

Centrale nucléaire de Palisades

The restart of the Palisades nuclear power plant in Michigan is the subject of intense debate in the US energy sector.
After a two-year shutdown, Holtec International, owner of the facility, plans to restart operation of the plant by the end of 2025.
This initiative follows a $1.52 billion conditional loan from the U.S. Department of Energy, which prompted Holtec to modify its initial decommissioning strategy.
Rising energy demand, fueled by booming sectors such as electric vehicles, artificial intelligence and cryptocurrencies, is driving this decision.

Technical challenges and inspections

However, recent inspections by the Nuclear Regulatory Commission (NRC) have highlighted significant technical problems.
A large number of steam generator tubes require further analysis or repair, which could delay the restart process.
Holtec has acknowledged the need for additional maintenance work, but has not yet provided a precise estimate of costs or additional lead times.
These uncertainties raise questions about the viability of the project, both technically and economically.
Alan Blind, former Technical Director of Palisades, has estimated that steam generator repairs could exceed $500 million and delay restart by two to three years.
This estimate highlights the financial challenges Holtec could face, despite its assurances that these contingencies had been factored into the original financial forecasts.
The current situation raises concerns about the economic feasibility of the project, especially in a context of ever-changing energy costs and investor expectations.

Criticism and concerns of experts

Industry experts also express concern about the transparency of the information provided by Holtec.
Edwin Lyman, physicist and nuclear safety expert, stresses that more in-depth details on the plant’s condition are needed before committing further public funds to the project.
He states,

“The public deserves the un-embellished truth before any more taxpayer and consumer dollars are invested in what could be a very deep money pit.”

This statement highlights the need for clear and honest communication about the risks associated with restarting the plant.
The restart of Palisades, if realized, would mark a first in the United States, where a closed nuclear power plant would be reopened to meet growing energy demand.
However, the technical and financial challenges remain considerable.
The NRC said that additional analysis, testing and repairs would be required in the coming months, which could further complicate the restart schedule.

Future prospects

The current situation at the Palisades plant raises crucial questions about the future of nuclear power in the United States.
While the federal government sees nuclear power as a key element in the fight against climate change, the technical and financial challenges associated with reopening closed plants could put the brakes on this ambition.
Industry players have to navigate a complex environment, where growing energy demand has to be balanced with safety and sustainability considerations.
Decisions taken by Holtec and regulators in the coming months will have repercussions not only for the Palisades plant, but for the US nuclear industry as a whole.
The ability to overcome technical hurdles and ensure adequate transparency will be crucial to investor and public confidence in the future of nuclear power.
The stakes are high, and the success or failure of this project could influence energy policy and investment in nuclear infrastructure nationwide.

Slovenské elektrárne has signed an agreement with Urenco for the purchase of enriched uranium for the Bohunice and Mochovce nuclear power plants, strengthening the diversification of its supply sources until the mid-2030s.
Emirates Nuclear Energy Company signs two major agreements with Hyundai Engineering & Construction and Westinghouse, strengthening its position in the global civil nuclear market and paving the way for new international industrial opportunities.
First Hydrogen expands its collaboration with the University of Alberta to optimise small modular nuclear reactor design and support green hydrogen development amid the growth of artificial intelligence data centres.
The French and Belgian energy ministers have signed a declaration of intent to strengthen ties between Paris and Brussels on nuclear energy, as Belgium has abandoned its 2003 nuclear phase-out plan.
The United States Nuclear Regulatory Commission has authorised the restart of the Palisades power plant, marking a key milestone for Holtec in reintegrating this reactor into the US energy mix. —
The Genkai nuclear power plant detected the intrusion of three unidentified drones, prompting an immediate investigation by Japanese authorities into this unusual incident with potential national security implications.
KATCO, a joint venture between Orano and Kazatomprom, has started operations at the South Tortkuduk site, backed by a $190mn investment, targeting a production capacity of 4,000 tonnes per year by 2026.
Tehran agrees to host experts from the International Atomic Energy Agency in the coming weeks, excluding any visit to sensitive sites as diplomatic tensions persist with European nations and the United States.
Standard Uranium announces the results of a high-resolution electromagnetic survey at the Corvo project, confirming 29 kilometres of conductive corridors and launching the planning of an inaugural drilling programme for 2026.
NANO Nuclear Energy assembles and tests its annular induction pump prototype, marking progress for its microreactor programmes and paving the way for potential commercialisation of the technology.
Arabelle Solutions, a subsidiary of EDF, will provide turbine island equipment for the first BWRX-300 small modular reactor project in Canada, marking a milestone for the industrialisation of SMRs in North America.
Framatome will supply nuclear fuel and technical services to ENEC, strengthening the United Arab Emirates’ energy supply chain for the Barakah nuclear plant.
French start-up Stellaria secures €23mn ($25.2mn) in funding to accelerate the design of its fast neutron nuclear reactor, with first fission expected in 2029 and commercial deployment targeted for 2035.
The Bulgarian National Audit Office report highlights persistent delays and contractual irregularities in the implementation of the national repository for low- and intermediate-level radioactive waste.
Bahrain has concluded a civil nuclear agreement with the United States and formalised a commitment of $17bn in public investments in the US market, further strengthening bilateral cooperation.
Kairos Power has installed the vessel for its third test prototype in Oak Ridge, aiming to validate manufacturing methods for its future Hermes reactor supported by the US Department of Energy.
London and Prague formalise a strategic partnership to develop the nuclear sector, focusing on small modular reactors and industrial cooperation on supply chains.
Experts have broadly approved France’s Cigéo deep nuclear waste repository project, highlighting technical uncertainties that demand stronger guarantees for long-term safety.
Uzbekistan advances its nuclear project by signing a protocol with Hungary for the supply and local assembly of dry cooling systems, expanding its industrial partnerships in the region.
Polskie Elektrownie Jądrowe is asking the European Commission to review its $49bn investment to build Poland’s first nuclear power plant, a step required under the Euratom Treaty before any construction permit can be issued.