Flamanville EPR: Restart after shutdown due to human error

After an automatic shutdown caused by a faulty configuration, the Flamanville EPR restarts and continues its ramp-up towards connection to the power grid.

Share:

Subscribe for unlimited access to all energy sector news.

Over 150 multisector articles and analyses every week.

Your 1st year at 99 £*

then 199 £/year

*renews at 199£/year, cancel anytime before renewal.

The Flamanville EPR reactor in the Manche region of France has restarted after an automatic shutdown last Wednesday.
This incident, linked to human error during post-divergence tests, triggered an automatic shutdown order for the reactor.
EDF points out that the event was not due to a hardware problem, but to a misconfiguration of the electronic control systems.
This situation, while regrettable, is commonplace during the commissioning phase of nuclear reactors, when precise procedures are essential.
The French nuclear safety authority (ASN) confirms that the shutdown was the result of a failure to comply with operating procedures.
According to Karine Herviou of the Institut de Radioprotection et de Sûreté Nucléaire (IRSN), this type of incident shows that the safety devices are working as intended, stopping the reactor when an anomaly is detected.
The reactor is currently stabilized at 0.2% power, and teams are continuing the tests required to prepare it for connection to the power grid, expected by late autumn.

Technical advances and obstacles

The Flamanville EPR project, launched over fifteen years ago, is experiencing numerous delays and budget overruns.
Initially estimated at 3.3 billion euros, the cost has now been re-evaluated at 13.2 billion euros.
Twelve years behind schedule, the project faces recurring technical challenges.
Each ramp-up stage is accompanied by a series of checks and tests to ensure the reactor’s safety and efficiency.
EDF recognizes that technical contingencies, including automatic shutdowns, may still occur before full capacity is reached.
Reactors of this scale, especially those commissioned for the first time after several decades, often face unforeseen challenges requiring real-time technical adjustments.
The ramp-up procedure, segmented into stages, enables these challenges to be managed gradually and in a controlled manner.

France’s nuclear revival strategy

The restart of the Flamanville EPR is part of a wider context of increased nuclear power generation in France.
In 2022, President Emmanuel Macron announced the construction of six new EPR2-type reactors, an optimized version of the EPR, with the possibility of eight additional reactors in the future.
The aim of this strategy is to secure the country’s energy supply, while meeting the need to renew the existing nuclear fleet.
France’s nuclear fleet, with 56 reactors in operation, requires major investment to maintain its production capacity and anticipate the closure of older reactors.
The Flamanville EPR, with its planned capacity of 1,600 MW, represents a major strategic addition in this context.
Its capacity to generate electricity for around two million households makes it a key component of this revival.

Prospects for grid integration

The Flamanville reactor moves closer to grid connection.
The first divergence, carried out last Tuesday, marks the start of a step-by-step power ramp-up process.
For the moment, the aim is to reach 25% power, the threshold required to couple the reactor to the grid by late autumn.
However, previous experience suggests that adjustments and delays are still possible.
The Flamanville EPR is the fourth reactor of its type built anywhere in the world, and the most powerful in France.
Its start-up, despite its obstacles, remains a central element of the French energy landscape, and its success or failure will influence future nuclear projects.
The coming months will be crucial in assessing the viability of this type of reactor and the adjustments needed for future projects.

enCore Energy Corp. has completed a $115 million fundraising through convertible notes maturing in 2030, strengthening its financial capacity for upcoming operations.
Vattenfall advances its nuclear project in Sweden by selecting two modular reactor suppliers, GE Vernova and Rolls-Royce SMR, for a potential installation on the Värö Peninsula.
NANO Nuclear Energy has been selected to compete in the final round of xTechSearch 9, a US Army initiative aimed at identifying high-potential dual-use technology solutions.
Aalo Atomics completes Series B funding, bringing its total to USD 136 million, to build its first modular nuclear power plant dedicated to data centers.
The Malaysian government initiates a national assessment on nuclear energy feasibility, targeting regions facing energy supply constraints and integrating international regulatory requirements.
The merger between Premier American Uranium and Nuclear Fuels reaches a key milestone following final approval of the arrangement plan by the Supreme Court of British Columbia.
TVA, Google, and Kairos Power formalize an agreement to connect an advanced reactor to the grid, supporting data center energy growth and reinforcing the U.S. nuclear industry.
The U.S. Department of Defense has signed an agreement with X-energy to develop a commercial nuclear microreactor intended to power sensitive military infrastructure.
With cash reserves multiplied sevenfold in nine months, NANO Nuclear intensifies development of its KRONOS MMR and positions itself in the Canadian and U.S. modular nuclear markets.
Equinix signed a preorder for 20 Kaleidos nuclear microreactors and a letter of intent for a power purchase agreement with ULC-Energy, reinforcing its energy supply strategy for its data centers.
The U.S. Department of Energy selects Oklo and its subsidiary Atomic Alchemy for three pilot reactor projects aiming for criticality before July 2026.
The United States Department of Energy has selected eleven companies to build experimental nuclear reactors by July 2026, under a programme aimed at meeting rising electricity demand.
The South African Minister of the Environment has approved Eskom’s authorisation to build a nuclear power plant in Duynefontein, ending appeals lodged by several environmental organisations.
An independent group calls for deep changes to speed up the approval of UK nuclear projects and cut costs linked to a system seen as too slow and complex.
Radiant has signed an agreement with the Department of the Air Force and the Defense Innovation Unit to supply a portable nuclear microreactor, marking a first in mass production for military use.
The Gravelines nuclear power plant, the largest in Western Europe, halted all production after its cooling systems were obstructed by an unexpected influx of jellyfish. EDF plans a gradual restart in the coming days.
The International Atomic Energy Agency confirmed that the tritium concentration in the 14th batch of ALPS-treated water discharged by TEPCO remains well below Japan’s operational limit.
Field studies to determine the location of Kazakhstan’s first nuclear power plant have begun near the village of Ulken, marking a key stage in a project led by Rosatom.
China’s nuclear safety authority has approved the construction of units 1 and 2 at the Jinqimen plant, authorising the start of foundation work for the first reactor.
India unveils a national plan to boost nuclear capacity to 100 GW by 2047, combining large reactors and small modules, with a strengthened regulatory framework and new public-private partnerships.

Log in to read this article

You'll also have access to a selection of our best content.

or

Go unlimited with our annual offer: 99 £ for the 1styear year, then 199 £ /year.

Consent Preferences