EDF requests ASN authorization to start up the Flamanville EPR

EDF has applied to the ASN to launch the Flamanville EPR, a complex project whose costs have quadrupled and which is twelve years behind schedule. The divergence authorization is awaited before production can begin.

Share:

EPR de Flamanville

Subscribe for unlimited access to all energy sector news.

Over 150 multisector articles and analyses every week.

Your 1st year at 99 $*

then 199 $/year

*renews at 199$/year, cancel anytime before renewal.

EDF has officially applied to the French Nuclear Safety Authority (ASN) to authorize the first divergence of the Flamanville EPR (European Pressurized Reactor), a decisive step for the start-up of this new-generation reactor.
In May 2024, the company completed the loading of 60,000 nuclear fuel rods into the reactor vessel, a process that continued with cold tests until July, followed by hot tests where the reactor pressure was raised to 155 bars and the temperature to 303 degrees.
These tests are the final stage in a project that began seventeen years ago and has been plagued by a series of technical problems, including cracks in the concrete slab and welding defects in the containment vessel.
These technical difficulties not only delayed the reactor’s commissioning by twelve years compared to the original 2012 schedule, but also quadrupled the budget, from 3.3 billion euros to 13.2 billion euros.
In 2020, the French Cour des Comptes estimated that the total cost of the project, including additional financing costs, could reach 19 billion euros.

Technical and financial challenges: Management under pressure

The Flamanville EPR, located in the French department of Manche, is set to be the fourth reactor of its type installed worldwide, and the most powerful in France, with a capacity of 1,600 MW.
This long-term project has raised numerous management and supervision challenges.
EDF claims that no changes to the schedule are currently planned for the connection to the electricity grid, also known as “coupling”, and is aiming to produce the first electrons by September 21, 2024.
When the reactor reaches full capacity, it will be able to supply around three million French households.
EDF hopes to reach full production before the end of the year, although the reactor is already scheduled to operate at 25% of capacity when it is initially commissioned.
The start-up of the Flamanville EPR is of strategic importance as France seeks to revitalize its nuclear industry.
The government has ordered six new EPR2 reactors, with an additional eight as an option, a strong sign of its determination to support this technology despite the delays and extra costs observed.

Symbolism and implications for the nuclear industry

The Flamanville project comes at a key moment in French energy policy.
The last nuclear reactors commissioned in France were Chooz in 2000 and Civaux in 2002.
The start-up of the Flamanville EPR, although initiated well before the government’s recent decision to revive nuclear power, takes on a highly symbolic dimension for the future of the industry.
EDF has the opportunity to demonstrate that the technical difficulties encountered on this project can be overcome, and to set a positive precedent for future EPR2s.
As for the ASN, it plays a key role in ensuring that the reactor complies with all safety standards before giving its go-ahead for commissioning.
This vigilance is all the more crucial given the project’s track record.
For EDF, the stakes are high: restoring confidence in its ability to manage projects of this scale, while respecting safety and cost constraints.

Impact on energy and industrial strategy

The commissioning of the Flamanville EPR will have significant implications for the French nuclear industry and for EDF, which remains wholly state-owned.
The ability to meet the deadlines and costs for this reactor will influence perceptions of the feasibility of future nuclear projects, particularly in a changing European energy market.
The evolution of this project could also serve as a benchmark for other nations considering modernizing or strengthening their nuclear capabilities.
Industry professionals are keeping a close eye on developments surrounding the Flamanville EPR.
Its commissioning could either strengthen the position of EPR technology on the international stage, or, in the event of further delays or difficulties, raise questions about the economic viability of these new-generation reactors.
The next few months will therefore be crucial for EDF and the French nuclear industry.

Nano Nuclear Energy has signed a memorandum of understanding with Dioxitek, Argentina’s only uranium supplier for nuclear fuel, to assess the development of local conversion and enrichment capacities.
Stockholm plans to restart uranium extraction by lifting the 2018 ban, aiming to secure strategic supply chains and support domestic nuclear electricity production.
The French Atomic Energy Commission has signed a letter of intent with start-up Calogena to study the installation of a 30 MW thermal small nuclear reactor at its Cadarache site.
A Guidehouse Research report anticipates strong growth in the global nuclear modular reactor market, with revenues rising from $375.8 million in 2025 to $8.1 billion in 2034.
KHNP, Doosan, POSCO and Samsung C&T join US partners to develop 5 GW of modular reactors, expand uranium enrichment and build an 11 GW energy complex in Texas.
The US Department of Energy is creating an industrial consortium to accelerate domestic enriched uranium production and reduce reliance on foreign imports ahead of the Russian supply ban in 2027.
The kamikaze drone damaged an auxiliary transformer at the Kursk plant, halving the output of its only reactor in operation, according to Rosatom and the International Atomic Energy Agency.
The four production units at the Gravelines nuclear power plant, shut down in mid-August by a massive jellyfish incursion, are back online, restoring the site’s full capacity.
enCore Energy Corp. has completed a $115 million fundraising through convertible notes maturing in 2030, strengthening its financial capacity for upcoming operations.
Vattenfall advances its nuclear project in Sweden by selecting two modular reactor suppliers, GE Vernova and Rolls-Royce SMR, for a potential installation on the Värö Peninsula.
NANO Nuclear Energy has been selected to compete in the final round of xTechSearch 9, a US Army initiative aimed at identifying high-potential dual-use technology solutions.
Aalo Atomics completes Series B funding, bringing its total to USD 136 million, to build its first modular nuclear power plant dedicated to data centers.
The Malaysian government initiates a national assessment on nuclear energy feasibility, targeting regions facing energy supply constraints and integrating international regulatory requirements.
The merger between Premier American Uranium and Nuclear Fuels reaches a key milestone following final approval of the arrangement plan by the Supreme Court of British Columbia.
TVA, Google, and Kairos Power formalize an agreement to connect an advanced reactor to the grid, supporting data center energy growth and reinforcing the U.S. nuclear industry.
The U.S. Department of Defense has signed an agreement with X-energy to develop a commercial nuclear microreactor intended to power sensitive military infrastructure.
With cash reserves multiplied sevenfold in nine months, NANO Nuclear intensifies development of its KRONOS MMR and positions itself in the Canadian and U.S. modular nuclear markets.
Equinix signed a preorder for 20 Kaleidos nuclear microreactors and a letter of intent for a power purchase agreement with ULC-Energy, reinforcing its energy supply strategy for its data centers.
The U.S. Department of Energy selects Oklo and its subsidiary Atomic Alchemy for three pilot reactor projects aiming for criticality before July 2026.
The United States Department of Energy has selected eleven companies to build experimental nuclear reactors by July 2026, under a programme aimed at meeting rising electricity demand.

Log in to read this article

You'll also have access to a selection of our best content.

or

Go unlimited with our annual offer: $99 for the 1styear year, then $ 199/year.