EDF requests ASN authorization to start up the Flamanville EPR

EDF has applied to the ASN to launch the Flamanville EPR, a complex project whose costs have quadrupled and which is twelve years behind schedule. The divergence authorization is awaited before production can begin.
EPR de Flamanville

Partagez:

EDF has officially applied to the French Nuclear Safety Authority (ASN) to authorize the first divergence of the Flamanville EPR (European Pressurized Reactor), a decisive step for the start-up of this new-generation reactor.
In May 2024, the company completed the loading of 60,000 nuclear fuel rods into the reactor vessel, a process that continued with cold tests until July, followed by hot tests where the reactor pressure was raised to 155 bars and the temperature to 303 degrees.
These tests are the final stage in a project that began seventeen years ago and has been plagued by a series of technical problems, including cracks in the concrete slab and welding defects in the containment vessel.
These technical difficulties not only delayed the reactor’s commissioning by twelve years compared to the original 2012 schedule, but also quadrupled the budget, from 3.3 billion euros to 13.2 billion euros.
In 2020, the French Cour des Comptes estimated that the total cost of the project, including additional financing costs, could reach 19 billion euros.

Technical and financial challenges: Management under pressure

The Flamanville EPR, located in the French department of Manche, is set to be the fourth reactor of its type installed worldwide, and the most powerful in France, with a capacity of 1,600 MW.
This long-term project has raised numerous management and supervision challenges.
EDF claims that no changes to the schedule are currently planned for the connection to the electricity grid, also known as “coupling”, and is aiming to produce the first electrons by September 21, 2024.
When the reactor reaches full capacity, it will be able to supply around three million French households.
EDF hopes to reach full production before the end of the year, although the reactor is already scheduled to operate at 25% of capacity when it is initially commissioned.
The start-up of the Flamanville EPR is of strategic importance as France seeks to revitalize its nuclear industry.
The government has ordered six new EPR2 reactors, with an additional eight as an option, a strong sign of its determination to support this technology despite the delays and extra costs observed.

Symbolism and implications for the nuclear industry

The Flamanville project comes at a key moment in French energy policy.
The last nuclear reactors commissioned in France were Chooz in 2000 and Civaux in 2002.
The start-up of the Flamanville EPR, although initiated well before the government’s recent decision to revive nuclear power, takes on a highly symbolic dimension for the future of the industry.
EDF has the opportunity to demonstrate that the technical difficulties encountered on this project can be overcome, and to set a positive precedent for future EPR2s.
As for the ASN, it plays a key role in ensuring that the reactor complies with all safety standards before giving its go-ahead for commissioning.
This vigilance is all the more crucial given the project’s track record.
For EDF, the stakes are high: restoring confidence in its ability to manage projects of this scale, while respecting safety and cost constraints.

Impact on energy and industrial strategy

The commissioning of the Flamanville EPR will have significant implications for the French nuclear industry and for EDF, which remains wholly state-owned.
The ability to meet the deadlines and costs for this reactor will influence perceptions of the feasibility of future nuclear projects, particularly in a changing European energy market.
The evolution of this project could also serve as a benchmark for other nations considering modernizing or strengthening their nuclear capabilities.
Industry professionals are keeping a close eye on developments surrounding the Flamanville EPR.
Its commissioning could either strengthen the position of EPR technology on the international stage, or, in the event of further delays or difficulties, raise questions about the economic viability of these new-generation reactors.
The next few months will therefore be crucial for EDF and the French nuclear industry.

After several decades without funding nuclear projects, the World Bank has formed a strategic partnership with the IAEA to provide technical and financial support to countries integrating nuclear energy into their energy strategies.
South Korea's Nuclear Safety and Security Commission officially validates the decommissioning of reactor number one at the Kori plant, initiating an unprecedented project for the national industry scheduled to last until 2037.
Uranium producer enCore Energy surpasses three thousand pounds per day at its Alta Mesa ISR complex and sees three new Texas laws as a strong signal for faster nuclear production permits.
The International Atomic Energy Agency expresses concerns over Iran’s enriched uranium stockpiles following the abrupt suspension of inspections at key sites disrupted by recent attacks whose consequences remain uncertain.
NPCIL has announced an extension until September 30 for industrial proposals concerning Bharat Small Reactors (BSR), following increased interest from the Indian private sector.
A regional court has upheld the award of two new reactors in the Czech Republic to Korea Hydro & Nuclear Power, dismissing Électricité de France’s challenge to the €16bn contract in a decisive step for the national energy programme.
Facing rising temperatures, EDF anticipates cuts in nuclear production starting early July, primarily due to thermal constraints on rivers used for cooling the power plants.
The preliminary agreement launches planning and site assessment for a tailored AP1000 reactor, following two years of feasibility study, and enlists Westinghouse and Hyundai to support Fortum’s regional nuclear expansion.
Donald Trump's unprecedented decision to dismiss Christopher Hanson, a member of the NRC, provokes outrage among former federal officials and raises concerns over the regulatory independence of the U.S. nuclear sector.
Uranium Energy Corp strengthens its position in Anfield Energy Inc., now holding approximately 32.4% of the company’s shares following an investment of CAD19.55mn ($14.82mn), significantly expanding its strategic influence in the uranium market.
New York State plans an advanced nuclear power plant with a 1-gigawatt capacity to meet long-term energy and economic goals, involving significant investment to enhance regional energy independence.
Niger announces its intention to nationalize SOMAÏR, a mining company jointly owned with Orano, provoking strong opposition from the French company and paving the way for further international legal tensions.
Russia strengthens its economic presence in Mali with new agreements, notably in nuclear energy and gold refining, consolidating strategic cooperation within a rapidly evolving geopolitical context.
The US government grants a fourth payment of $100.45 mn to Holtec International to restart the Palisades Nuclear Plant, pending regulatory approval, marking an unprecedented event in the United States.
EDF announces a major agreement with Apollo to raise up to £4.5 billion via bonds to finance the British nuclear project Hinkley Point C, whose costs continue to rise significantly.
The Élysée proposes Anne-Isabelle Étienvre, current Director of Fundamental Research at the CEA, as General Administrator to replace François Jacq, recently appointed President of CNES.
Greek Prime Minister Kyriakos Mitsotakis has announced his country's interest in small modular nuclear reactors to meet national energy challenges and decarbonize the maritime sector within the next fifteen years.
TerraPower, an American nuclear company, secures $650 million funding from investors, including NVIDIA, to develop its Natrium modular reactors in the United States and internationally.
EDF and the French state finalize a €70 billion financing plan for six EPR2 nuclear reactors, including a specific territorial coordination framework in Gravelines led by Michel Marbaix, awaiting European approval by 2026.
Maire S.p.A and Newcleo form strategic partnership to industrialise the development of 200 MW modular nuclear power plants, via a joint venture majority-owned by Nextchem.