Flamanville EPR reactor reconnected to grid two days ahead of schedule

EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.

Share:

Comprehensive energy news coverage, updated nonstop

Annual subscription

8.25£/month*

*billed annually at 99£/year for the first year then 149,00£/year ​

Unlimited access • Archives included • Professional invoice

OTHER ACCESS OPTIONS

Monthly subscription

Unlimited access • Archives included

5.2£/month*
then 14.90£ per month thereafter

FREE ACCOUNT

3 articles offered per month

FREE

*Prices are excluding VAT, which may vary depending on your location or professional status

Since 2021: 35,000 articles • 150+ analyses per week

The European Pressurised Reactor (EPR) located in Flamanville, Manche, was reconnected to the French power grid on Saturday 19 April at 8:30 p.m., according to information released by Électricité de France (EDF) the following day. This step marks progress in the power-up phase of the reactor, which had been offline since 15 February due to unplanned maintenance operations. The early return to the grid follows several successive delays related to safety inspections.

The reactor, which has a maximum output capacity of 1,620 megawatts, resumed operation at a limited level of 90 megawatts. EDF confirmed that power variation tests are scheduled until the following Wednesday. This gradual increase in output is part of the initial startup process for a third-generation nuclear reactor, which spans several months to comply with safety protocols. Full power output, equating to 100% of nominal capacity, remains scheduled for summer 2025.

Extended maintenance on cooling system components

The reactor’s shutdown, initially intended as temporary, was extended twice in February. EDF carried out work on a cooling system using seawater, on the turbo-alternator unit, and on other elements considered necessary to ensure safe progression through the power-up sequence. The group also noted that further adjustments had been made to the bearings guiding the turbine rotors.

These technical operations are part of the standard procedures for a new-generation reactor, particularly during the system validation phase. EDF highlighted that more than 1,500 safety criteria are assessed during the initial startup, which can require several planned stoppages or unexpected adjustments.

A restart following multiple delays since late March

The reactor’s recommissioning was originally scheduled for 30 March but was postponed several times. The latest timeline indicated a return to the grid on Monday 21 April. This recent progress in the Flamanville EPR project comes as EDF aims to stabilise availability across its national nuclear fleet, comprising 57 reactors.

The Flamanville reactor was connected to the grid for the first time on 21 December 2024, twelve years behind the original schedule. Since then, it has undergone two scheduled stoppages. EDF considers this gradual load increase a standard procedure for a first startup, requiring in-depth testing at each operational stage.

PGE acquires ZE PAK's stake in the joint venture responsible for developing Poland’s second nuclear site, consolidating a strategic asset within its energy portfolio.
Amazon unveils new visuals of its upcoming nuclear site, marking a key step in its partnership with X-energy to deploy up to 960 MW of modular nuclear capacity in Washington state.
Canadian uranium producer NexGen Energy has completed a A$1bn ($639mn) equity raise split between North American and Australian markets to support the development of its Rook I project.
Tokyo Electric Power Company Holdings is examining the permanent closure of units 1 and 2 at the Kashiwazaki-Kariwa nuclear power plant, the oldest at the site, while continuing efforts to restart unit 6.
The formal expiration of the 2015 nuclear deal with Iran comes as international sanctions have already been reinstated and diplomatic negotiations remain stalled.
Oklo, newcleo and Blykalla partner to develop advanced nuclear fuel infrastructure in the United States, backed by a planned $2bn investment.
enCore Energy has identified three new uranium roll fronts at its Alta Mesa project, with ongoing drilling aimed at defining their extent and accelerating development work.
California-based Radiant will build its first microreactor production facility in Oak Ridge, on a former Manhattan Project site, with production targeted at 50 units per year by 2028.
EDF restarted the Flamanville EPR reactor after repairing non-compliant valves, delaying the target of reaching full power output of 1,620 MW until the end of autumn.
Nano Nuclear and the University of Illinois will begin drilling operations for the KRONOS MMR™ reactor on October 24, marking a key step toward commercialisation of the nuclear project on the Urbana-Champaign campus.
Natura Resources is finalising construction of the MSR-1, an advanced liquid-fuel nuclear reactor, with a planned launch in 2026 on the Abilene Christian University campus.
JPMorganChase commits $10bn in direct investments as part of a $1.5tn plan to boost energy independence and strategic technologies, including next-generation nuclear power.
A roadmap under development aims to establish regulatory and technical foundations for the deployment of small modular reactors, with the goal of strengthening national energy security and attracting private capital.
EDF adjusts its 2025 nuclear production forecast to between 365 and 375 TWh, supported by the performance of its industrial programme START 2025 focused on maintenance efficiency.
The United Nations nuclear agency is urging Ukraine and Russia to establish a local ceasefire to repair damaged power lines at the Zaporizhzhia plant, which remains on alert after losing all external power supply.
Deep Isolation is calling on First Mover States to incorporate radioactive waste management into their joint strategy to ensure the industrial viability of new nuclear reactors.
Canada’s nuclear regulator has approved the launch of a new building that will store used steam generators from Bruce Power's refurbishment programme.
Costain has been selected to upgrade essential utilities at the Sellafield nuclear site under a contract worth up to £1bn over fifteen years.
A 5,000-megawatt nuclear programme will be launched by the South African government with NECSA to support national electricity supply and reduce power cuts.
Canada’s IsoEnergy will acquire Australia’s Toro Energy for AUD75mn ($49mn), creating a diversified uranium production platform with assets across Australia, Canada and the United States.

All the latest energy news, all the time

Annual subscription

8.25£/month*

*billed annually at 99£/year for the first year then 149,00£/year ​

Unlimited access - Archives included - Pro invoice

Monthly subscription

Unlimited access • Archives included

5.2£/month*
then 14.90£ per month thereafter

*Prices shown are exclusive of VAT, which may vary according to your location or professional status.

Since 2021: 30,000 articles - +150 analyses/week.