Flamanville EPR reactor reconnected to grid two days ahead of schedule

EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.

Share:

The European Pressurised Reactor (EPR) located in Flamanville, Manche, was reconnected to the French power grid on Saturday 19 April at 8:30 p.m., according to information released by Électricité de France (EDF) the following day. This step marks progress in the power-up phase of the reactor, which had been offline since 15 February due to unplanned maintenance operations. The early return to the grid follows several successive delays related to safety inspections.

The reactor, which has a maximum output capacity of 1,620 megawatts, resumed operation at a limited level of 90 megawatts. EDF confirmed that power variation tests are scheduled until the following Wednesday. This gradual increase in output is part of the initial startup process for a third-generation nuclear reactor, which spans several months to comply with safety protocols. Full power output, equating to 100% of nominal capacity, remains scheduled for summer 2025.

Extended maintenance on cooling system components

The reactor’s shutdown, initially intended as temporary, was extended twice in February. EDF carried out work on a cooling system using seawater, on the turbo-alternator unit, and on other elements considered necessary to ensure safe progression through the power-up sequence. The group also noted that further adjustments had been made to the bearings guiding the turbine rotors.

These technical operations are part of the standard procedures for a new-generation reactor, particularly during the system validation phase. EDF highlighted that more than 1,500 safety criteria are assessed during the initial startup, which can require several planned stoppages or unexpected adjustments.

A restart following multiple delays since late March

The reactor’s recommissioning was originally scheduled for 30 March but was postponed several times. The latest timeline indicated a return to the grid on Monday 21 April. This recent progress in the Flamanville EPR project comes as EDF aims to stabilise availability across its national nuclear fleet, comprising 57 reactors.

The Flamanville reactor was connected to the grid for the first time on 21 December 2024, twelve years behind the original schedule. Since then, it has undergone two scheduled stoppages. EDF considers this gradual load increase a standard procedure for a first startup, requiring in-depth testing at each operational stage.

Hunatom announces a strategic alliance with Synthos Green Energy to introduce US small modular reactor technology, strengthening energy ties between Hungary, Poland and the United States.
A joint feasibility study project on Korean i-SMR modular reactors has just been launched for a future nuclear site at the border of the Aure and Heim municipalities, aiming for significant regional industrial impact.
Unit 3 of the Tomari nuclear power plant takes a major step towards restart after its safety equipment was validated by the Japanese regulator.
The Russian Minister of Energy announces strengthened cooperation in uranium and civil nuclear energy in Niger, reinforcing Russia's economic presence in a key sector following the withdrawal of several Western players.
Last Energy reaches a key regulatory step for its PWR-20 microreactor project in Llynfi, advancing towards the objective of securing a site licence by December 2027 from British authorities.
Slovenské elektrárne has signed an agreement with Urenco for the purchase of enriched uranium for the Bohunice and Mochovce nuclear power plants, strengthening the diversification of its supply sources until the mid-2030s.
Emirates Nuclear Energy Company signs two major agreements with Hyundai Engineering & Construction and Westinghouse, strengthening its position in the global civil nuclear market and paving the way for new international industrial opportunities.
First Hydrogen expands its collaboration with the University of Alberta to optimise small modular nuclear reactor design and support green hydrogen development amid the growth of artificial intelligence data centres.
The French and Belgian energy ministers have signed a declaration of intent to strengthen ties between Paris and Brussels on nuclear energy, as Belgium has abandoned its 2003 nuclear phase-out plan.
The United States Nuclear Regulatory Commission has authorised the restart of the Palisades power plant, marking a key milestone for Holtec in reintegrating this reactor into the US energy mix. —
The Genkai nuclear power plant detected the intrusion of three unidentified drones, prompting an immediate investigation by Japanese authorities into this unusual incident with potential national security implications.
KATCO, a joint venture between Orano and Kazatomprom, has started operations at the South Tortkuduk site, backed by a $190mn investment, targeting a production capacity of 4,000 tonnes per year by 2026.
Tehran agrees to host experts from the International Atomic Energy Agency in the coming weeks, excluding any visit to sensitive sites as diplomatic tensions persist with European nations and the United States.
Standard Uranium announces the results of a high-resolution electromagnetic survey at the Corvo project, confirming 29 kilometres of conductive corridors and launching the planning of an inaugural drilling programme for 2026.
NANO Nuclear Energy assembles and tests its annular induction pump prototype, marking progress for its microreactor programmes and paving the way for potential commercialisation of the technology.
Hungary reaffirms its intent to double the capacity of its Paks nuclear power plant in partnership with Rosatom, with concrete works expected to begin in the autumn.
Arabelle Solutions, a subsidiary of EDF, will provide turbine island equipment for the first BWRX-300 small modular reactor project in Canada, marking a milestone for the industrialisation of SMRs in North America.
Framatome will supply nuclear fuel and technical services to ENEC, strengthening the United Arab Emirates’ energy supply chain for the Barakah nuclear plant.
French start-up Stellaria secures €23mn ($25.2mn) in funding to accelerate the design of its fast neutron nuclear reactor, with first fission expected in 2029 and commercial deployment targeted for 2035.
The Bulgarian National Audit Office report highlights persistent delays and contractual irregularities in the implementation of the national repository for low- and intermediate-level radioactive waste.