EDF requests ASN authorization to start up the Flamanville EPR

EDF has applied to the ASN to launch the Flamanville EPR, a complex project whose costs have quadrupled and which is twelve years behind schedule. The divergence authorization is awaited before production can begin.

Share:

EPR de Flamanville

Comprehensive energy news coverage, updated nonstop

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access • Archives included • Professional invoice

OTHER ACCESS OPTIONS

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

FREE ACCOUNT

3 articles offered per month

FREE

*Prices are excluding VAT, which may vary depending on your location or professional status

Since 2021: 35,000 articles • 150+ analyses per week

EDF has officially applied to the French Nuclear Safety Authority (ASN) to authorize the first divergence of the Flamanville EPR (European Pressurized Reactor), a decisive step for the start-up of this new-generation reactor.
In May 2024, the company completed the loading of 60,000 nuclear fuel rods into the reactor vessel, a process that continued with cold tests until July, followed by hot tests where the reactor pressure was raised to 155 bars and the temperature to 303 degrees.
These tests are the final stage in a project that began seventeen years ago and has been plagued by a series of technical problems, including cracks in the concrete slab and welding defects in the containment vessel.
These technical difficulties not only delayed the reactor’s commissioning by twelve years compared to the original 2012 schedule, but also quadrupled the budget, from 3.3 billion euros to 13.2 billion euros.
In 2020, the French Cour des Comptes estimated that the total cost of the project, including additional financing costs, could reach 19 billion euros.

Technical and financial challenges: Management under pressure

The Flamanville EPR, located in the French department of Manche, is set to be the fourth reactor of its type installed worldwide, and the most powerful in France, with a capacity of 1,600 MW.
This long-term project has raised numerous management and supervision challenges.
EDF claims that no changes to the schedule are currently planned for the connection to the electricity grid, also known as “coupling”, and is aiming to produce the first electrons by September 21, 2024.
When the reactor reaches full capacity, it will be able to supply around three million French households.
EDF hopes to reach full production before the end of the year, although the reactor is already scheduled to operate at 25% of capacity when it is initially commissioned.
The start-up of the Flamanville EPR is of strategic importance as France seeks to revitalize its nuclear industry.
The government has ordered six new EPR2 reactors, with an additional eight as an option, a strong sign of its determination to support this technology despite the delays and extra costs observed.

Symbolism and implications for the nuclear industry

The Flamanville project comes at a key moment in French energy policy.
The last nuclear reactors commissioned in France were Chooz in 2000 and Civaux in 2002.
The start-up of the Flamanville EPR, although initiated well before the government’s recent decision to revive nuclear power, takes on a highly symbolic dimension for the future of the industry.
EDF has the opportunity to demonstrate that the technical difficulties encountered on this project can be overcome, and to set a positive precedent for future EPR2s.
As for the ASN, it plays a key role in ensuring that the reactor complies with all safety standards before giving its go-ahead for commissioning.
This vigilance is all the more crucial given the project’s track record.
For EDF, the stakes are high: restoring confidence in its ability to manage projects of this scale, while respecting safety and cost constraints.

Impact on energy and industrial strategy

The commissioning of the Flamanville EPR will have significant implications for the French nuclear industry and for EDF, which remains wholly state-owned.
The ability to meet the deadlines and costs for this reactor will influence perceptions of the feasibility of future nuclear projects, particularly in a changing European energy market.
The evolution of this project could also serve as a benchmark for other nations considering modernizing or strengthening their nuclear capabilities.
Industry professionals are keeping a close eye on developments surrounding the Flamanville EPR.
Its commissioning could either strengthen the position of EPR technology on the international stage, or, in the event of further delays or difficulties, raise questions about the economic viability of these new-generation reactors.
The next few months will therefore be crucial for EDF and the French nuclear industry.

Work has begun at the Bailong and Lufeng sites with concrete poured for the nuclear islands, marking the start of construction for two CAP1000 reactors.
French group Orano receives USD900mn in public support to establish a new uranium enrichment facility in Tennessee, as part of a broader US nuclear sector revival plan.
Japan’s nuclear restart effort stalls after Chubu Electric acknowledged a possibly flawed seismic risk estimate at its Hamaoka facility under regulatory review.
Russia has connected its first 1,250 MW VVER-TOI reactor at the Kursk II nuclear power plant to the grid, signalling a key step toward full commissioning by 2034.
Chubu Electric acknowledged a methodological discrepancy in the seismic evaluation of two nuclear reactors, a situation that could weigh on the restart of nuclear operations in Japan.
Denison Mines is set to commit CAD600mn ($437mn) to build Phoenix, the first large-scale uranium mine developed in Canada in over a decade, with production expected by mid-2028.
A memorandum of understanding between four companies opens the way for industrial development around compact nuclear reactors, integrating hydrogen production, synthetic fuels, and digital infrastructure.
The Idaho Advanced Energy Consortium secured approval for its five strategic projects, now competing for $75mn in funding under the US Tech Hub programme.
Duke Energy has filed a permit application to assess the feasibility of a nuclear reactor in Stokes County on an existing power generation site, without committing to immediate construction.
The South Korean nuclear regulator has approved the launch of the 1,400-megawatt Saeul 3 reactor, beginning with a six-month pilot phase before full commercial operation.
Ankara confirmed new Russian funding for the Akkuyu project, Turkey’s first nuclear site, strengthening its energy ties with Moscow and advancing its domestic nuclear ambitions.
Niger’s military regime disputes theft allegations by French prosecutors after uranium stock vanished from a nationalised site previously operated by Orano.
Rosatom successfully completed a series of tests on its high-temperature gas-cooled reactor fuel, validating its performance at up to 1,700 °C under prolonged irradiation conditions.
Videberg Kraft AB becomes the first company to request government support to build two new reactors at the Ringhals site, under the national nuclear investment framework adopted in 2025.
The European Commission opens an in-depth investigation into Prague's public funding of a major nuclear project, which could reach €30bn ($32.88bn), with guaranteed revenues over forty years.
Niigata's assembly officially backs the restart of the Kashiwazaki-Kariwa site, marking a key step in Japan’s return to nuclear energy following the 2011 Fukushima disaster.
The Japanese government plans to fund up to 30% of loans required for nuclear projects, aiming to accelerate reactor restarts and double the share of nuclear energy in its energy mix by 2040.
French nuclear reactor developer Newcleo has submitted its lead-cooled small modular reactor design to Euratom, initiating the first regulatory phase to integrate nuclear non-proliferation safeguards at the European level.
French state utility EDF has increased the maximum estimated cost for building six new nuclear reactors to €72.8 billion ($85.29 billion), representing a 40% rise over the original figure.
US-based Holtec has signed a memorandum of understanding with Hungary’s energy group MVM to assess the deployment of its SMR-300 technology, strengthening bilateral nuclear cooperation and opening prospects for a new market in Central Europe.

All the latest energy news, all the time

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access - Archives included - Pro invoice

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

*Prices shown are exclusive of VAT, which may vary according to your location or professional status.

Since 2021: 30,000 articles - +150 analyses/week.