EDF postpones connection of Flamanville EPR by three months

EDF announces a further delay to the connection of the Flamanville EPR to the electricity grid. Start-up has been pushed back to late autumn 2024, adding to a long series of delays in this strategic nuclear project.

Share:

Comprehensive energy news coverage, updated nonstop

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access • Archives included • Professional invoice

OTHER ACCESS OPTIONS

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

FREE ACCOUNT

3 articles offered per month

FREE

*Prices are excluding VAT, which may vary depending on your location or professional status

Since 2021: 35,000 articles • 150+ analyses per week

EDF reports that the Flamanville EPR will not be connected to the electricity grid until late autumn 2024, three months later than planned.
The French nuclear safety authority (ASN) has given the go-ahead to start producing the first electrons, but the connection process, or “coupling”, still requires testing to reach an initial power level of 25%.
This latest setback comes on top of a twelve-year delay to the original schedule.
Divergence operations, which mark the start of controlled nuclear reactions, are scheduled for this week.
Régis Clément, Deputy Director of EDF’s Nuclear Generation Division, says this phase will take around ten hours.
He also stresses that the reactor will be ramped up in stages, without providing a precise date for reaching full capacity.

Technical problems and contingency management

The delays are attributed to various technical problems encountered at the Flamanville site.
On-site teams had to carry out additional operations during the summer due to unforeseen circumstances, thus delaying start-up.
These complications raise questions about risk management and cost control for this type of nuclear project.
The site has already been marked by construction anomalies, such as cracks in the concrete and welding defects, which have added considerably to the final bill.
Initially estimated at 3.3 billion euros, the cost of the Flamanville EPR has now risen to 13.2 billion euros.
The Cour des Comptes (French National Audit Office) had estimated it at 19 billion euros by 2020, taking into account additional financing costs.
These budget overruns reflect the complex challenges involved in implementing major nuclear projects in France.

Revision of nuclear production for 2024

Despite delays to the EPR, EDF has revised upwards its nuclear production forecast for 2024, now estimated at between 340 and 360 TWh.
This revision is due to the better performance of the other reactors in service, which are operating beyond initial expectations.
Optimized management of unit shutdowns and maintenance work, particularly concerning stress corrosion, contributed to this increase.
The summer weather, with no major events, also contributed to these results.
This revision does not take into account the potential contribution of the Flamanville EPR, whose contribution to the grid could represent an additional asset if the reactor is operational by the end of the year.
However, EDF remains cautious about the ramp-up of the EPR, stressing that each stage is conditional on successful testing and regulatory approvals.

Strategic context and industrial implications

The Flamanville EPR plays a key role in France’s nuclear strategy, particularly with the government’s commitment to revitalizing the industry.
President Emmanuel Macron has announced an order for six EPR2 reactors, with a further eight as options, to boost nuclear power generation.
Nevertheless, the difficulties encountered at Flamanville, both in terms of delays and cost overruns, are calling into question the planning and management of future similar projects.
The next stages of the project will be crucial for EDF and its partners.
The connection of the Flamanville EPR to the grid is expected to be an indicator of the Group’s ability to complete complex projects on time and on budget.
The success or failure of this project will influence future decisions, both for EDF and for the public authorities in charge of energy policy.

NextEra Energy announces an agreement with Google to restart a nuclear plant in Iowa, with operations expected to resume as early as 2029 and full site ownership secured.
The environmental review of TerraPower’s Natrium project in Wyoming has been completed, paving the way for a construction permit for this advanced nuclear reactor.
Santee Cooper has selected Brookfield Asset Management to lead a feasibility study aimed at completing two unfinished AP1000 reactors, without relying on public funds or raising consumer rates.
Endesa, Iberdrola and Naturgy have officially requested the Spanish government to delay the closure of the Almaraz nuclear power plant, originally scheduled for 2028, reigniting the debate on nuclear power's role in the national energy mix.
The reactor vessel for Unit 1 at Egypt’s El Dabaa nuclear plant has been delivered following a 20-day maritime transport from Saint Petersburg, marking a critical milestone in the country’s energy project.
Ontario Power Generation secures CAD3bn ($2.1bn) in public equity financing to construct four modular reactors at Darlington, aiming to ease private sector entry into next-generation nuclear infrastructure.
French developer Newcleo launches a joint venture with Nextchem through a EUR70 mn contract to design the conventional island of its upcoming 200 MW modular nuclear reactors.
NANO Nuclear strengthens its North American strategy by acquiring Global First Power in Canada, securing regulatory rights for its KRONOS MMR™ project at Chalk River.
South Korea becomes the first country to submit a safeguards technical report to the IAEA for a small modular reactor, setting a precedent for early integration of non-proliferation requirements in nuclear design.
The Environmental Authority criticises the lack of key data on health risks, chemical discharges and construction safety for EDF's two upcoming EPR2 reactors in Seine-Maritime.
Brazil and China have concluded a three-year agreement to secure access to essential radioisotopes for the medical, industrial and scientific sectors, with no financial exchange between the parties.
US-based developer Last Energy will deploy its first domestic microreactor at Texas A&M-RELLIS, marking a strategic step in the advanced modular reactor race.
PGE acquires ZE PAK's stake in the joint venture responsible for developing Poland’s second nuclear site, consolidating a strategic asset within its energy portfolio.
Amazon unveils new visuals of its upcoming nuclear site, marking a key step in its partnership with X-energy to deploy up to 960 MW of modular nuclear capacity in Washington state.
Canadian uranium producer NexGen Energy has completed a A$1bn ($639mn) equity raise split between North American and Australian markets to support the development of its Rook I project.
Tokyo Electric Power Company Holdings is examining the permanent closure of units 1 and 2 at the Kashiwazaki-Kariwa nuclear power plant, the oldest at the site, while continuing efforts to restart unit 6.
The formal expiration of the 2015 nuclear deal with Iran comes as international sanctions have already been reinstated and diplomatic negotiations remain stalled.
Oklo, newcleo and Blykalla partner to develop advanced nuclear fuel infrastructure in the United States, backed by a planned $2bn investment.
enCore Energy has identified three new uranium roll fronts at its Alta Mesa project, with ongoing drilling aimed at defining their extent and accelerating development work.
California-based Radiant will build its first microreactor production facility in Oak Ridge, on a former Manhattan Project site, with production targeted at 50 units per year by 2028.

All the latest energy news, all the time

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access - Archives included - Pro invoice

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

*Prices shown are exclusive of VAT, which may vary according to your location or professional status.

Since 2021: 30,000 articles - +150 analyses/week.