EDF postpones connection of Flamanville EPR by three months

EDF announces a further delay to the connection of the Flamanville EPR to the electricity grid. Start-up has been pushed back to late autumn 2024, adding to a long series of delays in this strategic nuclear project.

Share:

EDF reports that the Flamanville EPR will not be connected to the electricity grid until late autumn 2024, three months later than planned.
The French nuclear safety authority (ASN) has given the go-ahead to start producing the first electrons, but the connection process, or “coupling”, still requires testing to reach an initial power level of 25%.
This latest setback comes on top of a twelve-year delay to the original schedule.
Divergence operations, which mark the start of controlled nuclear reactions, are scheduled for this week.
Régis Clément, Deputy Director of EDF’s Nuclear Generation Division, says this phase will take around ten hours.
He also stresses that the reactor will be ramped up in stages, without providing a precise date for reaching full capacity.

Technical problems and contingency management

The delays are attributed to various technical problems encountered at the Flamanville site.
On-site teams had to carry out additional operations during the summer due to unforeseen circumstances, thus delaying start-up.
These complications raise questions about risk management and cost control for this type of nuclear project.
The site has already been marked by construction anomalies, such as cracks in the concrete and welding defects, which have added considerably to the final bill.
Initially estimated at 3.3 billion euros, the cost of the Flamanville EPR has now risen to 13.2 billion euros.
The Cour des Comptes (French National Audit Office) had estimated it at 19 billion euros by 2020, taking into account additional financing costs.
These budget overruns reflect the complex challenges involved in implementing major nuclear projects in France.

Revision of nuclear production for 2024

Despite delays to the EPR, EDF has revised upwards its nuclear production forecast for 2024, now estimated at between 340 and 360 TWh.
This revision is due to the better performance of the other reactors in service, which are operating beyond initial expectations.
Optimized management of unit shutdowns and maintenance work, particularly concerning stress corrosion, contributed to this increase.
The summer weather, with no major events, also contributed to these results.
This revision does not take into account the potential contribution of the Flamanville EPR, whose contribution to the grid could represent an additional asset if the reactor is operational by the end of the year.
However, EDF remains cautious about the ramp-up of the EPR, stressing that each stage is conditional on successful testing and regulatory approvals.

Strategic context and industrial implications

The Flamanville EPR plays a key role in France’s nuclear strategy, particularly with the government’s commitment to revitalizing the industry.
President Emmanuel Macron has announced an order for six EPR2 reactors, with a further eight as options, to boost nuclear power generation.
Nevertheless, the difficulties encountered at Flamanville, both in terms of delays and cost overruns, are calling into question the planning and management of future similar projects.
The next stages of the project will be crucial for EDF and its partners.
The connection of the Flamanville EPR to the grid is expected to be an indicator of the Group’s ability to complete complex projects on time and on budget.
The success or failure of this project will influence future decisions, both for EDF and for the public authorities in charge of energy policy.

Energy Exploration Technologies acquires Daytona Lithium, an Australian subsidiary of Pantera Lithium, for AUD40mn ($27mn), bringing its strategic lithium basin footprint in Smackover, USA to nearly 50,000 acres.
The Canadian Nuclear Safety Commission has identified no major barriers to licensing the ARC-100 reactor, announces ARC Clean Technology.
SE Ignalina, the Lithuanian nuclear operator, has signed a memorandum of understanding with French firm Newcleo to explore the integration of small modular reactors (SMRs) using lead-cooled fast reactor (LFR) technology in Lithuania.
Egyptian President Abdel Fattah al-Sisi oversaw the signing of new agreements for the construction of the El Dabaa nuclear power plant, thus strengthening the strategic cooperation between Egypt and Russia.
Vistra Corp receives green light to extend Perry nuclear plant operations in Ohio by 20 years, securing regional electricity supply until 2046 and ensuring operational continuity for all its nuclear reactors in the United States.
EDF will hold a 12.5% stake in the Sizewell C nuclear project in the UK, a €1.3 billion investment announced during Emmanuel Macron’s official visit to London, confirming the strategic nuclear energy alignment between the two countries.
The French Cigéo project, designed to bury the most hazardous radioactive waste deep underground, obtains a crucial technical validation before its final authorization, expected by the end of 2027.
EDF confirms the continuation of its industrial project in Fessenheim for recycling very low-level radioactive metals, a first in France requiring specific regulatory authorizations, following a public debate concluded last February.
NANO Nuclear Energy Inc. formalizes its collaboration with UrAmerica Ltd. to strengthen Argentina’s uranium supply, aiming to secure future nuclear fuel supply chains for the U.S. market.
American companies SHINE Technologies and Standard Nuclear partner to recycle uranium and plutonium, supplying advanced fuel to the nuclear reactor sector and enhancing the national energy security of the United States.
The American Bureau of Shipping and two nuclear sector companies are studying the potential deployment of floating nuclear power plants to meet the energy needs of island and coastal regions in the Mediterranean, notably via electricity and desalination.
Lithuania establishes a working group tasked with assessing the feasibility of modular nuclear reactors to meet electricity demand estimated at 74 TWh by 2050.
Framatome has secured two significant contracts from Electrabel covering modernisation and technical support for the Tihange 3 and Doel 4 nuclear reactors, as part of their extension agreed upon between Engie and the Belgian government.
EDF extends Flamanville EPR's shutdown to August 13 to conduct technical checks on three valves of the reactor's primary circuit, initially scheduled to resume production this week.
The US Department of Energy has selected Westinghouse and Radiant Nuclear to conduct the first nuclear microreactor tests at the DOME experimental centre located in Idaho, with operational start expected in spring 2026.
GE Vernova Hitachi Nuclear Energy and Fortum announce partnership aimed at preparing for the potential deployment of small modular reactors in Finland and Sweden, with commissioning scheduled for the 2030s.
Energy Fuels Inc. announced record production of 638,700 pounds of uranium during the second quarter of 2025 at its Pinyon Plain mine in Arizona, significantly surpassing initial site performance forecasts.
Argentina and Peru have signed an agreement expanding their scientific and technological cooperation in the civil nuclear field, including joint research projects and specialised training programmes for future development.
After several decades without funding nuclear projects, the World Bank has formed a strategic partnership with the IAEA to provide technical and financial support to countries integrating nuclear energy into their energy strategies.
South Korea's Nuclear Safety and Security Commission officially validates the decommissioning of reactor number one at the Kori plant, initiating an unprecedented project for the national industry scheduled to last until 2037.