popular articles

EDF postpones connection of Flamanville EPR by three months

EDF announces a further delay to the connection of the Flamanville EPR to the electricity grid. Start-up has been pushed back to late autumn 2024, adding to a long series of delays in this strategic nuclear project.

Please share:

EDF reports that the Flamanville EPR will not be connected to the electricity grid until late autumn 2024, three months later than planned.
The French nuclear safety authority (ASN) has given the go-ahead to start producing the first electrons, but the connection process, or “coupling”, still requires testing to reach an initial power level of 25%.
This latest setback comes on top of a twelve-year delay to the original schedule.
Divergence operations, which mark the start of controlled nuclear reactions, are scheduled for this week.
Régis Clément, Deputy Director of EDF’s Nuclear Generation Division, says this phase will take around ten hours.
He also stresses that the reactor will be ramped up in stages, without providing a precise date for reaching full capacity.

Technical problems and contingency management

The delays are attributed to various technical problems encountered at the Flamanville site.
On-site teams had to carry out additional operations during the summer due to unforeseen circumstances, thus delaying start-up.
These complications raise questions about risk management and cost control for this type of nuclear project.
The site has already been marked by construction anomalies, such as cracks in the concrete and welding defects, which have added considerably to the final bill.
Initially estimated at 3.3 billion euros, the cost of the Flamanville EPR has now risen to 13.2 billion euros.
The Cour des Comptes (French National Audit Office) had estimated it at 19 billion euros by 2020, taking into account additional financing costs.
These budget overruns reflect the complex challenges involved in implementing major nuclear projects in France.

Revision of nuclear production for 2024

Despite delays to the EPR, EDF has revised upwards its nuclear production forecast for 2024, now estimated at between 340 and 360 TWh.
This revision is due to the better performance of the other reactors in service, which are operating beyond initial expectations.
Optimized management of unit shutdowns and maintenance work, particularly concerning stress corrosion, contributed to this increase.
The summer weather, with no major events, also contributed to these results.
This revision does not take into account the potential contribution of the Flamanville EPR, whose contribution to the grid could represent an additional asset if the reactor is operational by the end of the year.
However, EDF remains cautious about the ramp-up of the EPR, stressing that each stage is conditional on successful testing and regulatory approvals.

Strategic context and industrial implications

The Flamanville EPR plays a key role in France’s nuclear strategy, particularly with the government’s commitment to revitalizing the industry.
President Emmanuel Macron has announced an order for six EPR2 reactors, with a further eight as options, to boost nuclear power generation.
Nevertheless, the difficulties encountered at Flamanville, both in terms of delays and cost overruns, are calling into question the planning and management of future similar projects.
The next stages of the project will be crucial for EDF and its partners.
The connection of the Flamanville EPR to the grid is expected to be an indicator of the Group’s ability to complete complex projects on time and on budget.
The success or failure of this project will influence future decisions, both for EDF and for the public authorities in charge of energy policy.

Register free of charge for uninterrupted access.

Publicite

Recently published in

Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
Washington and Abu Dhabi pave the way for renewed civil nuclear cooperation, aiming to strengthen Emirati technological and energy capabilities within a complex regional strategic context.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
EDF has delayed the restart of the Flamanville EPR to 11 April, citing a new maintenance operation, while keeping its 2025 production forecast unchanged.
EDF has delayed the restart of the Flamanville EPR to 11 April, citing a new maintenance operation, while keeping its 2025 production forecast unchanged.
EDF's plan to build a facility for recycling low-level radioactive metals in Fessenheim is raising significant concerns over health, economics and regulation.
enCore Energy extracted 50,000 pounds of uranium in March from its Alta Mesa site in Texas, while consolidating its operations through strategic leadership appointments.
enCore Energy extracted 50,000 pounds of uranium in March from its Alta Mesa site in Texas, while consolidating its operations through strategic leadership appointments.
Canada's nuclear regulator has issued Ontario Power Generation a construction licence for a BWRX-300 small modular reactor at the Darlington site, marking a key step in the province’s nuclear development.
Canada's nuclear regulator has issued Ontario Power Generation a construction licence for a BWRX-300 small modular reactor at the Darlington site, marking a key step in the province’s nuclear development.
Despite severe Western sanctions targeting Russian energy, Rosatom continues its international nuclear projects and maintains a steady flow of enriched uranium to Europe and the United States, thus supporting the Russian economy through an effective diversification strategy.
Despite severe Western sanctions targeting Russian energy, Rosatom continues its international nuclear projects and maintains a steady flow of enriched uranium to Europe and the United States, thus supporting the Russian economy through an effective diversification strategy.
Polskie Elektrownie Jądrowe has signed a development agreement with the Westinghouse-Bechtel consortium, ensuring continuity of Poland's first nuclear plant project after a previous contract expired.
Fermi Energia has signed a strategic agreement with Samsung C&T to develop two small modular reactors in Estonia, targeting commercial operation by 2035.
Fermi Energia has signed a strategic agreement with Samsung C&T to develop two small modular reactors in Estonia, targeting commercial operation by 2035.
China National Nuclear Corporation mobilizes international investors and financial partners for a unique nuclear project combining two distinct technologies to simultaneously supply industrial heat and electricity, marking a new strategic step for China's energy industry.
China National Nuclear Corporation mobilizes international investors and financial partners for a unique nuclear project combining two distinct technologies to simultaneously supply industrial heat and electricity, marking a new strategic step for China's energy industry.
Framatome and TechnicAtome have acquired Segault, a strategic nuclear valve manufacturer, thereby blocking a takeover by the American firm Flowserve following opposition from the French government.
Framatome and TechnicAtome have acquired Segault, a strategic nuclear valve manufacturer, thereby blocking a takeover by the American firm Flowserve following opposition from the French government.

Advertising