EDF postpones connection of Flamanville EPR by three months

EDF announces a further delay to the connection of the Flamanville EPR to the electricity grid. Start-up has been pushed back to late autumn 2024, adding to a long series of delays in this strategic nuclear project.

Partagez:

EDF reports that the Flamanville EPR will not be connected to the electricity grid until late autumn 2024, three months later than planned.
The French nuclear safety authority (ASN) has given the go-ahead to start producing the first electrons, but the connection process, or “coupling”, still requires testing to reach an initial power level of 25%.
This latest setback comes on top of a twelve-year delay to the original schedule.
Divergence operations, which mark the start of controlled nuclear reactions, are scheduled for this week.
Régis Clément, Deputy Director of EDF’s Nuclear Generation Division, says this phase will take around ten hours.
He also stresses that the reactor will be ramped up in stages, without providing a precise date for reaching full capacity.

Technical problems and contingency management

The delays are attributed to various technical problems encountered at the Flamanville site.
On-site teams had to carry out additional operations during the summer due to unforeseen circumstances, thus delaying start-up.
These complications raise questions about risk management and cost control for this type of nuclear project.
The site has already been marked by construction anomalies, such as cracks in the concrete and welding defects, which have added considerably to the final bill.
Initially estimated at 3.3 billion euros, the cost of the Flamanville EPR has now risen to 13.2 billion euros.
The Cour des Comptes (French National Audit Office) had estimated it at 19 billion euros by 2020, taking into account additional financing costs.
These budget overruns reflect the complex challenges involved in implementing major nuclear projects in France.

Revision of nuclear production for 2024

Despite delays to the EPR, EDF has revised upwards its nuclear production forecast for 2024, now estimated at between 340 and 360 TWh.
This revision is due to the better performance of the other reactors in service, which are operating beyond initial expectations.
Optimized management of unit shutdowns and maintenance work, particularly concerning stress corrosion, contributed to this increase.
The summer weather, with no major events, also contributed to these results.
This revision does not take into account the potential contribution of the Flamanville EPR, whose contribution to the grid could represent an additional asset if the reactor is operational by the end of the year.
However, EDF remains cautious about the ramp-up of the EPR, stressing that each stage is conditional on successful testing and regulatory approvals.

Strategic context and industrial implications

The Flamanville EPR plays a key role in France’s nuclear strategy, particularly with the government’s commitment to revitalizing the industry.
President Emmanuel Macron has announced an order for six EPR2 reactors, with a further eight as options, to boost nuclear power generation.
Nevertheless, the difficulties encountered at Flamanville, both in terms of delays and cost overruns, are calling into question the planning and management of future similar projects.
The next stages of the project will be crucial for EDF and its partners.
The connection of the Flamanville EPR to the grid is expected to be an indicator of the Group’s ability to complete complex projects on time and on budget.
The success or failure of this project will influence future decisions, both for EDF and for the public authorities in charge of energy policy.

After several decades without funding nuclear projects, the World Bank has formed a strategic partnership with the IAEA to provide technical and financial support to countries integrating nuclear energy into their energy strategies.
South Korea's Nuclear Safety and Security Commission officially validates the decommissioning of reactor number one at the Kori plant, initiating an unprecedented project for the national industry scheduled to last until 2037.
Uranium producer enCore Energy surpasses three thousand pounds per day at its Alta Mesa ISR complex and sees three new Texas laws as a strong signal for faster nuclear production permits.
The International Atomic Energy Agency expresses concerns over Iran’s enriched uranium stockpiles following the abrupt suspension of inspections at key sites disrupted by recent attacks whose consequences remain uncertain.
NPCIL has announced an extension until September 30 for industrial proposals concerning Bharat Small Reactors (BSR), following increased interest from the Indian private sector.
A regional court has upheld the award of two new reactors in the Czech Republic to Korea Hydro & Nuclear Power, dismissing Électricité de France’s challenge to the €16bn contract in a decisive step for the national energy programme.
Facing rising temperatures, EDF anticipates cuts in nuclear production starting early July, primarily due to thermal constraints on rivers used for cooling the power plants.
The preliminary agreement launches planning and site assessment for a tailored AP1000 reactor, following two years of feasibility study, and enlists Westinghouse and Hyundai to support Fortum’s regional nuclear expansion.
Donald Trump's unprecedented decision to dismiss Christopher Hanson, a member of the NRC, provokes outrage among former federal officials and raises concerns over the regulatory independence of the U.S. nuclear sector.
Uranium Energy Corp strengthens its position in Anfield Energy Inc., now holding approximately 32.4% of the company’s shares following an investment of CAD19.55mn ($14.82mn), significantly expanding its strategic influence in the uranium market.
New York State plans an advanced nuclear power plant with a 1-gigawatt capacity to meet long-term energy and economic goals, involving significant investment to enhance regional energy independence.
Niger announces its intention to nationalize SOMAÏR, a mining company jointly owned with Orano, provoking strong opposition from the French company and paving the way for further international legal tensions.
Russia strengthens its economic presence in Mali with new agreements, notably in nuclear energy and gold refining, consolidating strategic cooperation within a rapidly evolving geopolitical context.
The US government grants a fourth payment of $100.45 mn to Holtec International to restart the Palisades Nuclear Plant, pending regulatory approval, marking an unprecedented event in the United States.
EDF announces a major agreement with Apollo to raise up to £4.5 billion via bonds to finance the British nuclear project Hinkley Point C, whose costs continue to rise significantly.
The Élysée proposes Anne-Isabelle Étienvre, current Director of Fundamental Research at the CEA, as General Administrator to replace François Jacq, recently appointed President of CNES.
Greek Prime Minister Kyriakos Mitsotakis has announced his country's interest in small modular nuclear reactors to meet national energy challenges and decarbonize the maritime sector within the next fifteen years.
TerraPower, an American nuclear company, secures $650 million funding from investors, including NVIDIA, to develop its Natrium modular reactors in the United States and internationally.
EDF and the French state finalize a €70 billion financing plan for six EPR2 nuclear reactors, including a specific territorial coordination framework in Gravelines led by Michel Marbaix, awaiting European approval by 2026.
Maire S.p.A and Newcleo form strategic partnership to industrialise the development of 200 MW modular nuclear power plants, via a joint venture majority-owned by Nextchem.