The Hinkley Point plant will allow a “better controlled rate” of nuclear construction in France

EDF CEO Luc Rémont recently visited the Hinkley Point nuclear reactor site in the UK and stressed the importance of "industrial cadence" for the successful construction of future French nuclear power plants. He explained how the experience gained on this site can help EDF avoid past mistakes.

Share:

The construction of nuclear reactors in the United Kingdom at Hinkley Point allows EDF to enter an “industrial pace” and should avoid the pitfalls encountered on the site of Flamanville during the construction of future French nuclear power plants, said Thursday the CEO of EDF Luc Rémont.

Avoiding the setbacks of Flamanville

“It’s really one of the fundamental aspects of any industrial sector: the more you do, the better you are,” Rémont told a few reporters during a visit to the British yard with Energy Transition Minister Agnès Pannier-Runacher and her British counterpart Grant Shapps. “There, we have entered a phase of industrial rate of which Hinkley Point is the start because it is the first time that we make two (EPR) at once,” he said. “When we go from Hinkley Point to Sizewell (another EPR project carried by EDF in the United Kingdom), we will repeat the same gestures and when we go to the EPR 2 (optimized version of the EPR), we will also go directly to a series by repeating the same gestures”, he argued.

Mr. Rémont hopes to avoid a repetition of the setbacks encountered on the Flamanville EPR project, which is already 12 years behind schedule and whose initial budget has been multiplied by four, while France wishes to revive nuclear power with at least six EPRs to be built. “This site is very different from our experience in Flamanville,” he said. “In Flamanville, we were building our first reactor in France, a long, long time ago (…). Here, we are building two in one go, after the experience of Taishan in China, Olkiluoto in Finland and Flamanville, and with feedback from all these sites,” he said. The CEO of EDF also mentioned the digitization of the site “which allows us to know exactly what each person has to do at any given time and to take this into account in our work programming”.

The Hinkley Point site remains imperfect

However, the Hinkley Point project has also experienced several setbacks: the latest was on 19 May 2022, when EDF announced a new minimum delay of one year and additional costs of at least 3 billion pounds, with the first unit now scheduled to be commissioned in June 2027, instead of late 2025. Questioned about possible new hazards, the CEO of EDF assured that “all the teams are tense to keep” the target schedule.

Regarding the concerns expressed at the outset, particularly by the unions, about EDF taking on most of the financial risk of Hinkley Point, Mr. Rémont said that this project now allowed “a long-term vision” to be supported. Without it, the French industrial sector “would not be in a position to embark on the sequence (…) necessary for the sustainability of the electricity supply” with the construction of at least six EPR2.

The Canadian Nuclear Safety Commission has identified no major barriers to licensing the ARC-100 reactor, announces ARC Clean Technology.
SE Ignalina, the Lithuanian nuclear operator, has signed a memorandum of understanding with French firm Newcleo to explore the integration of small modular reactors (SMRs) using lead-cooled fast reactor (LFR) technology in Lithuania.
Egyptian President Abdel Fattah al-Sisi oversaw the signing of new agreements for the construction of the El Dabaa nuclear power plant, thus strengthening the strategic cooperation between Egypt and Russia.
Vistra Corp receives green light to extend Perry nuclear plant operations in Ohio by 20 years, securing regional electricity supply until 2046 and ensuring operational continuity for all its nuclear reactors in the United States.
EDF will hold a 12.5% stake in the Sizewell C nuclear project in the UK, a €1.3 billion investment announced during Emmanuel Macron’s official visit to London, confirming the strategic nuclear energy alignment between the two countries.
The French Cigéo project, designed to bury the most hazardous radioactive waste deep underground, obtains a crucial technical validation before its final authorization, expected by the end of 2027.
EDF confirms the continuation of its industrial project in Fessenheim for recycling very low-level radioactive metals, a first in France requiring specific regulatory authorizations, following a public debate concluded last February.
NANO Nuclear Energy Inc. formalizes its collaboration with UrAmerica Ltd. to strengthen Argentina’s uranium supply, aiming to secure future nuclear fuel supply chains for the U.S. market.
American companies SHINE Technologies and Standard Nuclear partner to recycle uranium and plutonium, supplying advanced fuel to the nuclear reactor sector and enhancing the national energy security of the United States.
The American Bureau of Shipping and two nuclear sector companies are studying the potential deployment of floating nuclear power plants to meet the energy needs of island and coastal regions in the Mediterranean, notably via electricity and desalination.
Lithuania establishes a working group tasked with assessing the feasibility of modular nuclear reactors to meet electricity demand estimated at 74 TWh by 2050.
Framatome has secured two significant contracts from Electrabel covering modernisation and technical support for the Tihange 3 and Doel 4 nuclear reactors, as part of their extension agreed upon between Engie and the Belgian government.
Cairo is stepping up connection works for the planned 4,800 MW El-Dabaa nuclear plant, developed with Rosatom, to feed the grid from 2026 with output equal to about seven % of national electricity.
GE Vernova Hitachi Nuclear Energy and Fortum announce partnership aimed at preparing for the potential deployment of small modular reactors in Finland and Sweden, with commissioning scheduled for the 2030s.
Energy Fuels Inc. announced record production of 638,700 pounds of uranium during the second quarter of 2025 at its Pinyon Plain mine in Arizona, significantly surpassing initial site performance forecasts.
Argentina and Peru have signed an agreement expanding their scientific and technological cooperation in the civil nuclear field, including joint research projects and specialised training programmes for future development.
After several decades without funding nuclear projects, the World Bank has formed a strategic partnership with the IAEA to provide technical and financial support to countries integrating nuclear energy into their energy strategies.
South Korea's Nuclear Safety and Security Commission officially validates the decommissioning of reactor number one at the Kori plant, initiating an unprecedented project for the national industry scheduled to last until 2037.
Uranium producer enCore Energy surpasses three thousand pounds per day at its Alta Mesa ISR complex and sees three new Texas laws as a strong signal for faster nuclear production permits.
The International Atomic Energy Agency expresses concerns over Iran’s enriched uranium stockpiles following the abrupt suspension of inspections at key sites disrupted by recent attacks whose consequences remain uncertain.