popular articles

The UK Denies Cost Surge in Sizewell C Nuclear Project

The British government refutes Financial Times claims about the doubling of costs for the Sizewell C nuclear power plant project led by EDF in eastern England.

Please share:

The British government has categorically denied reports that the cost of the Sizewell C nuclear power plant, currently under development by EDF, has doubled to reach £40 billion (approximately €47 billion). These claims, published by the economic daily *Financial Times* (FT), were described as “speculative” by a spokesperson for the Department of Energy.

According to the *Financial Times*, this cost overrun is attributed to multiple factors, including inflation and delays affecting the twin project of Hinkley Point C, also managed by EDF. Hinkley Point C has experienced significant budget overruns, reaching nearly £34 billion, according to an estimate released last year.

Statements from Involved Parties

The team managing the Sizewell C project also responded to the figures reported by the *Financial Times*, stating that they are “inaccurate.” They noted that project costs benefit from efficiencies gained from lessons learned at Hinkley Point C, particularly in workforce training and supply chain management.

An EDF representative highlighted that Sizewell C is designed to host two European Pressurized Reactors (EPR), each with a capacity of 1.6 gigawatts. The plant’s electricity production is slated for 2035. Meanwhile, the British government is continuing discussions with private investors to finalize funding, with negotiations expected to conclude in spring 2025.

Investment and Partnership

The UK government approved the Sizewell C project in July 2022, acquiring a 50% stake after the withdrawal of Chinese partner CGN. London has already invested billions of pounds in the project, but the final investment decision remains contingent on ongoing fundraising efforts.

This project is part of the UK’s strategy to reduce reliance on fossil fuels by expanding low-carbon nuclear power generation. However, it has drawn criticism for delays and financial risks borne by EDF, as highlighted in a recent report by France’s Court of Auditors. The report recommends that EDF limit its financial exposure in international projects.

A Challenging International Context

Simultaneously, EDF faces criticism for the management of its EPR projects abroad, including those in Flamanville (France) and Olkiluoto (Finland). These projects have been plagued by delays and cost overruns, casting doubt on the economic viability of this technology in a competitive energy market.

The Sizewell C nuclear power plant is seen as a critical test for the future of nuclear energy in the UK. Success could bolster the country’s position as a leader in the energy transition, while further setbacks might deter international investors.

Register free of charge for uninterrupted access.

Publicite

Recently published in

Czech justice has suspended the signing of a major contract between Prague and South Korea’s KHNP, following a complaint by French group EDF challenging the fairness of the Dukovany nuclear project tender.
Thanks to recent strategic agreements, Utah is establishing itself as a key regional hub for the development and production of Small Modular Reactors, boosting a rapidly growing industry at the heart of the United States.
Thanks to recent strategic agreements, Utah is establishing itself as a key regional hub for the development and production of Small Modular Reactors, boosting a rapidly growing industry at the heart of the United States.
The United States is multiplying energy agreements with Romania and Bulgaria, focusing on civil nuclear power and hydropower storage to deepen its influence in strategic regional projects.
The United States is multiplying energy agreements with Romania and Bulgaria, focusing on civil nuclear power and hydropower storage to deepen its influence in strategic regional projects.
U.S.-based Energy Fuels extracted 151,400 pounds of uranium in April, reaching an unprecedented level since the opening of its Pinyon Plain mine, while underground drilling reveals exceptionally high grades.
U.S.-based Energy Fuels extracted 151,400 pounds of uranium in April, reaching an unprecedented level since the opening of its Pinyon Plain mine, while underground drilling reveals exceptionally high grades.
The Nuclear Safety and Radiation Protection Authority (ASNR) will now publish its decisions and expert reports simultaneously, amid a controversial merger of nuclear oversight bodies.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Two French MPs have raised concerns over the massive cost overruns of the Hinkley Point nuclear project, describing it as a “financial sinkhole” for EDF, now fully owned by the State.
Two French MPs have raised concerns over the massive cost overruns of the Hinkley Point nuclear project, describing it as a “financial sinkhole” for EDF, now fully owned by the State.
The Chinese State Council has just authorized the construction of ten new nuclear reactors across five strategic sites, highlighting a massive acceleration in energy ambitions to achieve record installed capacity by 2025.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
Trondheimsleia Kjernekraft AS was founded to lead a nuclear plant project based on several small modular reactors in the Trøndelag region, targeting up to 1500 MWe of installed capacity.
Trondheimsleia Kjernekraft AS was founded to lead a nuclear plant project based on several small modular reactors in the Trøndelag region, targeting up to 1500 MWe of installed capacity.
Flamanville’s EPR nuclear reactor experienced a temporary shutdown on Friday and Saturday, without affecting its ramp-up schedule, EDF confirmed.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.

Advertising