popular articles

The French Government announces the delay of the commissioning of the EPR2 reactors to 2038

President Emmanuel Macron has announced an additional delay for the commissioning of the first EPR2 reactors, now set for 2038 instead of 2035. This decision was made during a meeting dedicated to the nuclear program.

Please share:

On March 17, 2025, the Élysée confirmed that the first of the six EPR2 nuclear reactors (Evolutionary Power Reactor 2) would not be commissioned before 2038, thus postponing the initial target of 2035. This change in schedule follows a meeting of the Nuclear Policy Council, chaired by French President Emmanuel Macron. The program, announced in February 2022, involves the construction of six new nuclear reactors, with the possibility of adding eight more.

The 2038 target for the start of electricity production from these reactors, announced on Monday, came after a government audit in 2022 suggested that the commissioning of the first reactors could be delayed until 2037. This revision of timelines is part of a broader overhaul of the national nuclear policy, aimed at strengthening energy production capacity while addressing safety and financing concerns.

Financing of the EPR2 Program

Discussions during the meeting focused on the financing modalities of the project. The financing of the EPR2 reactors would largely be secured through a subsidized loan from the state, covering at least 50% of the construction costs. This financing model would draw on elements observed in the funding of the Czech Dukovany nuclear plant, approved by the European Union, particularly the use of a zero-interest loan.

A contract for difference, ensuring a maximum price of 100 euros per megawatt-hour (MWh) in 2024 euros, could be put in place to secure the price of electricity production from the future reactors. This model aims to protect investors while stabilizing energy market prices.

Follow-up and Updated Costs

The Élysée clarified that discussions between the state and EDF should be concluded in the coming weeks. A dialogue will also be initiated with the European Commission to obtain a final investment decision from EDF by 2026. This step is critical before officially launching the construction of the reactors.

The program’s costs have been revised upwards. Initially estimated at €51.7 billion in 2022, the total cost of the six EPR2 reactors is now estimated at €67.4 billion for 2023, according to the Court of Auditors. Taking inflation into account, a total budget of nearly €80 billion is now being considered. Government officials have stated that a final financial framework will be determined soon.

Register free of charge for uninterrupted access.

Publicite

Recently published in

U.S.-based Energy Fuels extracted 151,400 pounds of uranium in April, reaching an unprecedented level since the opening of its Pinyon Plain mine, while underground drilling reveals exceptionally high grades.
The Nuclear Safety and Radiation Protection Authority (ASNR) will now publish its decisions and expert reports simultaneously, amid a controversial merger of nuclear oversight bodies.
The Nuclear Safety and Radiation Protection Authority (ASNR) will now publish its decisions and expert reports simultaneously, amid a controversial merger of nuclear oversight bodies.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Two French MPs have raised concerns over the massive cost overruns of the Hinkley Point nuclear project, describing it as a “financial sinkhole” for EDF, now fully owned by the State.
The Chinese State Council has just authorized the construction of ten new nuclear reactors across five strategic sites, highlighting a massive acceleration in energy ambitions to achieve record installed capacity by 2025.
The Chinese State Council has just authorized the construction of ten new nuclear reactors across five strategic sites, highlighting a massive acceleration in energy ambitions to achieve record installed capacity by 2025.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
Trondheimsleia Kjernekraft AS was founded to lead a nuclear plant project based on several small modular reactors in the Trøndelag region, targeting up to 1500 MWe of installed capacity.
Flamanville’s EPR nuclear reactor experienced a temporary shutdown on Friday and Saturday, without affecting its ramp-up schedule, EDF confirmed.
Flamanville’s EPR nuclear reactor experienced a temporary shutdown on Friday and Saturday, without affecting its ramp-up schedule, EDF confirmed.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
Washington and Abu Dhabi pave the way for renewed civil nuclear cooperation, aiming to strengthen Emirati technological and energy capabilities within a complex regional strategic context.
Washington and Abu Dhabi pave the way for renewed civil nuclear cooperation, aiming to strengthen Emirati technological and energy capabilities within a complex regional strategic context.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.

Advertising