popular articles

Orano envisages a long and uncertain restart for its uranium mine in Niger

The Orano group faces a difficult restart of its mining operations in Niger after losing control of its subsidiaries. The restart of the Somaïr mine could take nearly two years due to political tensions with the local junta.

Please share:

Orano’s situation in Niger remains complex, with highly uncertain prospects for the restart of its mining operations in the country. The French group, a specialist in nuclear fuel, has expressed doubts about a quick restart of its uranium site at Somaïr (Société des Mines de l’Air), which has been on hold since the political instability caused by the military coup in July 2023. According to Orano’s CEO, Nicolas Maes, the current situation could result in a delay of several years before the mine fully restarts.

At the end of 2024, Orano was forced to remove from its accounts its three main mining subsidiaries in Niger, namely Somaïr, Cominak (Compagnie des Mines de l’Akokan), and Imouraren. This decision followed interference by the Nigerien authorities in the management of these subsidiaries, resulting in a complete loss of operational control over these mining sites. Orano still holds majority stakes in these companies (63.5% in Somaïr, 69% in Cominak, and 63.5% in Imouraren), but local authorities have altered the terms of operation, deeply affecting the profitability and stability of the operations.

Challenges in restarting the Somaïr mine

The Somaïr site, one of the oldest uranium producers in Niger, is facing a very difficult financial situation after being paralyzed by local politics. Orano is facing administrative blockages that prevent the shipment of 1,300 tonnes of uranium concentrate stored on-site. These tonnes represent a market value of 250 million euros, but the Nigerien authorities have not authorized their export. This critical financial situation makes it virtually impossible to restart operations, as the mine no longer has revenue to pay its creditors and 780 employees.

Orano has estimated that, if an agreement were reached with the authorities, it could take up to two years to restart operations at the mine. However, the group highlights the complete lack of communication with the government since the 2023 coup. The military junta in power in Niamey, which emphasizes national sovereignty, seeks to revise the terms of natural resource exploitation by foreign companies, particularly Orano, which has been extracting uranium in the northern part of the country since 1971.

Suspension of rehabilitation works at the Cominak mine

Regarding Cominak, Orano has also faced significant difficulties. The uranium mine, closed in 2021, is undergoing rehabilitation work. However, due to the loss of control over the subsidiary, these works have been suspended. Orano clarified that although the company can no longer carry out these works, it believes it has an obligation to finalize the rehabilitation process. To this end, Orano decided to maintain a provision of 70 million euros, initially allocated by Cominak for the rehabilitation works. This decision is in addition to the 193 million euros of depreciation and provisions recorded by the group for its other mining activities in 2024, notably at the Imouraren and Somaïr sites.

Orano, whose activities in Niger have undergone a major reassessment, is trying to manage the financial implications of this situation while maintaining its obligations to the Nigerien authorities and local employees. However, the future of uranium mining in Niger remains uncertain.

Register free of charge for uninterrupted access.

Publicite

Recently published in

Czech justice has suspended the signing of a major contract between Prague and South Korea’s KHNP, following a complaint by French group EDF challenging the fairness of the Dukovany nuclear project tender.
Thanks to recent strategic agreements, Utah is establishing itself as a key regional hub for the development and production of Small Modular Reactors, boosting a rapidly growing industry at the heart of the United States.
Thanks to recent strategic agreements, Utah is establishing itself as a key regional hub for the development and production of Small Modular Reactors, boosting a rapidly growing industry at the heart of the United States.
The United States is multiplying energy agreements with Romania and Bulgaria, focusing on civil nuclear power and hydropower storage to deepen its influence in strategic regional projects.
The United States is multiplying energy agreements with Romania and Bulgaria, focusing on civil nuclear power and hydropower storage to deepen its influence in strategic regional projects.
U.S.-based Energy Fuels extracted 151,400 pounds of uranium in April, reaching an unprecedented level since the opening of its Pinyon Plain mine, while underground drilling reveals exceptionally high grades.
U.S.-based Energy Fuels extracted 151,400 pounds of uranium in April, reaching an unprecedented level since the opening of its Pinyon Plain mine, while underground drilling reveals exceptionally high grades.
The Nuclear Safety and Radiation Protection Authority (ASNR) will now publish its decisions and expert reports simultaneously, amid a controversial merger of nuclear oversight bodies.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Two French MPs have raised concerns over the massive cost overruns of the Hinkley Point nuclear project, describing it as a “financial sinkhole” for EDF, now fully owned by the State.
Two French MPs have raised concerns over the massive cost overruns of the Hinkley Point nuclear project, describing it as a “financial sinkhole” for EDF, now fully owned by the State.
The Chinese State Council has just authorized the construction of ten new nuclear reactors across five strategic sites, highlighting a massive acceleration in energy ambitions to achieve record installed capacity by 2025.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
Trondheimsleia Kjernekraft AS was founded to lead a nuclear plant project based on several small modular reactors in the Trøndelag region, targeting up to 1500 MWe of installed capacity.
Trondheimsleia Kjernekraft AS was founded to lead a nuclear plant project based on several small modular reactors in the Trøndelag region, targeting up to 1500 MWe of installed capacity.
Flamanville’s EPR nuclear reactor experienced a temporary shutdown on Friday and Saturday, without affecting its ramp-up schedule, EDF confirmed.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.

Advertising