popular articles

OPG obtains CNSC approval to extend Pickering units’ operation until 2026

The Canadian Nuclear Safety Commission has authorized Ontario Power Generation to keep Pickering units 5-8 operational until the end of 2026, facilitating the preparation for their refurbishment.

Please share:

Ontario Power Generation (OPG) has received approval from the Canadian Nuclear Safety Commission (CNSC) to extend the operation of Pickering units 5 to 8 until December 31, 2026. This decision allows the units to remain in operation until they are taken offline for refurbishment.

Submissions from OPG, CNSC staff, and 54 intervenors during a public hearing in June 2024 in Pickering were considered by the CNSC before granting the extension. Initially, OPG was authorized to operate the units until December 31 of this year, with a maximum limit of 295,000 equivalent full power hours (EFPH). The modified license increases this limit to 305,000 EFPH and requires OPG to implement an enhanced fitness-for-service program.

The Pickering Nuclear Generating Station consists of two reactor facilities with a total of eight Candu reactor units. Units 5-8, sometimes referred to as Pickering B, began operation between 1983 and 1986. Units 1 and 4, part of the four-unit Pickering A plant which was first commissioned in the early 1970s and was shut down in 1997, underwent refurbishment before returning to service in 2003 (unit 4) and in 2005 (unit 1).

Unit 1 was taken offline on September 30 as planned and will now be dewatered and placed in safe storage. Unit 4 will also be taken offline by the end of December, while OPG continues to plan the refurbishment of units 5-8.

The CNSC’s decision will help meet Ontario’s growing electricity demand, particularly as other nuclear stations in the province undergo refurbishment, OPG said.

“This is another great milestone for Pickering Nuclear and all our station staff, who have worked hard to help Pickering achieve some of its best performance in its history in recent years,” said Steve Gregoris, OPG’s Chief Nuclear Officer.

Plans to refurbish units 5-8 were formalized earlier this year when the provincial government announced its support for the project. OPG’s timeline envisions putting the entire station into a “layup state” in 2026 so that refurbishment activities can begin. All four refurbished reactors will be back online by the mid-2030s.

Additionally, OPG is currently refurbishing four Candu units at its Darlington site, aiming to complete the project by 2026, and is also planning to build up to four BWRX-300 small modular reactors (SMRs) at its Darlington New Nuclear project.

Implications for the energy sector

The extension of the operation of Pickering units 5-8 ensures continuity in nuclear energy production in Ontario, a critical element for the stability of the province’s power grid. This decision comes at a time when the renewal of energy infrastructure is essential to meet the growing need for clean and sustainable energy.

Renovation and technological innovation

OPG’s refurbishment projects include the integration of advanced technologies to enhance reactor efficiency and safety. The implementation of BWRX-300 SMRs at the Darlington site represents a significant step toward modular and flexible energy solutions, tailored to today’s market requirements.

Economic and environmental impact

The continued operation of the Pickering units also contributes to the local economy by maintaining jobs and supporting nuclear-related service providers. Environmentally, nuclear energy remains a low-carbon source, aligned with the province’s greenhouse gas reduction goals.

Future outlook

With the refurbishment of the Pickering and Darlington units, OPG is positioning itself as a key player in Ontario’s energy transition. Continued efforts in innovation and refurbishment will ensure reliable and sustainable energy production for decades to come.

Register free of charge for uninterrupted access.

Publicite

Recently published in

U.S.-based Energy Fuels extracted 151,400 pounds of uranium in April, reaching an unprecedented level since the opening of its Pinyon Plain mine, while underground drilling reveals exceptionally high grades.
The Nuclear Safety and Radiation Protection Authority (ASNR) will now publish its decisions and expert reports simultaneously, amid a controversial merger of nuclear oversight bodies.
The Nuclear Safety and Radiation Protection Authority (ASNR) will now publish its decisions and expert reports simultaneously, amid a controversial merger of nuclear oversight bodies.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
The French Parliament has approved Bernard Fontana's appointment as CEO of EDF, paving the way for a new industrial phase in the nuclear sector under close scrutiny from public and industrial stakeholders.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Polskie Elektrownie Jądrowe signed a new agreement with the Westinghouse-Bechtel consortium to ensure the continuity of the development of Poland’s first nuclear power plant project.
Two French MPs have raised concerns over the massive cost overruns of the Hinkley Point nuclear project, describing it as a “financial sinkhole” for EDF, now fully owned by the State.
The Chinese State Council has just authorized the construction of ten new nuclear reactors across five strategic sites, highlighting a massive acceleration in energy ambitions to achieve record installed capacity by 2025.
The Chinese State Council has just authorized the construction of ten new nuclear reactors across five strategic sites, highlighting a massive acceleration in energy ambitions to achieve record installed capacity by 2025.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
Axpo reconnected unit 1 of the Beznau nuclear power plant to the grid after two weeks of refuelling, marking the start of a new operating cycle for the Swiss facility.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
The Czech competition regulator has dismissed EDF’s appeal, confirming the selection of Korea Hydro & Nuclear Power for the construction of new nuclear capacity at Dukovany.
Trondheimsleia Kjernekraft AS was founded to lead a nuclear plant project based on several small modular reactors in the Trøndelag region, targeting up to 1500 MWe of installed capacity.
Flamanville’s EPR nuclear reactor experienced a temporary shutdown on Friday and Saturday, without affecting its ramp-up schedule, EDF confirmed.
Flamanville’s EPR nuclear reactor experienced a temporary shutdown on Friday and Saturday, without affecting its ramp-up schedule, EDF confirmed.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
Japanese operator Tepco has completed the extraction of a second radioactive debris sample from the damaged Fukushima reactor, a critical technical step in a decommissioning project set to span several decades.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
US-based enCore Energy continues to optimise its uranium project in Texas with a record installation rate and strengthened leadership team.
Framatome has commissioned a new facility in Romans-sur-Isère to secure long-term production of research reactor fuels and medical isotopes.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
EDF reconnected the Flamanville EPR nuclear reactor to the power grid on 19 April, two days ahead of schedule, following a series of technical maintenance works and adjustments on critical components.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
Washington and Abu Dhabi pave the way for renewed civil nuclear cooperation, aiming to strengthen Emirati technological and energy capabilities within a complex regional strategic context.
Washington and Abu Dhabi pave the way for renewed civil nuclear cooperation, aiming to strengthen Emirati technological and energy capabilities within a complex regional strategic context.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.

Advertising