Ofgem, the UK’s energy regulator, has officially approved the costs of the Eastern Green Link 2 (EGL2) project.
This infrastructure, which will link Peterhead in Scotland to Drax in England via a 525 kV, 2 GW high-voltage direct current (HVDC) submarine cable, represents the most significant investment in the history of the UK transmission network.
Scheduled to enter service in 2029, EGL2 is designed to relieve congestion on the grid, particularly between Scotland and England, strategic areas for offshore wind power generation.
This approval marks the start of the construction phase for the 500 km-long link, which will play a crucial role in optimizing the distribution of renewable energies.
The North Sea, which borders these regions, is a major site for wind farms such as Seagreen Wind Farm (1,075 MW) and Dogger Bank Wind Farm (3.6 GW).
The EGL2 project is therefore part of a wider drive to boost grid capacity without the need for major additional onshore infrastructure.

Collaboration and Strategic Investments

EGL2 is the result of a collaboration between National Grid and SSEN Transmission, two major players in UK electricity transmission.
The project is part of SSEN’s Pathway to 2030 program, which includes a £20 billion investment to modernize Scotland’s electricity network.
The Prysmian Group will manufacture 1,000 km of HVDC cables, while Hitachi Energy and BAM will build the necessary converter stations at each end of the submarine link.
This infrastructure responds to the needs identified by National Grid operator ESO, which in its “Beyond 2030” report highlighted the need to improve transmission infrastructure to eliminate bottlenecks and ensure more efficient distribution of electricity.
The rapid approval of this project was facilitated by Ofgem’s Accelerated Strategic Transmission Investment (ASTI) regulatory framework, which reduces approval times for strategic projects by up to two years.

Regulatory and financial impact

Ofgem’s ASTI framework, designed to accelerate the development of critical infrastructures, does not translate into financial laxity.
The regulator retains the ability to intervene to adjust costs, thus guaranteeing the economic efficiency of the project and the protection of consumer interests.
With a total investment estimated at £4.3 billion, EGL2 is an emblematic project that marks a milestone in the evolution of the British transmission network.
The outlook for the sector is promising, with other similar initiatives in the pipeline, such as a third Eastern Green Link to connect Peterhead to Lincolnshire in England.
These projects demonstrate the UK’s ongoing commitment to investing in robust, sustainable infrastructure to support the transition to a low-carbon energy mix.

According to the 2025 report on global energy access, despite notable progress in renewable energy, insufficient targeted financing continues to hinder electricity and clean cooking access, particularly in sub-Saharan Africa.
While advanced economies maintain global energy leadership, China and the United States have significantly progressed in the security and sustainability of their energy systems, according to the World Economic Forum's annual report.
On the sidelines of the US–Africa summit in Luanda, Algiers and Luanda consolidate their energy collaboration to better exploit their oil, gas, and mining potential, targeting a common strategy in regional and international markets.
The UK's Climate Change Committee is urging the government to quickly reduce electricity costs to facilitate the adoption of heat pumps and electric vehicles, judged too slow to achieve the set climate targets.
The European Commission will extend until the end of 2030 an expanded state-aid framework, allowing capitals to fund low-carbon technologies and nuclear power to preserve competitiveness against China and the United States.
Japan's grid operator forecasts an energy shortfall of up to 89 GW by 2050 due to rising demand from semiconductor manufacturing, electric vehicles, and artificial intelligence technologies.
Energy-intensive European industries will be eligible for temporary state aid to mitigate high electricity prices, according to a new regulatory framework proposed by the European Commission under the "Clean Industrial Deal."
Mauritius seeks international investors to swiftly build a floating power plant of around 100 MW, aiming to secure the national energy supply by January 2026 and address current production shortfalls.
Madrid announces immediate energy storage measures while Lisbon secures its electrical grid, responding to the historic outage that affected the entire Iberian Peninsula in late April.
Indonesia has unveiled its new national energy plan, projecting an increase of 69.5 GW in electricity capacity over ten years, largely funded by independent producers, to address rapidly rising domestic demand.
French Minister Agnès Pannier-Runacher condemns the parliamentary moratorium on new renewable energy installations, warning of the potential loss of 150,000 industrial jobs and increased energy dependence on foreign countries.
The European battery regulation, fully effective from August 18, significantly alters industrial requirements related to electric cars and bicycles, imposing strict rules on recycling, supply chains, and transparency for companies.
The European Parliament calls on the Commission to strengthen energy infrastructure and accelerate the implementation of the Clean Industrial Deal to enhance the continent's energy flexibility and security amid increased market volatility.
The European Commission unveils an ambitious plan to modernize electricity grids and introduces the Clean Industrial Deal, mobilizing hundreds of billions of euros to strengthen the continent's industrial and energy autonomy.
In the United States, regulated electric grid operators hold a decisive advantage in connecting new data centres to the grid, now representing 134 GW of projects, according to a Wood Mackenzie report published on June 19.
The French National Assembly approves a specific target of 200 TWh renewable electricity production by 2030 within a legislative text extensively debated about the future national energy mix.
In 2024, US CO₂ emissions remain stable at 5.1bn tonnes, as the Trump administration prepares hydrocarbon-friendly energy policies, raising questions about the future evolution of the American market.
The early publication of France's energy decree triggers strong parliamentary reactions, as the government aims to rapidly secure investments in nuclear and other energy sectors.
Seven weeks after the major Iberian power outage, Spain identifies technical network failures, while the European Investment Bank approves major funding to strengthen the interconnection with France.
The European Union has announced a detailed schedule aiming to definitively halt Russian gas imports by the end of 2027, anticipating internal legal and commercial challenges to overcome.