Flamanville: the EPR power-up postponed until the end of autumn 2025

The Flamanville EPR nuclear reactor will not reach full power until before the end of autumn, postponing the initially scheduled date due to preventive maintenance operations on the primary circuit valves.

Share:

The schedule for the new generation nuclear reactor at Flamanville is facing a new delay, with full power now expected only before the end of autumn. The French electricity provider has announced that the extension of a shutdown, for checks and maintenance on a primary circuit safety valve, requires a change in the plant’s power-up schedule.

Preventive maintenance on key equipment

The EPR (European Pressurised Reactor) had been shut down since June 19 for commissioning tests, a standard step during the launch of new nuclear installations. On July 2, the operating company decided to keep the reactor offline to intervene on several valves located at the top of the pressuriser. These pieces of equipment play a major role in keeping the primary circuit water at a pressure of 155 bars.

During these tests, it was found that two of the three valves in this circuit were not entirely compliant with the expected sealing requirements. As a result, preventive maintenance was scheduled on the third valve, making use of the teams already mobilised on site.

Impact on industrial schedule and project costs

Restarting the nuclear reactor is now set for October 1, thereby shifting the achievement of 100% power that was initially scheduled for the end of summer. According to a spokesperson for the electricity provider, each reactor start-up requires testing of 1,500 safety criteria, sometimes involving the readjustment of certain settings throughout the tests.

The Flamanville EPR reactor, which was connected to the electricity grid on December 21, 2024, is now twelve years behind the original schedule. The project has experienced numerous technical setbacks since construction began.

Budget overrun and financial challenges

The total project cost has greatly exceeded the initial estimate of €3.3bn ($3.57bn). According to the Cour des comptes, the total project cost is now estimated at €19.3bn ($20.92bn) at 2015 prices, and even €22.6bn ($24.50bn) at 2023 prices, including financing. The Flamanville 3 reactor remains the first of its kind to start in France in twenty-five years.

The large number of safety criteria checked and the technical complexity of the project demonstrate the vigilance required for new reactors of this type, as the nuclear sector continues to face significant scheduling and cost challenges.

Hunatom announces a strategic alliance with Synthos Green Energy to introduce US small modular reactor technology, strengthening energy ties between Hungary, Poland and the United States.
A joint feasibility study project on Korean i-SMR modular reactors has just been launched for a future nuclear site at the border of the Aure and Heim municipalities, aiming for significant regional industrial impact.
Unit 3 of the Tomari nuclear power plant takes a major step towards restart after its safety equipment was validated by the Japanese regulator.
The Russian Minister of Energy announces strengthened cooperation in uranium and civil nuclear energy in Niger, reinforcing Russia's economic presence in a key sector following the withdrawal of several Western players.
Last Energy reaches a key regulatory step for its PWR-20 microreactor project in Llynfi, advancing towards the objective of securing a site licence by December 2027 from British authorities.
Slovenské elektrárne has signed an agreement with Urenco for the purchase of enriched uranium for the Bohunice and Mochovce nuclear power plants, strengthening the diversification of its supply sources until the mid-2030s.
Emirates Nuclear Energy Company signs two major agreements with Hyundai Engineering & Construction and Westinghouse, strengthening its position in the global civil nuclear market and paving the way for new international industrial opportunities.
First Hydrogen expands its collaboration with the University of Alberta to optimise small modular nuclear reactor design and support green hydrogen development amid the growth of artificial intelligence data centres.
The French and Belgian energy ministers have signed a declaration of intent to strengthen ties between Paris and Brussels on nuclear energy, as Belgium has abandoned its 2003 nuclear phase-out plan.
The United States Nuclear Regulatory Commission has authorised the restart of the Palisades power plant, marking a key milestone for Holtec in reintegrating this reactor into the US energy mix. —
The Genkai nuclear power plant detected the intrusion of three unidentified drones, prompting an immediate investigation by Japanese authorities into this unusual incident with potential national security implications.
KATCO, a joint venture between Orano and Kazatomprom, has started operations at the South Tortkuduk site, backed by a $190mn investment, targeting a production capacity of 4,000 tonnes per year by 2026.
Tehran agrees to host experts from the International Atomic Energy Agency in the coming weeks, excluding any visit to sensitive sites as diplomatic tensions persist with European nations and the United States.
Standard Uranium announces the results of a high-resolution electromagnetic survey at the Corvo project, confirming 29 kilometres of conductive corridors and launching the planning of an inaugural drilling programme for 2026.
NANO Nuclear Energy assembles and tests its annular induction pump prototype, marking progress for its microreactor programmes and paving the way for potential commercialisation of the technology.
Hungary reaffirms its intent to double the capacity of its Paks nuclear power plant in partnership with Rosatom, with concrete works expected to begin in the autumn.
Arabelle Solutions, a subsidiary of EDF, will provide turbine island equipment for the first BWRX-300 small modular reactor project in Canada, marking a milestone for the industrialisation of SMRs in North America.
Framatome will supply nuclear fuel and technical services to ENEC, strengthening the United Arab Emirates’ energy supply chain for the Barakah nuclear plant.
French start-up Stellaria secures €23mn ($25.2mn) in funding to accelerate the design of its fast neutron nuclear reactor, with first fission expected in 2029 and commercial deployment targeted for 2035.
The Bulgarian National Audit Office report highlights persistent delays and contractual irregularities in the implementation of the national repository for low- and intermediate-level radioactive waste.