Flamanville: the EPR power-up postponed until the end of autumn 2025

The Flamanville EPR nuclear reactor will not reach full power until before the end of autumn, postponing the initially scheduled date due to preventive maintenance operations on the primary circuit valves.

Share:

Comprehensive energy news coverage, updated nonstop

Annual subscription

8.25€/month*

*billed annually at 99€/year for the first year then 149,00€/year ​

Unlimited access • Archives included • Professional invoice

OTHER ACCESS OPTIONS

Monthly subscription

Unlimited access • Archives included

5.2€/month*
then 14.90€ per month thereafter

FREE ACCOUNT

3 articles offered per month

FREE

*Prices are excluding VAT, which may vary depending on your location or professional status

Since 2021: 35,000 articles • 150+ analyses per week

The schedule for the new generation nuclear reactor at Flamanville is facing a new delay, with full power now expected only before the end of autumn. The French electricity provider has announced that the extension of a shutdown, for checks and maintenance on a primary circuit safety valve, requires a change in the plant’s power-up schedule.

Preventive maintenance on key equipment

The EPR (European Pressurised Reactor) had been shut down since June 19 for commissioning tests, a standard step during the launch of new nuclear installations. On July 2, the operating company decided to keep the reactor offline to intervene on several valves located at the top of the pressuriser. These pieces of equipment play a major role in keeping the primary circuit water at a pressure of 155 bars.

During these tests, it was found that two of the three valves in this circuit were not entirely compliant with the expected sealing requirements. As a result, preventive maintenance was scheduled on the third valve, making use of the teams already mobilised on site.

Impact on industrial schedule and project costs

Restarting the nuclear reactor is now set for October 1, thereby shifting the achievement of 100% power that was initially scheduled for the end of summer. According to a spokesperson for the electricity provider, each reactor start-up requires testing of 1,500 safety criteria, sometimes involving the readjustment of certain settings throughout the tests.

The Flamanville EPR reactor, which was connected to the electricity grid on December 21, 2024, is now twelve years behind the original schedule. The project has experienced numerous technical setbacks since construction began.

Budget overrun and financial challenges

The total project cost has greatly exceeded the initial estimate of €3.3bn ($3.57bn). According to the Cour des comptes, the total project cost is now estimated at €19.3bn ($20.92bn) at 2015 prices, and even €22.6bn ($24.50bn) at 2023 prices, including financing. The Flamanville 3 reactor remains the first of its kind to start in France in twenty-five years.

The large number of safety criteria checked and the technical complexity of the project demonstrate the vigilance required for new reactors of this type, as the nuclear sector continues to face significant scheduling and cost challenges.

NextEra Energy announces an agreement with Google to restart a nuclear plant in Iowa, with operations expected to resume as early as 2029 and full site ownership secured.
The environmental review of TerraPower’s Natrium project in Wyoming has been completed, paving the way for a construction permit for this advanced nuclear reactor.
Santee Cooper has selected Brookfield Asset Management to lead a feasibility study aimed at completing two unfinished AP1000 reactors, without relying on public funds or raising consumer rates.
Endesa, Iberdrola and Naturgy have officially requested the Spanish government to delay the closure of the Almaraz nuclear power plant, originally scheduled for 2028, reigniting the debate on nuclear power's role in the national energy mix.
The reactor vessel for Unit 1 at Egypt’s El Dabaa nuclear plant has been delivered following a 20-day maritime transport from Saint Petersburg, marking a critical milestone in the country’s energy project.
Ontario Power Generation secures CAD3bn ($2.1bn) in public equity financing to construct four modular reactors at Darlington, aiming to ease private sector entry into next-generation nuclear infrastructure.
French developer Newcleo launches a joint venture with Nextchem through a EUR70 mn contract to design the conventional island of its upcoming 200 MW modular nuclear reactors.
NANO Nuclear strengthens its North American strategy by acquiring Global First Power in Canada, securing regulatory rights for its KRONOS MMR™ project at Chalk River.
South Korea becomes the first country to submit a safeguards technical report to the IAEA for a small modular reactor, setting a precedent for early integration of non-proliferation requirements in nuclear design.
The Environmental Authority criticises the lack of key data on health risks, chemical discharges and construction safety for EDF's two upcoming EPR2 reactors in Seine-Maritime.
Brazil and China have concluded a three-year agreement to secure access to essential radioisotopes for the medical, industrial and scientific sectors, with no financial exchange between the parties.
US-based developer Last Energy will deploy its first domestic microreactor at Texas A&M-RELLIS, marking a strategic step in the advanced modular reactor race.
PGE acquires ZE PAK's stake in the joint venture responsible for developing Poland’s second nuclear site, consolidating a strategic asset within its energy portfolio.
Amazon unveils new visuals of its upcoming nuclear site, marking a key step in its partnership with X-energy to deploy up to 960 MW of modular nuclear capacity in Washington state.
Canadian uranium producer NexGen Energy has completed a A$1bn ($639mn) equity raise split between North American and Australian markets to support the development of its Rook I project.
Tokyo Electric Power Company Holdings is examining the permanent closure of units 1 and 2 at the Kashiwazaki-Kariwa nuclear power plant, the oldest at the site, while continuing efforts to restart unit 6.
The formal expiration of the 2015 nuclear deal with Iran comes as international sanctions have already been reinstated and diplomatic negotiations remain stalled.
Oklo, newcleo and Blykalla partner to develop advanced nuclear fuel infrastructure in the United States, backed by a planned $2bn investment.
enCore Energy has identified three new uranium roll fronts at its Alta Mesa project, with ongoing drilling aimed at defining their extent and accelerating development work.
California-based Radiant will build its first microreactor production facility in Oak Ridge, on a former Manhattan Project site, with production targeted at 50 units per year by 2028.

All the latest energy news, all the time

Annual subscription

8.25€/month*

*billed annually at 99€/year for the first year then 149,00€/year ​

Unlimited access - Archives included - Pro invoice

Monthly subscription

Unlimited access • Archives included

5.2€/month*
then 14.90€ per month thereafter

*Prices shown are exclusive of VAT, which may vary according to your location or professional status.

Since 2021: 30,000 articles - +150 analyses/week.