Flamanville: the EPR power-up postponed until the end of autumn 2025

The Flamanville EPR nuclear reactor will not reach full power until before the end of autumn, postponing the initially scheduled date due to preventive maintenance operations on the primary circuit valves.

Share:

Subscribe for unlimited access to all the latest energy sector news.

Over 150 multisector articles and analyses every week.

For less than €3/week*

*For an annual commitment

*Engagement annuel à seulement 99 € (au lieu de 149 €), offre valable jusqu'au 30/07/2025 minuit.

The schedule for the new generation nuclear reactor at Flamanville is facing a new delay, with full power now expected only before the end of autumn. The French electricity provider has announced that the extension of a shutdown, for checks and maintenance on a primary circuit safety valve, requires a change in the plant’s power-up schedule.

Preventive maintenance on key equipment

The EPR (European Pressurised Reactor) had been shut down since June 19 for commissioning tests, a standard step during the launch of new nuclear installations. On July 2, the operating company decided to keep the reactor offline to intervene on several valves located at the top of the pressuriser. These pieces of equipment play a major role in keeping the primary circuit water at a pressure of 155 bars.

During these tests, it was found that two of the three valves in this circuit were not entirely compliant with the expected sealing requirements. As a result, preventive maintenance was scheduled on the third valve, making use of the teams already mobilised on site.

Impact on industrial schedule and project costs

Restarting the nuclear reactor is now set for October 1, thereby shifting the achievement of 100% power that was initially scheduled for the end of summer. According to a spokesperson for the electricity provider, each reactor start-up requires testing of 1,500 safety criteria, sometimes involving the readjustment of certain settings throughout the tests.

The Flamanville EPR reactor, which was connected to the electricity grid on December 21, 2024, is now twelve years behind the original schedule. The project has experienced numerous technical setbacks since construction began.

Budget overrun and financial challenges

The total project cost has greatly exceeded the initial estimate of €3.3bn ($3.57bn). According to the Cour des comptes, the total project cost is now estimated at €19.3bn ($20.92bn) at 2015 prices, and even €22.6bn ($24.50bn) at 2023 prices, including financing. The Flamanville 3 reactor remains the first of its kind to start in France in twenty-five years.

The large number of safety criteria checked and the technical complexity of the project demonstrate the vigilance required for new reactors of this type, as the nuclear sector continues to face significant scheduling and cost challenges.

NANO Nuclear Energy has been selected to compete in the final round of xTechSearch 9, a US Army initiative aimed at identifying high-potential dual-use technology solutions.
Aalo Atomics completes Series B funding, bringing its total to USD 136 million, to build its first modular nuclear power plant dedicated to data centers.
The Malaysian government initiates a national assessment on nuclear energy feasibility, targeting regions facing energy supply constraints and integrating international regulatory requirements.
The merger between Premier American Uranium and Nuclear Fuels reaches a key milestone following final approval of the arrangement plan by the Supreme Court of British Columbia.
TVA, Google, and Kairos Power formalize an agreement to connect an advanced reactor to the grid, supporting data center energy growth and reinforcing the U.S. nuclear industry.
The U.S. Department of Defense has signed an agreement with X-energy to develop a commercial nuclear microreactor intended to power sensitive military infrastructure.
With cash reserves multiplied sevenfold in nine months, NANO Nuclear intensifies development of its KRONOS MMR and positions itself in the Canadian and U.S. modular nuclear markets.
Equinix signed a preorder for 20 Kaleidos nuclear microreactors and a letter of intent for a power purchase agreement with ULC-Energy, reinforcing its energy supply strategy for its data centers.
The U.S. Department of Energy selects Oklo and its subsidiary Atomic Alchemy for three pilot reactor projects aiming for criticality before July 2026.
The United States Department of Energy has selected eleven companies to build experimental nuclear reactors by July 2026, under a programme aimed at meeting rising electricity demand.
The South African Minister of the Environment has approved Eskom’s authorisation to build a nuclear power plant in Duynefontein, ending appeals lodged by several environmental organisations.
An independent group calls for deep changes to speed up the approval of UK nuclear projects and cut costs linked to a system seen as too slow and complex.
Radiant has signed an agreement with the Department of the Air Force and the Defense Innovation Unit to supply a portable nuclear microreactor, marking a first in mass production for military use.
The Gravelines nuclear power plant, the largest in Western Europe, halted all production after its cooling systems were obstructed by an unexpected influx of jellyfish. EDF plans a gradual restart in the coming days.
The International Atomic Energy Agency confirmed that the tritium concentration in the 14th batch of ALPS-treated water discharged by TEPCO remains well below Japan’s operational limit.
Field studies to determine the location of Kazakhstan’s first nuclear power plant have begun near the village of Ulken, marking a key stage in a project led by Rosatom.
China’s nuclear safety authority has approved the construction of units 1 and 2 at the Jinqimen plant, authorising the start of foundation work for the first reactor.
India unveils a national plan to boost nuclear capacity to 100 GW by 2047, combining large reactors and small modules, with a strengthened regulatory framework and new public-private partnerships.
Belarus offers its expertise to support the construction of Uzbekistan’s first nuclear power plant, as Tashkent accelerates its civil energy projects with new international partnerships.
Start-up HYLENR finalises a strategic $3 mn fundraising to move from pilot phase to industrialisation of its low-energy nuclear reaction systems for industrial heat production.
Consent Preferences