Flamanville: the EPR power-up postponed until the end of autumn 2025

The Flamanville EPR nuclear reactor will not reach full power until before the end of autumn, postponing the initially scheduled date due to preventive maintenance operations on the primary circuit valves.

Share:

Comprehensive energy news coverage, updated nonstop

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access • Archives included • Professional invoice

OTHER ACCESS OPTIONS

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

FREE ACCOUNT

3 articles offered per month

FREE

*Prices are excluding VAT, which may vary depending on your location or professional status

Since 2021: 35,000 articles • 150+ analyses per week

The schedule for the new generation nuclear reactor at Flamanville is facing a new delay, with full power now expected only before the end of autumn. The French electricity provider has announced that the extension of a shutdown, for checks and maintenance on a primary circuit safety valve, requires a change in the plant’s power-up schedule.

Preventive maintenance on key equipment

The EPR (European Pressurised Reactor) had been shut down since June 19 for commissioning tests, a standard step during the launch of new nuclear installations. On July 2, the operating company decided to keep the reactor offline to intervene on several valves located at the top of the pressuriser. These pieces of equipment play a major role in keeping the primary circuit water at a pressure of 155 bars.

During these tests, it was found that two of the three valves in this circuit were not entirely compliant with the expected sealing requirements. As a result, preventive maintenance was scheduled on the third valve, making use of the teams already mobilised on site.

Impact on industrial schedule and project costs

Restarting the nuclear reactor is now set for October 1, thereby shifting the achievement of 100% power that was initially scheduled for the end of summer. According to a spokesperson for the electricity provider, each reactor start-up requires testing of 1,500 safety criteria, sometimes involving the readjustment of certain settings throughout the tests.

The Flamanville EPR reactor, which was connected to the electricity grid on December 21, 2024, is now twelve years behind the original schedule. The project has experienced numerous technical setbacks since construction began.

Budget overrun and financial challenges

The total project cost has greatly exceeded the initial estimate of €3.3bn ($3.57bn). According to the Cour des comptes, the total project cost is now estimated at €19.3bn ($20.92bn) at 2015 prices, and even €22.6bn ($24.50bn) at 2023 prices, including financing. The Flamanville 3 reactor remains the first of its kind to start in France in twenty-five years.

The large number of safety criteria checked and the technical complexity of the project demonstrate the vigilance required for new reactors of this type, as the nuclear sector continues to face significant scheduling and cost challenges.

TRISO-X has started above-ground works on the first U.S. facility dedicated to manufacturing fuel for small modular reactors, marking a key industrial milestone in the deployment of the Xe-100.
The first Russian test rig for the experimental ITER reactor has been delivered to the site in France, marking a major milestone in the international collaboration on nuclear fusion.
Niigata’s governor is expected to approve the restart of one reactor at the Kashiwazaki-Kariwa plant, inactive since the Fukushima accident, reviving a strategic asset for Japan’s energy sector.
Canadian firm Aecon and private developer Norsk Kjernekraft have signed a strategic agreement targeting the deployment of BWRX-300 small modular reactors across several potential locations in Norway.
The South African government has officially lifted the PBMR reactor out of inactivity, launching a public investment programme and transferring the strategic nuclear asset from Eskom to Necsa.
The French Court of Auditors values EDF’s grand carénage at over €100bn, while EPR2 reactors already exceed €67–75bn. The State simultaneously directs regulation, financing, and industrial strategy, raising the risk of conflict of interest.
Belarus commits major public investment to add a third reactor at the Ostrovets plant and initiates studies for a second nuclear site to support national energy demand.
Framatome’s accident-tolerant fuel prototype has completed a second 24-month cycle in a commercial nuclear reactor in the United States, paving the way for a third phase of industrial testing.
The Wylfa site in Wales will host three Rolls-Royce small modular reactors from 2026, marking a strategic investment in the UK’s nuclear expansion.
EDF confirmed that the Flamanville EPR has reached a major milestone, while planning a nearly year-long shutdown in 2026 for extensive regulatory inspections and key component replacement.
EDF is opening access to its long-term nuclear supply contracts to companies consuming more than 7 GWh per year, an adjustment driven by the gradual end of the Arenh mechanism.
South Korean authorities have approved the continued operation of the Kori 2 reactor for an additional eight years, marking a key milestone in the national nuclear strategy.
A public-private consortium is developing a 5 MW thermal microreactor designed to operate without refuelling for ten years, marking a strategic step in Brazil's nuclear innovation efforts.
EDF has announced that the Flamanville EPR reactor is now operating at 80% of its capacity. The target of reaching full output by the end of autumn remains confirmed by the utility.
The accelerated approval of the Aurora facility’s nuclear safety plan marks a strategic milestone in rebuilding a domestic nuclear fuel production line in the United States.
The Industrikraft consortium will invest SEK400mn ($42.2mn) to become a shareholder in Videberg Kraft, marking a new phase in Sweden’s nuclear project led by Vattenfall on the Värö Peninsula.
MVM Group has signed an agreement with Westinghouse to secure VVER-440 fuel supplies from 2028, reducing its reliance on Russia and strengthening nuclear cooperation between Budapest and Washington.
The delivery of nuclear fuel by Russian subsidiary TVEL to the Da Lat research reactor marks a key step in strengthening the nuclear commercial partnership between Moscow and Hanoi.
US supplier X-energy has formalised a graphite supply contract with Japan's Toyo Tanso for the construction of its first four small modular reactors, in partnership with Dow and backed by the US Department of Energy.
US-based Enveniam has signed an agreement with LIS Technologies Inc. to oversee the design and construction of a new laser-based uranium enrichment facility on American soil.

All the latest energy news, all the time

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access - Archives included - Pro invoice

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

*Prices shown are exclusive of VAT, which may vary according to your location or professional status.

Since 2021: 30,000 articles - +150 analyses/week.