Skip to content

Flamanville EPR restarts after four-month technical shutdown

EDF restarted the Flamanville EPR reactor after repairing non-compliant valves, delaying the target of reaching full power output of 1,620 MW until the end of autumn.

Flamanville EPR restarts after four-month technical shutdown

Sectors Nuclear Energy, EPR
Themes Commissioning, Project Development
Countries France

The European Pressurised Reactor (EPR) at Flamanville, located in Normandy, was brought back online during the night of October 14 to 15, following a four-month interruption due to maintenance work on safety equipment. French electricity utility Électricité de France (EDF) confirmed the restart procedure began at 12:33 a.m., two days ahead of the originally scheduled date.

The restart follows the detection of sealing defects on two pressuriser valves during commissioning tests. These critical components ensure the system maintains a pressure of 155 bars in the reactor’s primary circuit, allowing efficient heat transfer to steam generators. The reactor shutdown was extended in July to allow technical intervention on these units.

Gradual power ramp-up under regulatory oversight

According to EDF, the power increase will proceed in stages, first reaching 60 % and then moving to 80 %, the latter requiring approval from the Autorité de sûreté nucléaire et de radioprotection (ASNR). The operator also announced tests involving power variation up to 75 MW in the coming days. The reactor’s nominal capacity of 1,620 MW is expected to be reached before December 21.

Unit Flamanville 3, first connected to the grid in December 2024, is the first new nuclear reactor to go live in France in over 25 years. Initially launched in 2007, the project was originally scheduled for commissioning in 2012.

Costs rise more than sevenfold in fifteen years

The Flamanville 3 construction has faced multiple delays and technical setbacks, significantly increasing its costs. Initially budgeted at €3.3bn ($3.5bn), the total cost is now estimated at €20.4bn ($21.63bn) in 2015 terms, and €23.7bn ($25.13bn) in 2023 terms.

A report from the Cour des comptes published in January confirmed these figures, highlighting the discrepancy between original estimates and actual expenditures. The cost overrun places Flamanville 3 among the most expensive energy infrastructure projects in Europe to date.

Also read

CETY and Hoppy Power Target 2 MW Waste-to-Energy Deployment in Alberta

Clean Energy Technologies has signed a non-binding letter of intent with Hoppy Power to evaluate deployment of its high-temperature pyrolysis technology in Westlock, Alberta, targe

CETY and Hoppy Power Target 2 MW Waste-to-Energy Deployment in Alberta

Framatome Qualifies Ultrasonic Inspection Technology for PWR Reactors in the United States

Framatome has qualified its ultrasonic inspection technology for pressurized water reactor core barrel welds, achieving a 100% success rate in certification tests led by EPRI.

Framatome Qualifies Ultrasonic Inspection Technology for PWR Reactors in the United States

TotalEnergies and EDF Conclude a 12-Year Nuclear Power Deal for 400 MW

TotalEnergies and EDF have signed a 12-year Nuclear Power Allocation Contract effective in 2028, covering approximately 60% of the electricity needs at TotalEnergies' French refini

TotalEnergies and EDF Conclude a 12-Year Nuclear Power Deal for 400 MW