Flamanville EPR extends shutdown until March 30 for maintenance

The Flamanville EPR nuclear reactor will remain shut down until March 30 due to a series of unexpected technical interventions. These operations, which began on February 15, aim to optimise its performance before reaching full power.

Share:

Subscribe for unlimited access to all the latest energy sector news.

Over 150 multisector articles and analyses every week.

For less than €3/week*

*For an annual commitment

*Engagement annuel à seulement 99 € (au lieu de 149 €), offre valable jusqu'au 30/07/2025 minuit.

Since February 15, the Flamanville EPR nuclear reactor has been undergoing an unscheduled shutdown for a series of technical interventions. Initially expected to last for a shorter period, this shutdown will now extend until March 30, according to the operator. These operations are part of the adjustments required for the reactor’s gradual commissioning.

When it was connected to the power grid in December, the operator indicated that the reactor’s power increase would follow a progressive process, potentially requiring multiple scheduled maintenance shutdowns. A company executive noted that such adjustments are common for new installations, describing them as part of a technical break-in phase. These events, referred to as technical contingencies, do not call into question the installation’s design.

Successive technical interventions

The first shutdown, which took place on February 15, was dedicated to an intervention on a cooling circuit using seawater. This system, intended to be activated only in exceptional situations, showed a decline in performance that required correction.

On February 22, the shutdown was extended to allow for work on a temperature sensor in the primary circuit, which is responsible for transferring heat from the reactor core to the steam generators.

Optimisation of the turbo-alternator group

Another extension was decided on February 28 to carry out adjustments on the turbo-alternator group. This key component, consisting of a turbine and an alternator, ensures the conversion of thermal energy into electricity. The intervention focuses on two bearings, crucial elements for guiding and supporting the device’s rotors.

At the same time, additional maintenance work is underway on a second temperature sensor in the primary circuit. These adjustments follow two scheduled production shutdowns that took place after the reactor was connected to the power grid.

Power increase target maintained

The operator still expects to reach 100% power by the summer, despite these interventions. Although initially unforeseen, these technical adjustments are considered part of the reactor’s optimisation process before full-scale operation.

Aalo Atomics completes Series B funding, bringing its total to USD 136 million, to build its first modular nuclear power plant dedicated to data centers.
The Malaysian government initiates a national assessment on nuclear energy feasibility, targeting regions facing energy supply constraints and integrating international regulatory requirements.
The merger between Premier American Uranium and Nuclear Fuels reaches a key milestone following final approval of the arrangement plan by the Supreme Court of British Columbia.
TVA, Google, and Kairos Power formalize an agreement to connect an advanced reactor to the grid, supporting data center energy growth and reinforcing the U.S. nuclear industry.
The U.S. Department of Defense has signed an agreement with X-energy to develop a commercial nuclear microreactor intended to power sensitive military infrastructure.
With cash reserves multiplied sevenfold in nine months, NANO Nuclear intensifies development of its KRONOS MMR and positions itself in the Canadian and U.S. modular nuclear markets.
Equinix signed a preorder for 20 Kaleidos nuclear microreactors and a letter of intent for a power purchase agreement with ULC-Energy, reinforcing its energy supply strategy for its data centers.
The U.S. Department of Energy selects Oklo and its subsidiary Atomic Alchemy for three pilot reactor projects aiming for criticality before July 2026.
The United States Department of Energy has selected eleven companies to build experimental nuclear reactors by July 2026, under a programme aimed at meeting rising electricity demand.
The South African Minister of the Environment has approved Eskom’s authorisation to build a nuclear power plant in Duynefontein, ending appeals lodged by several environmental organisations.
An independent group calls for deep changes to speed up the approval of UK nuclear projects and cut costs linked to a system seen as too slow and complex.
Radiant has signed an agreement with the Department of the Air Force and the Defense Innovation Unit to supply a portable nuclear microreactor, marking a first in mass production for military use.
The Gravelines nuclear power plant, the largest in Western Europe, halted all production after its cooling systems were obstructed by an unexpected influx of jellyfish. EDF plans a gradual restart in the coming days.
The International Atomic Energy Agency confirmed that the tritium concentration in the 14th batch of ALPS-treated water discharged by TEPCO remains well below Japan’s operational limit.
Field studies to determine the location of Kazakhstan’s first nuclear power plant have begun near the village of Ulken, marking a key stage in a project led by Rosatom.
China’s nuclear safety authority has approved the construction of units 1 and 2 at the Jinqimen plant, authorising the start of foundation work for the first reactor.
India unveils a national plan to boost nuclear capacity to 100 GW by 2047, combining large reactors and small modules, with a strengthened regulatory framework and new public-private partnerships.
Belarus offers its expertise to support the construction of Uzbekistan’s first nuclear power plant, as Tashkent accelerates its civil energy projects with new international partnerships.
Start-up HYLENR finalises a strategic $3 mn fundraising to move from pilot phase to industrialisation of its low-energy nuclear reaction systems for industrial heat production.
The regulatory approval granted to PT Thorcon Power Indonesia for its site study on Kelasa Island marks a decisive step toward the development of the country’s first private nuclear project.
Consent Preferences