Flamanville EPR: ASN gives the green light to postpone the replacement of the defective cover

The French nuclear safety authority (ASN) has accepted the postponement of the replacement of the defective cover of the Flamanville EPR reactor vessel until 2025. This deferral is due to manufacturing anomalies in the cover and will require a global maintenance visit during 2025.

Share:

Subscribe for unlimited access to all the latest energy sector news.

Over 150 multisector articles and analyses every week.

For less than €3/week*

*For an annual commitment

*Engagement annuel à seulement 99 € (au lieu de 149 €), offre valable jusqu'au 30/07/2025 minuit.

The nuclear safety authority (ASN) has accepted that EDF postpone to 2025 the replacement of the defective cover of the Flamanville EPR reactor, which is supposed to enter into service in the first quarter of 2024, after a 12-year delay, the nuclear safety watchdog said Friday. The ASN explained that…

The nuclear safety authority (ASN) has accepted that EDF postpone to 2025 the replacement of the defective cover of the Flamanville EPR reactor, which is supposed to enter into service in the first quarter of 2024, after a 12-year delay, the nuclear safety watchdog said Friday.

The ASN explained that “the replacement of the reactor vessel cover before the commissioning of the reactor would lead to a postponement of about one year”. Until now, the safety authority had set December 31, 2024 as the deadline for replacing the cover, which would have forced EDF to shut down its EPR only a few months after its start-up, scheduled for the first quarter of next year.

In a decision of 16 May published on its website, the ASN has agreed to wait for the first full operating cycle of the EPR, i.e. between “15 and 18 months” before changing the part, as requested by the nuclear manufacturer Framatome. The replacement of the tank cover, which has “manufacturing anomalies”, will have to be done in conjunction with a first global maintenance visit planned for 2025. It will last between 4 and 9 months according to the operator EDF.

“The manufacture of the replacement cover is underway at Framatome” for a delivery “scheduled for the end of summer 2024,” the ASN said. This is a crucial part, since it covers the tank that contains the nuclear fuel. The deadline to replace the cover had been stopped by the ASN in 2018, but at the time, the reactor was scheduled to start up in the fall of 2019. In the meantime, the timetable has slipped: “hazards that have occurred since then have led to the commissioning of the reactor being envisaged during the first quarter of 2024”, the ASN recalls.

The ASN specifies that “in the event of a further significant delay in the project, the operator will have to re-examine the possibility of replacing the cover before the reactor is commissioned. After a new delay of 6 months announced in December, the start-up of this reactor, the first of this generation planned on French soil, will take place 12 years after the initial planning. These delays have led to an explosion in the cost of the project, which was launched in 2007 and now stands at 13.2 billion euros, according to EDF, four times the initial budget of 3.3 billion euros.

The Malaysian government initiates a national assessment on nuclear energy feasibility, targeting regions facing energy supply constraints and integrating international regulatory requirements.
The merger between Premier American Uranium and Nuclear Fuels reaches a key milestone following final approval of the arrangement plan by the Supreme Court of British Columbia.
TVA, Google, and Kairos Power formalize an agreement to connect an advanced reactor to the grid, supporting data center energy growth and reinforcing the U.S. nuclear industry.
The U.S. Department of Defense has signed an agreement with X-energy to develop a commercial nuclear microreactor intended to power sensitive military infrastructure.
With cash reserves multiplied sevenfold in nine months, NANO Nuclear intensifies development of its KRONOS MMR and positions itself in the Canadian and U.S. modular nuclear markets.
Equinix signed a preorder for 20 Kaleidos nuclear microreactors and a letter of intent for a power purchase agreement with ULC-Energy, reinforcing its energy supply strategy for its data centers.
The U.S. Department of Energy selects Oklo and its subsidiary Atomic Alchemy for three pilot reactor projects aiming for criticality before July 2026.
The United States Department of Energy has selected eleven companies to build experimental nuclear reactors by July 2026, under a programme aimed at meeting rising electricity demand.
The South African Minister of the Environment has approved Eskom’s authorisation to build a nuclear power plant in Duynefontein, ending appeals lodged by several environmental organisations.
An independent group calls for deep changes to speed up the approval of UK nuclear projects and cut costs linked to a system seen as too slow and complex.
Radiant has signed an agreement with the Department of the Air Force and the Defense Innovation Unit to supply a portable nuclear microreactor, marking a first in mass production for military use.
The Gravelines nuclear power plant, the largest in Western Europe, halted all production after its cooling systems were obstructed by an unexpected influx of jellyfish. EDF plans a gradual restart in the coming days.
The International Atomic Energy Agency confirmed that the tritium concentration in the 14th batch of ALPS-treated water discharged by TEPCO remains well below Japan’s operational limit.
Field studies to determine the location of Kazakhstan’s first nuclear power plant have begun near the village of Ulken, marking a key stage in a project led by Rosatom.
China’s nuclear safety authority has approved the construction of units 1 and 2 at the Jinqimen plant, authorising the start of foundation work for the first reactor.
India unveils a national plan to boost nuclear capacity to 100 GW by 2047, combining large reactors and small modules, with a strengthened regulatory framework and new public-private partnerships.
Belarus offers its expertise to support the construction of Uzbekistan’s first nuclear power plant, as Tashkent accelerates its civil energy projects with new international partnerships.
Start-up HYLENR finalises a strategic $3 mn fundraising to move from pilot phase to industrialisation of its low-energy nuclear reaction systems for industrial heat production.
The regulatory approval granted to PT Thorcon Power Indonesia for its site study on Kelasa Island marks a decisive step toward the development of the country’s first private nuclear project.
Uranium output from American mines surged more than thirteen-fold in 2024, driven by increased investment, exploration drilling and a partial restart of industrial capacity across several key states.
Consent Preferences