popular articles

Environmental Challenges and EDF’s Response to the EPR2 Project

The French Environmental Authority has raised major concerns about the ecological impact of the future EPR2 reactors, prompting EDF to take action.
EDF réagit aux défis environnementaux EPR2

Please share:

Against a backdrop of heightened sensitivity to environmental issues, attention is turning to major energy projects and their ecological impact. In this vein, the recent opinion of the Environmental Authority on EDF’s EPR2 project raises important questions and requires particular attention.

Concerns of the Environmental Authority

On the other hand, the Authority, an independent body responsible for assessing the environmental impact of large-scale projects, recently published a critical opinion on the impact study carried out by EDF for the construction of two new EPR2-type nuclear reactors. Although it did not assess the nuclear safety of the site, its report highlighted several notable environmental concerns.

Impact of Construction and Operation

During the construction phase, the main environmental concerns identified include the health of local populations, noise impact, and the preservation of biodiversity and the natural environment. As for the reactor operation phase, the Authority points the finger at the risks associated with radiological, thermal and chemical releases, as well as the production of nuclear waste and greenhouse gas emissions.

Recommendations for environmental protection

A lack of clarity was noted regarding site reclamation at the end of operations or should the project not be successful. In addition, the authority raised questions about the artificialization of 24 hectares of seabed, suggesting avoidance, reduction or compensation measures.

EDF’s response and commitment

In response, EDF took note of the Authority’s opinion and undertook to publish a detailed response before the public inquiry scheduled for the first quarter of 2024. The Group stressed the importance of environmental issues in the EPR2 project and affirmed its commitment to integrating these concerns into its ongoing discussions with local stakeholders.
Indeed, this situation highlights the importance of rigorous environmental assessment for large-scale projects, particularly in the nuclear power sector. It also reiterates the need for companies like EDF to maintain a transparent and constructive dialogue with the regulatory authorities and the communities concerned.

The Environmental Authority’s recommendation calls on EDF to rethink its environmental approach for the EPR2 reactors. This situation underlines the importance of close collaboration between companies, regulatory authorities and communities to ensure the sustainability and environmental responsibility of large-scale projects.

Register free of charge for uninterrupted access.

Publicite

Recently published in

TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
Washington and Abu Dhabi pave the way for renewed civil nuclear cooperation, aiming to strengthen Emirati technological and energy capabilities within a complex regional strategic context.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
EDF has delayed the restart of the Flamanville EPR to 11 April, citing a new maintenance operation, while keeping its 2025 production forecast unchanged.
EDF has delayed the restart of the Flamanville EPR to 11 April, citing a new maintenance operation, while keeping its 2025 production forecast unchanged.
EDF's plan to build a facility for recycling low-level radioactive metals in Fessenheim is raising significant concerns over health, economics and regulation.
enCore Energy extracted 50,000 pounds of uranium in March from its Alta Mesa site in Texas, while consolidating its operations through strategic leadership appointments.
enCore Energy extracted 50,000 pounds of uranium in March from its Alta Mesa site in Texas, while consolidating its operations through strategic leadership appointments.
Canada's nuclear regulator has issued Ontario Power Generation a construction licence for a BWRX-300 small modular reactor at the Darlington site, marking a key step in the province’s nuclear development.
Canada's nuclear regulator has issued Ontario Power Generation a construction licence for a BWRX-300 small modular reactor at the Darlington site, marking a key step in the province’s nuclear development.
Despite severe Western sanctions targeting Russian energy, Rosatom continues its international nuclear projects and maintains a steady flow of enriched uranium to Europe and the United States, thus supporting the Russian economy through an effective diversification strategy.
Despite severe Western sanctions targeting Russian energy, Rosatom continues its international nuclear projects and maintains a steady flow of enriched uranium to Europe and the United States, thus supporting the Russian economy through an effective diversification strategy.
The agreement between NANO Nuclear Energy and the University of Illinois launches the first university-based installation of the KRONOS MMR reactor, marking the beginning of construction and certification procedures.
Polskie Elektrownie Jądrowe has signed a development agreement with the Westinghouse-Bechtel consortium, ensuring continuity of Poland's first nuclear plant project after a previous contract expired.
Polskie Elektrownie Jądrowe has signed a development agreement with the Westinghouse-Bechtel consortium, ensuring continuity of Poland's first nuclear plant project after a previous contract expired.
Fermi Energia has signed a strategic agreement with Samsung C&T to develop two small modular reactors in Estonia, targeting commercial operation by 2035.
Fermi Energia has signed a strategic agreement with Samsung C&T to develop two small modular reactors in Estonia, targeting commercial operation by 2035.
China National Nuclear Corporation mobilizes international investors and financial partners for a unique nuclear project combining two distinct technologies to simultaneously supply industrial heat and electricity, marking a new strategic step for China's energy industry.
China National Nuclear Corporation mobilizes international investors and financial partners for a unique nuclear project combining two distinct technologies to simultaneously supply industrial heat and electricity, marking a new strategic step for China's energy industry.
The United States Nuclear Regulatory Commission has approved a 20-year extension for the operating licences of Oconee Nuclear Station, reinforcing energy supply in the Carolinas amid growing regional demand.
A radioactive steam leak detected in the reactor building of Flamanville unit 1 forces EDF to postpone its restart by one month, according to the Nuclear Safety and Radiation Protection Authority.
A radioactive steam leak detected in the reactor building of Flamanville unit 1 forces EDF to postpone its restart by one month, according to the Nuclear Safety and Radiation Protection Authority.
French firm Framatome has been selected to modernise control systems at Switzerland’s Leibstadt nuclear plant, as part of a strategic investment aiming to extend its operation through 2045.
French firm Framatome has been selected to modernise control systems at Switzerland’s Leibstadt nuclear plant, as part of a strategic investment aiming to extend its operation through 2045.
The U.S. Department of Energy reopens a $900M envelope to finance the construction of third-generation small modular reactors, aiming to rapidly expand national power capacity.
The U.S. Department of Energy reopens a $900M envelope to finance the construction of third-generation small modular reactors, aiming to rapidly expand national power capacity.

Advertising