EDF postpones Calvados wind farm to 2027 due to faulty drilling tool

EDF is delaying the start-up of the Calvados offshore wind farm by more than two years, citing extended adjustments to a drilling tool vital for installing the sixty-four monopile foundations off Courseulles-sur-Mer.

Share:

EDF confirmed on 5 July that the commercial commissioning of the Calvados offshore wind farm has been pushed back to late 2027, a delay of more than two years against the original schedule. A spokesperson said tests of a drilling system designed specifically for the site remain unfinished, a detail first reported by Bloomberg and later picked up by Agence France-Presse. The project, ten kilometres from the D-Day beaches, had previously targeted start-up in 2025. EDF added that the power-purchase agreements and grid-connection contracts with transmission operator RTE remain unchanged.

A custom tool still under validation
The equipment at issue is a high-capacity drill intended to secure monopiles in a calcareous seabed between twenty and thirty-one metres deep. Several qualification campaigns revealed a need to optimise lubrication circuits and verticality control to sustain an industrial rhythm. These adjustments halted work after four foundations were installed, pushing back the main drilling phase. Saipem, the Italian subsea contractor, will resume monopile installation in August once final internal certification is granted.

EDF stresses that geophysical and geotechnical surveys confirm the expected soil quality, noting that the delay stems solely from fine-tuning the tool. The group has disclosed no quantified cost overrun but says the phasing of the EUR2.3bn ($2.51bn) senior financing package, led by BNP Paribas, will be adjusted with no change in rates. Potential contractual penalties remain under discussion with suppliers, according to a person familiar with the matter. No change is planned in the project’s equity structure.

Infrastructure in place and regional scope
The offshore substation, installed in 2023 by Chantiers de l’Atlantique and Deme, is already connected to the onshore grid and is undergoing no-load tests. Once the sixty-four turbines are operational, the 450-megawatt site will supply the equivalent domestic consumption of more than 630 000 people—virtually the entire Calvados département. EDF notes that the park is Normandy’s second offshore project after Fécamp, which entered service in 2024. “The park will be commissioned at the end of 2027, with a delay of a little over two years,” the press office said in a written statement, adding that long-term production targets remain intact.

Energy company TGS has won a major high-resolution geophysical imaging contract for offshore wind site characterization in Norway, strengthening its position in this rapidly growing market.
ENGIE begins full operation of the Red Sea Wind Energy wind farm in Egypt, increasing its capacity to 650 MW, four months ahead of schedule, now powering over one million homes in the region.
Tokyo Gas, through TOWII Renewables, a joint venture with EWII, purchases two onshore wind projects developed by Finnish company Puhuri, totalling 74.4 MW, marking its expansion beyond the Danish market.
The European Investment Bank grants EWE AG historic €450mn financing for the installation of 2,600 km of underground power lines and the upgrade of over 1,100 substations in Lower Saxony.
Japan’s Ministry of Industry and Siemens Gamesa Renewable Energy launch a strategic partnership to develop local offshore wind supply chains and strengthen the country's industrial competitiveness in this energy sector.
Energiekontor AG confirms financial close for the Nartum wind farm, adding 23 megawatts to its owned portfolio and starting the construction phase in the Rotenburg district, Lower Saxony.
Airloom Energy begins construction of a pilot site in Wyoming to test an innovative turbine aimed at enhancing American energy security in the face of anticipated growth in electricity demand.
ACCIONA Energía transfers the San Juan de Marcona wind farm to Luz del Sur S.A.A., a major player in Peru's energy sector, for up to USD 253 million, pending necessary regulatory approvals.
German operator Encavis AG strengthens its portfolio by acquiring two wind farms in Lower Saxony and Saxony, totalling 59 MW, in a transaction with Energiequelle GmbH, thereby expanding its renewable energy assets.
Ocergy officially launches an industrial project aiming to install by 2028 a new-generation floating wind turbine of over 15 MW, in partnership with EnBW, Kyuden Mirai, and TEPCO Renewable Power.
France officially commissions its first floating wind farm, consisting of three turbines with a combined capacity of 25 megawatts, introducing strategic technology in the Mediterranean, vital for national energy goals.
Inaugurated on 20 June, the five-turbine plant of wpd onshore France feeds 18 MW into the grid and unlocks new tax revenue for four Côtes-d’Armor municipalities.
Statkraft refocuses investments on flexible Nordic hydropower and reduces commitments in offshore wind and hydrogen to lower operating costs, amid an uncertain economic environment and pressured profitability.
Suzlon Group receives third consecutive order from AMPIN Energy Transition to supply 170.1 MW of wind turbines for a project in India's Andhra Pradesh state, strengthening their strategic industrial partnership.
The Muir Mhòr floating wind project secures Aberdeenshire's onshore consent, paving the way for the potential production of one gigawatt of electricity, enough to power up to 1.2 million British homes by the early 2030s.
Iberdrola España and Renfe conclude a virtual power purchase agreement for 370 GWh per year for ten years, strengthening the use of renewable energy in Spanish railway transport.
TotalEnergies has been awarded a concession in the North Sea enabling the development of a 1GW offshore wind project, reinforcing its strategic presence in Germany.
With an annual increase of 14%, global offshore wind capacity now reaches 85.2 gigawatts, driven mainly by China, the United Kingdom, and Germany, while another 27.3 gigawatts are currently under construction.
Seabed exploration begins in Jammerland Bay to validate the placement of sixteen turbines and the cable corridor, the first tangible step before construction of the project led by TotalEnergies and European Energy.
RWE and Østermark Entreprenørforretning celebrate advanced construction of the operational building for Denmark's largest offshore wind farm, promising up to 60 permanent local jobs by 2026.