EDF extends shutdown of Flamanville EPR due to additional maintenance operations

EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.

Share:

Subscribe for unlimited access to all the latest energy sector news.

Over 150 multisector articles and analyses every week.

For less than €3/week*

*For an annual commitment

*Engagement annuel à seulement 99 € (au lieu de 149 €), offre valable jusqu'au 30/07/2025 minuit.

The state-owned group ÉlectricitĂ© de France (EDF) confirmed that the restart of the Flamanville EPR (European Pressurised Reactor) nuclear reactor, initially scheduled for April 12, has been postponed again. This decision follows the identification of new maintenance requirements on equipment located within the nuclear part of the facility. EDF stated that these interventions are essential to ensure the reactor’s power ramp-up is conducted under safety conditions in compliance with regulatory standards.

A controlled power ramp-up process

According to information published on the company’s official website, the ongoing shutdown is now extended until April 17, a date subject to revision depending on technical developments. The EPR reactor, with a nominal capacity of 1,650 megawatts, had been shut down on February 15. Since then, several postponements of the restart date have occurred. EDF reminded that the initial startup of a nuclear reactor is a complex sequence, marked by successive phases of testing, monitoring and verification.

Technical constraints and recurring delays

The group emphasised that adjustments during testing phases may result in changes to the schedule for reconnecting to the national power grid. Sources quoted by La Tribune reported that technical issues with the turbogenerator may limit the reactor’s ability to deliver full power output without major intervention. This operation would notably require the installation of scaffolding in a particularly hard-to-access area.

The Flamanville EPR reactor, located in the Manche department, was first connected to the power grid on December 21, 2024, after a delay of 12 years. Since its connection, two scheduled maintenance shutdowns have already taken place. EDF had warned from the outset that the ramp-up of this 57th reactor in the French fleet would require around ten technical interventions, including some unforeseen ones.

NANO Nuclear Energy has been selected to compete in the final round of xTechSearch 9, a US Army initiative aimed at identifying high-potential dual-use technology solutions.
Aalo Atomics completes Series B funding, bringing its total to USD 136 million, to build its first modular nuclear power plant dedicated to data centers.
The Malaysian government initiates a national assessment on nuclear energy feasibility, targeting regions facing energy supply constraints and integrating international regulatory requirements.
The merger between Premier American Uranium and Nuclear Fuels reaches a key milestone following final approval of the arrangement plan by the Supreme Court of British Columbia.
TVA, Google, and Kairos Power formalize an agreement to connect an advanced reactor to the grid, supporting data center energy growth and reinforcing the U.S. nuclear industry.
The U.S. Department of Defense has signed an agreement with X-energy to develop a commercial nuclear microreactor intended to power sensitive military infrastructure.
With cash reserves multiplied sevenfold in nine months, NANO Nuclear intensifies development of its KRONOS MMR and positions itself in the Canadian and U.S. modular nuclear markets.
Equinix signed a preorder for 20 Kaleidos nuclear microreactors and a letter of intent for a power purchase agreement with ULC-Energy, reinforcing its energy supply strategy for its data centers.
The U.S. Department of Energy selects Oklo and its subsidiary Atomic Alchemy for three pilot reactor projects aiming for criticality before July 2026.
The United States Department of Energy has selected eleven companies to build experimental nuclear reactors by July 2026, under a programme aimed at meeting rising electricity demand.
The South African Minister of the Environment has approved Eskom’s authorisation to build a nuclear power plant in Duynefontein, ending appeals lodged by several environmental organisations.
An independent group calls for deep changes to speed up the approval of UK nuclear projects and cut costs linked to a system seen as too slow and complex.
Radiant has signed an agreement with the Department of the Air Force and the Defense Innovation Unit to supply a portable nuclear microreactor, marking a first in mass production for military use.
The Gravelines nuclear power plant, the largest in Western Europe, halted all production after its cooling systems were obstructed by an unexpected influx of jellyfish. EDF plans a gradual restart in the coming days.
The International Atomic Energy Agency confirmed that the tritium concentration in the 14th batch of ALPS-treated water discharged by TEPCO remains well below Japan’s operational limit.
Field studies to determine the location of Kazakhstan’s first nuclear power plant have begun near the village of Ulken, marking a key stage in a project led by Rosatom.
China’s nuclear safety authority has approved the construction of units 1 and 2 at the Jinqimen plant, authorising the start of foundation work for the first reactor.
India unveils a national plan to boost nuclear capacity to 100 GW by 2047, combining large reactors and small modules, with a strengthened regulatory framework and new public-private partnerships.
Belarus offers its expertise to support the construction of Uzbekistan’s first nuclear power plant, as Tashkent accelerates its civil energy projects with new international partnerships.
Start-up HYLENR finalises a strategic $3 mn fundraising to move from pilot phase to industrialisation of its low-energy nuclear reaction systems for industrial heat production.
Consent Preferences