EDF delays Flamanville EPR restart for the fourth time

The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.

Share:

The restart of the European Pressurised Reactor (EPR) at Flamanville, located in the Manche department, has been delayed for the fourth time by Électricité de France (EDF). The unit, offline since 15 February, was due to resume electricity production on 17 April. The new target date has been set for 21 April, following the completion of additional maintenance works.

A power ramp-up hindered by technical setbacks

According to EDF, the Flamanville 3 teams are currently undertaking reactor restart operations under conditions deemed safe, aiming for grid connection within the updated timeframe. The initial shutdown was prompted by a series of technical interventions, subsequently extended to carry out further work on several critical systems.

The company specified that the interventions involved the seawater cooling system, adjustments to the turbo-alternator group—particularly concerning three mechanical bearings—and maintenance on equipment required for the reactor’s gradual power increase. EDF noted that all affected components are located within the nuclear section of the installation.

Target of full output by summer 2025 remains unchanged

The Flamanville 3 reactor, a third-generation unit, was connected to the national grid in December 2024, twelve years later than originally planned. Since commissioning, it has undergone two scheduled shutdowns, followed by the current suspension due to unanticipated technical issues. EDF had previously stated that the ramp-up of the reactor—France’s 57th nuclear unit—would involve up to ten planned maintenance stops, with potential for unscheduled interventions.

Despite the latest delay, EDF maintains its target timeline for full power output, aiming to reach 100% of nominal capacity by summer 2025, in line with its initial roadmap.

Hunatom announces a strategic alliance with Synthos Green Energy to introduce US small modular reactor technology, strengthening energy ties between Hungary, Poland and the United States.
A joint feasibility study project on Korean i-SMR modular reactors has just been launched for a future nuclear site at the border of the Aure and Heim municipalities, aiming for significant regional industrial impact.
Unit 3 of the Tomari nuclear power plant takes a major step towards restart after its safety equipment was validated by the Japanese regulator.
The Russian Minister of Energy announces strengthened cooperation in uranium and civil nuclear energy in Niger, reinforcing Russia's economic presence in a key sector following the withdrawal of several Western players.
Last Energy reaches a key regulatory step for its PWR-20 microreactor project in Llynfi, advancing towards the objective of securing a site licence by December 2027 from British authorities.
Slovenské elektrárne has signed an agreement with Urenco for the purchase of enriched uranium for the Bohunice and Mochovce nuclear power plants, strengthening the diversification of its supply sources until the mid-2030s.
Emirates Nuclear Energy Company signs two major agreements with Hyundai Engineering & Construction and Westinghouse, strengthening its position in the global civil nuclear market and paving the way for new international industrial opportunities.
First Hydrogen expands its collaboration with the University of Alberta to optimise small modular nuclear reactor design and support green hydrogen development amid the growth of artificial intelligence data centres.
The French and Belgian energy ministers have signed a declaration of intent to strengthen ties between Paris and Brussels on nuclear energy, as Belgium has abandoned its 2003 nuclear phase-out plan.
The United States Nuclear Regulatory Commission has authorised the restart of the Palisades power plant, marking a key milestone for Holtec in reintegrating this reactor into the US energy mix. —
The Genkai nuclear power plant detected the intrusion of three unidentified drones, prompting an immediate investigation by Japanese authorities into this unusual incident with potential national security implications.
KATCO, a joint venture between Orano and Kazatomprom, has started operations at the South Tortkuduk site, backed by a $190mn investment, targeting a production capacity of 4,000 tonnes per year by 2026.
Tehran agrees to host experts from the International Atomic Energy Agency in the coming weeks, excluding any visit to sensitive sites as diplomatic tensions persist with European nations and the United States.
Standard Uranium announces the results of a high-resolution electromagnetic survey at the Corvo project, confirming 29 kilometres of conductive corridors and launching the planning of an inaugural drilling programme for 2026.
NANO Nuclear Energy assembles and tests its annular induction pump prototype, marking progress for its microreactor programmes and paving the way for potential commercialisation of the technology.
Hungary reaffirms its intent to double the capacity of its Paks nuclear power plant in partnership with Rosatom, with concrete works expected to begin in the autumn.
Arabelle Solutions, a subsidiary of EDF, will provide turbine island equipment for the first BWRX-300 small modular reactor project in Canada, marking a milestone for the industrialisation of SMRs in North America.
Framatome will supply nuclear fuel and technical services to ENEC, strengthening the United Arab Emirates’ energy supply chain for the Barakah nuclear plant.
French start-up Stellaria secures €23mn ($25.2mn) in funding to accelerate the design of its fast neutron nuclear reactor, with first fission expected in 2029 and commercial deployment targeted for 2035.
The Bulgarian National Audit Office report highlights persistent delays and contractual irregularities in the implementation of the national repository for low- and intermediate-level radioactive waste.