Skip to content

EDF delays Flamanville EPR restart for the fourth time

The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.

EDF delays Flamanville EPR restart for the fourth time

Sectors Nuclear Energy, EPR
Themes Risks & Events, Project Delays
Countries France

The restart of the European Pressurised Reactor (EPR) at Flamanville, located in the Manche department, has been delayed for the fourth time by Électricité de France (EDF). The unit, offline since 15 February, was due to resume electricity production on 17 April. The new target date has been set for 21 April, following the completion of additional maintenance works.

A power ramp-up hindered by technical setbacks

According to EDF, the Flamanville 3 teams are currently undertaking reactor restart operations under conditions deemed safe, aiming for grid connection within the updated timeframe. The initial shutdown was prompted by a series of technical interventions, subsequently extended to carry out further work on several critical systems.

The company specified that the interventions involved the seawater cooling system, adjustments to the turbo-alternator group—particularly concerning three mechanical bearings—and maintenance on equipment required for the reactor’s gradual power increase. EDF noted that all affected components are located within the nuclear section of the installation.

Target of full output by summer 2025 remains unchanged

The Flamanville 3 reactor, a third-generation unit, was connected to the national grid in December 2024, twelve years later than originally planned. Since commissioning, it has undergone two scheduled shutdowns, followed by the current suspension due to unanticipated technical issues. EDF had previously stated that the ramp-up of the reactor—France’s 57th nuclear unit—would involve up to ten planned maintenance stops, with potential for unscheduled interventions.

Despite the latest delay, EDF maintains its target timeline for full power output, aiming to reach 100% of nominal capacity by summer 2025, in line with its initial roadmap.

Also read

Akkuyu: Rosatom installs 282-tonne polar crane bridge on unit 2

At Akkuyu, in Turkey's Mersin province, Rosatom has installed the metallic structures of the polar crane bridge on unit 2. The 282-tonne crane prepares for closure of the reactor's

Akkuyu: Rosatom installs 282-tonne polar crane bridge on unit 2

New Hampshire Issues Executive Order to Assess Advanced Nuclear Reactor Deployment

New Hampshire's governor has signed an executive order directing the state's Department of Energy to assess conditions for deploying next-generation nuclear reactors, with a roadma

New Hampshire Issues Executive Order to Assess Advanced Nuclear Reactor Deployment

Bulgaria finalizes 138,200 m³ radioactive waste repository near Kozloduy plant

Bulgaria's national construction authority has confirmed completion of the Radiana radioactive waste repository, with a capacity of 138,200 m³. SE RAW now awaits an operating permi

Bulgaria finalizes 138,200 m³ radioactive waste repository near Kozloduy plant