EDF and the French State Agree on €70 Billion Plan for EPR2

EDF and the French state finalize a €70 billion financing plan for six EPR2 nuclear reactors, including a specific territorial coordination framework in Gravelines led by Michel Marbaix, awaiting European approval by 2026.

Share:

EDF (Électricité de France) and the French state have concluded a decisive financial agreement for the construction of six new second-generation European Pressurized Reactor (EPR2) nuclear reactors. This project represents a total investment of approximately €70 billion. Financing will primarily rely on a preferential state loan covering at least half of the construction costs, accompanied by a Contract for Difference (CFD) mechanism. This contract guarantees EDF a maximum price of €100 per megawatt-hour (MWh) at 2024 constant euros, with compensation from the state if the market price falls below this threshold, or payments from EDF if it exceeds.

Launch of Territorial Framework in Gravelines

Simultaneously, Marc Ferracci, Minister responsible for Industry and Energy, officially launched the “Grand Chantier EPR2 Gravelines” initiative. Michel Marbaix has been appointed local coordinator under the authority of the Prefect of the Hauts-de-France region to oversee the territorial preparations for this strategic project. This initiative follows a specific request formulated during the public debate on the Gravelines nuclear reactor project. It comes two years after a similar initiative was launched in Penly, Seine-Maritime, also focused on accommodating two EPR2 reactors.

The first meeting of the local Strategic Committee has already taken place to establish close coordination among local elected officials, economic stakeholders, and state representatives. Michel Marbaix’s role will be to facilitate territorial integration of the project, particularly addressing logistical issues such as mobility, housing, and local employment. This framework aims to ensure continuous dialogue and transparency throughout the project’s stages, directly addressing the needs identified by local communities and stakeholders.

Integrated and National Governance

This territorial initiative in Gravelines forms part of a national strategy coordinated by the Interministerial Delegation for New Nuclear Projects (Délégation Interministérielle au Nouveau Nucléaire, DINN). This delegation ensures overall coherence of the national EPR2 program. Within this framework, Michel Marbaix will have access to all necessary state resources, both local and national, to effectively implement preparatory activities for the project.

This territorial framework also marks the evolution of an approach initiated in 2023 aimed at maximizing local economic benefits through rigorous and collaborative management of large-scale energy projects. Final validation of the financing and territorial framework now depends on the European Commission, which will soon examine its compliance with EU rules regarding state aid. This final step, expected by 2026, is an essential prerequisite to definitively starting construction works.

The French and Belgian energy ministers have signed a declaration of intent to strengthen ties between Paris and Brussels on nuclear energy, as Belgium has abandoned its 2003 nuclear phase-out plan.
The United States Nuclear Regulatory Commission has authorised the restart of the Palisades power plant, marking a key milestone for Holtec in reintegrating this reactor into the US energy mix. —
The Genkai nuclear power plant detected the intrusion of three unidentified drones, prompting an immediate investigation by Japanese authorities into this unusual incident with potential national security implications.
KATCO, a joint venture between Orano and Kazatomprom, has started operations at the South Tortkuduk site, backed by a $190mn investment, targeting a production capacity of 4,000 tonnes per year by 2026.
Tehran agrees to host experts from the International Atomic Energy Agency in the coming weeks, excluding any visit to sensitive sites as diplomatic tensions persist with European nations and the United States.
Standard Uranium announces the results of a high-resolution electromagnetic survey at the Corvo project, confirming 29 kilometres of conductive corridors and launching the planning of an inaugural drilling programme for 2026.
NANO Nuclear Energy assembles and tests its annular induction pump prototype, marking progress for its microreactor programmes and paving the way for potential commercialisation of the technology.
Hungary reaffirms its intent to double the capacity of its Paks nuclear power plant in partnership with Rosatom, with concrete works expected to begin in the autumn.
Framatome will supply nuclear fuel and technical services to ENEC, strengthening the United Arab Emirates’ energy supply chain for the Barakah nuclear plant.
French start-up Stellaria secures €23mn ($25.2mn) in funding to accelerate the design of its fast neutron nuclear reactor, with first fission expected in 2029 and commercial deployment targeted for 2035.
The Bulgarian National Audit Office report highlights persistent delays and contractual irregularities in the implementation of the national repository for low- and intermediate-level radioactive waste.
Bahrain has concluded a civil nuclear agreement with the United States and formalised a commitment of $17bn in public investments in the US market, further strengthening bilateral cooperation.
Kairos Power has installed the vessel for its third test prototype in Oak Ridge, aiming to validate manufacturing methods for its future Hermes reactor supported by the US Department of Energy.
London and Prague formalise a strategic partnership to develop the nuclear sector, focusing on small modular reactors and industrial cooperation on supply chains.
Experts have broadly approved France’s Cigéo deep nuclear waste repository project, highlighting technical uncertainties that demand stronger guarantees for long-term safety.
Uzbekistan advances its nuclear project by signing a protocol with Hungary for the supply and local assembly of dry cooling systems, expanding its industrial partnerships in the region.
Polskie Elektrownie Jądrowe is asking the European Commission to review its $49bn investment to build Poland’s first nuclear power plant, a step required under the Euratom Treaty before any construction permit can be issued.
The International Atomic Energy Agency mission completed on July 11 warns that the National Nuclear Safety Administration must hire staff to oversee a fleet of 59 reactors in operation and 32 more under construction.
Energoatom signed strategic agreements with Westinghouse and Holtec at the Ukraine Recovery Conference, aiming to establish nuclear fuel production and small modular reactor capabilities in the country.
Tehran agrees to reopen its nuclear facilities to the IAEA, aiming to resume negotiations with Washington, while Moscow pushes for a “zero enrichment” agreement without getting involved in supervision.