Flamanville EPR: ASNR Authorizes EDF to Exceed 25% of Nominal Power

The Nuclear Safety Authority (ASNR) has validated the continuation of tests on the Flamanville EPR by authorizing EDF to exceed the 25% nominal power threshold, a crucial step in the power ramp-up program.

Partagez:

The Flamanville EPR, designed to be the most powerful reactor in France, continues its testing program in strict compliance with safety standards. EDF, or Électricité de France, submitted its authorization request in January 2025 as part of the program initiated following the issuance of the operating license by the ASN on May 7, 2024.

Tests and Authorizations

The results from the initial tests, covering the period from the first nuclear fission up to the 25% power level, demonstrated the availability of the reactor core’s monitoring and protection system. The ASNR, responsible for regulating nuclear safety, thereby validated the conformity of the physical test results performed on the reactor core.

By decision on January 31, 2025, the ASNR confirmed that all verifications and inspections, including the analysis of significant events reported by EDF and the corrective actions implemented, posed no obstacle to the continued power ramp-up. These regular inspections ensure the maintenance of a high level of safety throughout the testing phases.

Safety Controls and Monitoring

ASNR’s controls also include the analysis of vibratory phenomena observed during the tests. Olivier Dubois, an ASNR commissioner, indicated that modifications had been made to the reactor to incorporate feedback from identified vibratory phenomena. These corrective measures ensure a better anticipation of deviations in the system’s behavior.

Within its monitoring framework, the ASNR plans to rigorously control the reactor’s power ramp-up until it reaches nominal power, scheduled for the summer of 2025. Moreover, EDF will need to obtain new authorizations to increase power beyond 80% of the nominal capacity, thus ensuring continuous compliance with nuclear safety requirements.

Perspectives on Power Ramp-Up

The progress of the tests and the validation of the safety systems attest to the seriousness of the Flamanville EPR commissioning program. Each testing phase is meticulously monitored to meet the strict regulatory requirements imposed by the ASNR.

The upcoming stages of the testing program, along with the scheduling of additional controls, illustrate the commitment of both the authorities and EDF in the development of a next-generation reactor that conforms to international standards of nuclear safety.

Argentina and Peru have signed an agreement expanding their scientific and technological cooperation in the civil nuclear field, including joint research projects and specialised training programmes for future development.
South Korea's Nuclear Safety and Security Commission officially validates the decommissioning of reactor number one at the Kori plant, initiating an unprecedented project for the national industry scheduled to last until 2037.
Uranium producer enCore Energy surpasses three thousand pounds per day at its Alta Mesa ISR complex and sees three new Texas laws as a strong signal for faster nuclear production permits.
The International Atomic Energy Agency expresses concerns over Iran’s enriched uranium stockpiles following the abrupt suspension of inspections at key sites disrupted by recent attacks whose consequences remain uncertain.
NPCIL has announced an extension until September 30 for industrial proposals concerning Bharat Small Reactors (BSR), following increased interest from the Indian private sector.
A regional court has upheld the award of two new reactors in the Czech Republic to Korea Hydro & Nuclear Power, dismissing Électricité de France’s challenge to the €16bn contract in a decisive step for the national energy programme.
Facing rising temperatures, EDF anticipates cuts in nuclear production starting early July, primarily due to thermal constraints on rivers used for cooling the power plants.
The preliminary agreement launches planning and site assessment for a tailored AP1000 reactor, following two years of feasibility study, and enlists Westinghouse and Hyundai to support Fortum’s regional nuclear expansion.
Donald Trump's unprecedented decision to dismiss Christopher Hanson, a member of the NRC, provokes outrage among former federal officials and raises concerns over the regulatory independence of the U.S. nuclear sector.
Uranium Energy Corp strengthens its position in Anfield Energy Inc., now holding approximately 32.4% of the company’s shares following an investment of CAD19.55mn ($14.82mn), significantly expanding its strategic influence in the uranium market.
New York State plans an advanced nuclear power plant with a 1-gigawatt capacity to meet long-term energy and economic goals, involving significant investment to enhance regional energy independence.
Niger announces its intention to nationalize SOMAÏR, a mining company jointly owned with Orano, provoking strong opposition from the French company and paving the way for further international legal tensions.
Russia strengthens its economic presence in Mali with new agreements, notably in nuclear energy and gold refining, consolidating strategic cooperation within a rapidly evolving geopolitical context.
The US government grants a fourth payment of $100.45 mn to Holtec International to restart the Palisades Nuclear Plant, pending regulatory approval, marking an unprecedented event in the United States.
EDF announces a major agreement with Apollo to raise up to £4.5 billion via bonds to finance the British nuclear project Hinkley Point C, whose costs continue to rise significantly.
The Élysée proposes Anne-Isabelle Étienvre, current Director of Fundamental Research at the CEA, as General Administrator to replace François Jacq, recently appointed President of CNES.
Greek Prime Minister Kyriakos Mitsotakis has announced his country's interest in small modular nuclear reactors to meet national energy challenges and decarbonize the maritime sector within the next fifteen years.
TerraPower, an American nuclear company, secures $650 million funding from investors, including NVIDIA, to develop its Natrium modular reactors in the United States and internationally.
EDF and the French state finalize a €70 billion financing plan for six EPR2 nuclear reactors, including a specific territorial coordination framework in Gravelines led by Michel Marbaix, awaiting European approval by 2026.
Maire S.p.A and Newcleo form strategic partnership to industrialise the development of 200 MW modular nuclear power plants, via a joint venture majority-owned by Nextchem.