The EPR of Flamanville: Chronicle of a Chaotic Journey and the Future of Nuclear

The EPR of Flamanville symbolizes the challenges of French nuclear energy: delays, cost overruns, and loss of expertise. As the future shifts toward EPR2, the revival of this strategic sector remains fraught with uncertainties.

Share:

Subscribe for unlimited access to all the latest energy sector news.

Over 150 multisector articles and analyses every week.

For less than €3/week*

*For an annual commitment

*Engagement annuel à seulement 99 € (au lieu de 149 €), offre valable jusqu'au 30/07/2025 minuit.

The European Pressurized Reactor (EPR) of Flamanville, recently connected to the power grid, marks the culmination of a 17-year project plagued by technical and financial hurdles. While this achievement was long-awaited, it highlights the structural challenges of the French nuclear industry while paving the way for an ambitious revival program.

A challenging construction: key dates and facts

Launched in 2007 at the Flamanville site in Normandy, the EPR was initially scheduled for completion in 2012 at an estimated cost of €3.3 billion. However, technical and organizational issues repeatedly delayed the project.

In 2015, the French Nuclear Safety Authority (ASN) identified serious defects in the reactor vessel, including abnormal steel composition. Additional issues, such as welding defects in the primary circuit and cracks in the concrete containment, further delayed the project. These setbacks have quadrupled the final cost, which now stands at €13.2 billion according to EDF—or €19 billion, according to the French Court of Auditors, when financing overruns are included.

These challenges are not unique to France. In Finland, the Olkiluoto EPR was delayed by 12 years before becoming operational in 2023. In China, the two EPRs at Taishan encountered technical incidents despite starting operations in 2018 and 2019, including early corrosion reported in 2023.

Lessons from a struggling project

The construction of the Flamanville EPR exposed structural weaknesses in the French nuclear industry. One major cause identified is the loss of expertise resulting from a decades-long hiatus in building new reactors. Since Civaux 2, commissioned 25 years ago, no reactor had been built in France, creating a generational gap among engineers and technicians.

The French Court of Auditors also pointed out a lack of coordination among project stakeholders, including EDF and regulatory authorities. Insufficient oversight and overly optimistic initial estimates contributed to a cascade of costly errors.

To address these issues, EDF is developing a new generation of reactors called EPR2. These reactors will feature digital designs and prefabrication techniques to reduce construction errors and delays.

An ambitious but fragile program

In February 2022, President Emmanuel Macron announced the revival of civilian nuclear power with plans to build six EPR2 reactors, alongside an option for eight additional reactors. This program, the first in decades, is part of a dual strategy to reduce greenhouse gas emissions and strengthen energy independence, particularly in light of Russia’s role as a major global supplier of nuclear technology.

However, financial challenges loom large. The initial cost estimate for the six EPR2 reactors has already risen by 30%, reaching €67.4 billion. Heavily indebted, EDF must also address workforce shortages and avoid repeating past mistakes.

Public debates: a democratic challenge

Nuclear energy remains a divisive issue in France. Public consultations held for the upcoming reactors in Penly and Gravelines have highlighted deep concerns over environmental risks, radioactive waste management, and economic impacts.

Luc Marin, chair of the Gravelines debate, summarized public sentiment as “concerns about nuclear risks, radioactivity, waste, and more broadly, the environment.” These discussions aim to enhance transparency in nuclear projects but also contribute to delays.

An international perspective

The revival of French nuclear power extends beyond national borders. EDF is in talks with several countries, including the Netherlands, Poland, and Finland, for new reactor construction. However, competition is fierce. In the Czech Republic, EDF lost a contract to South Korea’s Kepco, underscoring the competitiveness challenges facing the French nuclear sector.

Toward a new era with SMRs

In addition to EPR2 reactors, France is also exploring Small Modular Reactors (SMRs). These smaller, less expensive units could meet specific needs, such as industrial electrification. EDF recently redesigned its Nuward project, although it remains at the prototype stage.

Belarus offers its expertise to support the construction of Uzbekistan’s first nuclear power plant, as Tashkent accelerates its civil energy projects with new international partnerships.
Start-up HYLENR finalises a strategic $3 mn fundraising to move from pilot phase to industrialisation of its low-energy nuclear reaction systems for industrial heat production.
The regulatory approval granted to PT Thorcon Power Indonesia for its site study on Kelasa Island marks a decisive step toward the development of the country’s first private nuclear project.
Uranium output from American mines surged more than thirteen-fold in 2024, driven by increased investment, exploration drilling and a partial restart of industrial capacity across several key states.
NextEra Energy launches the recommissioning of the Duane Arnold nuclear site in Iowa, aiming to inject over 600 MWe back into the grid to meet the growing electricity demand of the American industrial sector.
Nasa has launched a call for tenders for a nuclear reactor on the Moon by 2030, aiming to support American ambitions for a permanent base, despite budget uncertainties and mounting pressure from China and Russia.
Explosions were heard near the Zaporizhzhia nuclear power plant, still under Russian military control, raising fresh concerns over the safety of the site and the Ukrainian energy sector.
Tractebel and NRG-Pallas have formalised the continuation of their technical cooperation at the Pallas research reactor site in Petten, the Netherlands, reinforcing their commitment to a key project in the European nuclear sector.
Tanzania, together with Russia, is starting construction of a uranium plant in Namtumbo for $1.2bn, aiming to boost mining revenues and secure a place in the global nuclear industry.
South Korea forecasts 2.4% annual growth in nuclear generation, with 29 operational reactors by 2035 and export ambitions for the sector.
TEPCO reports a significant net loss due to nuclear compensation charges and debris removal preparations, while its revenues decline over the period.
Rolls-Royce SMR has entered into cooperation agreements with Ĺ koda JS and Curtiss-Wright to accelerate the manufacturing of essential components and the supply of safety systems as part of its international development of modular reactors.
French group Orano returns to profitability in the first half of the year, supported by strong plant performance and stabilisation of international activities, notably after resolving the situation in Niger.
Hunatom announces a strategic alliance with Synthos Green Energy to introduce US small modular reactor technology, strengthening energy ties between Hungary, Poland and the United States.
A joint feasibility study project on Korean i-SMR modular reactors has just been launched for a future nuclear site at the border of the Aure and Heim municipalities, aiming for significant regional industrial impact.
Unit 3 of the Tomari nuclear power plant takes a major step towards restart after its safety equipment was validated by the Japanese regulator.
The Russian Minister of Energy announces strengthened cooperation in uranium and civil nuclear energy in Niger, reinforcing Russia's economic presence in a key sector following the withdrawal of several Western players.
Last Energy reaches a key regulatory step for its PWR-20 microreactor project in Llynfi, advancing towards the objective of securing a site licence by December 2027 from British authorities.
Slovenské elektrárne has signed an agreement with Urenco for the purchase of enriched uranium for the Bohunice and Mochovce nuclear power plants, strengthening the diversification of its supply sources until the mid-2030s.
Emirates Nuclear Energy Company signs two major agreements with Hyundai Engineering & Construction and Westinghouse, strengthening its position in the global civil nuclear market and paving the way for new international industrial opportunities.