Cost Explosion for Belgium’s Energy Island in the North Sea

Belgium’s ambitious artificial island in the North Sea, designed to centralize renewable energy distribution, sees its costs triple, raising concerns about its financial and environmental future.

Share:

Located about 45 kilometers off the Belgian coast, the artificial island named “Princess Elisabeth” is a major initiative in Belgium’s energy transition. This project spans six hectares and consolidates facilities for transporting electricity from multiple offshore wind farms. With the integration of transformers and undersea cables, this platform is meant to serve as an “electric hub” to channel electricity to Belgium and neighboring European countries. Launched in 2021, this project is seen as a key step toward reducing Belgium’s dependence on fossil fuels.

The Belgian government plans to install offshore wind farms with a capacity of 3.5 gigawatts (GW), enough to cover nearly 30% of national energy needs and power all Belgian households. However, the project’s scope and ecological ambitions face an unprecedented surge in costs. Initially estimated at €2.2 billion, the budget for Princess Elisabeth Island was recently re-evaluated to €7 billion, a tripling that alarms political and industrial stakeholders.

Complex Financial and Geopolitical Factors

Belgian Minister of Energy, Tinne Van der Straeten, expressed concern over this cost surge. She attributes it to the Ukraine conflict and Europe’s dependency on Russian gas, which indirectly drove up the prices of equipment and materials needed for the project. “Every country wants to buy the same equipment: cables, AC/DC converters for electricity, and even access to ships,” stated Frédéric Dunon, CEO of Elia Transmission Belgium, the company overseeing the project.

These constraints have also delayed the project’s construction. The costs of materials and the logistical challenges of constructing this island in open sea forced Elia to revise its initial budget and seek financial support from the European Investment Bank, which granted a loan of €650 million to help finance the project.

Impact on Consumers and Political Debate

The Belgian industrial sector, the largest energy consumer, fears that budget overruns will lead to increased electricity bills. Some voices among industrialists and economists are questioning the project’s economic viability and are calling for a revision of its initial objectives. Meanwhile, environmental NGOs and green political parties continue to support the project, emphasizing its positive impacts on marine biodiversity, including the installation of an artificial reef and measures to protect seabirds.

Despite this support, European funding may not be sufficient to cover the budget deficit, and concerns are emerging about the future Belgian government’s ability to support such an investment given the current austerity context.

An Essential Project Amid Climate Uncertainties

Princess Elisabeth Island is part of the European strategy to reach 42.5% renewable energy by 2030. With the rise of far-right politics in Europe and climate-skeptical rhetoric, the completion of this artificial island holds symbolic value for environmentalists, who fear a return to fossil fuels if the project were interrupted.

Minister Van der Straeten stresses the necessity of “transformative projects” for the European Union’s energy future. She highlights that large-scale infrastructure investments are essential to meet carbon neutrality goals. The debate on the sustainability of this North Sea project extends beyond Belgium, shedding light on the financial and political challenges that large-scale ecological initiatives face in Europe.

Final energy consumption in the European industrial sector dropped by 5% in 2023, reaching a level not seen in three decades, with renewables taking a growing role in certain key segments.
Réseau de transport d’électricité is planning a long-term modernisation of its infrastructure. A national public debate will begin on September 4 to address implementation methods, challenges and conditions.
The Spanish Parliament has rejected a package of reforms aimed at preventing another major power outage, plunging the national energy sector into uncertainty and revealing the fragility of the government's majority.
The U.S. government has supported Argentina’s request for a temporary suspension of an order to hand over its stake in YPF, a 16.1 billion USD judgment aimed at satisfying creditors.
The United States Environmental Protection Agency extends compliance deadlines for coal-fired power plant operators regarding groundwater monitoring and the closure of waste ponds.
Eskom aims to accelerate its energy transition through a new dedicated unit, despite a USD22.03bn debt and tariff uncertainties slowing investment.
Several major U.S. corporations announce investments totaling nearly USD 90 billion to strengthen energy infrastructure in Pennsylvania, aimed at powering data centers vital to the rapid growth of the artificial intelligence sector.
Nearly USD92bn will be invested by major American and international groups in new data centres and energy infrastructure, responding to the surge in electricity demand linked to the rise of artificial intelligence.
Nouakchott has endured lengthy power interruptions for several weeks, highlighting the financial and technical limits of the Mauritanian Electricity Company as Mauritania aims to widen access and green its mix by 2030.
Between 2015 and 2024, four multilateral climate funds committed nearly eight bn USD to clean energy, attracting private capital through concessional terms while Africa and Asia absorbed more than half of the volume.
The Global Energy Policies Hub shows that strategic reserves, gas obligations, cybersecurity and critical-mineral policies are expanding rapidly, lifting oil coverage to 98 % of world imports.
According to a report by Ember, the Chinese government’s appliance trade-in campaign could double residential air-conditioner efficiency gains in 2025 and trim up to USD943mn from household electricity spending this year.
Washington is examining sectoral taxes on polysilicon and drones, two supply chains dominated by China, after triggering Section 232 to measure industrial dependency risks.
The 2025-2034 development plan presented by Terna includes strengthening Sicily’s grid, new interconnections, and major projects to support the region’s growing renewable energy capacity.
Terna and NPC Ukrenergo have concluded a three-year partnership in Rome aimed at strengthening the integration of the Ukrainian grid into the pan-European system, with an in-depth exchange of technological and regulatory expertise.
GE Vernova has secured a major contract to modernise the Kühmoos substation in Germany, enhancing grid reliability and integration capacity for power flows between Germany, France and Switzerland.
The National Energy System Operator forecasts electricity demand to rise to 785 TWh by 2050, underlining the need to modernise grids and integrate more clean energy to support the UK’s energy transition.
Terna has signed a guarantee agreement with SACE and the European Investment Bank to finance the Adriatic Link project, totalling approximately €1bn ($1.08bn) and validated as a major transaction under Italian regulations.
India unveils a series of reforms on oil and gas contracts, introducing a fiscal stability clause to enhance the sector’s attractiveness for foreign companies and boost its growth ambitions in upstream energy.
The European Commission is launching a special fund of EUR2.3bn ($2.5bn) to boost Ukraine’s reconstruction and attract private capital to the energy and infrastructure sectors.