New Phase of Safety on Chernobyl’s Original Shelter

The project aimed at securing Chernobyl's original shelter enters a new phase, evaluating structures requiring immediate dismantling or stabilization. This essential initiative extends site safety.

Share:

The project to secure the initial shelter built around Chernobyl’s unit 4 after the 1986 accident enters a new phase. This step aims to determine which parts of the shelter require immediate dismantling and which need stabilization to ensure the site’s long-term safety.

The funding for this project is provided by the International Chernobyl Cooperation Account, with the goal of defining the scope of early deconstruction work for the shelter’s unstable structures. This approach also includes an initial cost estimate and allows the start of the design for the next stage, which encompasses the dismantling of fragile structures.

History and Project Objectives

The original shelter, often called the “sarcophagus,” was erected in just a few months after the accident to contain the radioactive materials of the destroyed unit. In the 1990s, the International Shelter Implementation Plan outlined three main phases: the stabilization of the initial structure, the construction of the New Safe Confinement (NSC) completed in 2017, and finally the dismantling and deconstruction.

The sarcophagus still contains the molten core of the reactor and approximately 200 tonnes of highly radioactive materials. The stability of this structure represents one of the main risks at the site. A project to reinforce the structure was carried out and completed in 2008, but the maximum lifespan of the stabilized structures was estimated until the end of 2023.

License Extension and Project Deadlines

Last year, the license for storing radioactive waste within the shelter was extended from 2023 to 2029. This extension imposes a deadline of 2025 for developing a new design aimed at dismantling “unstable structures with an unacceptably high probability of collapse,” and October 31, 2029, as the deadline for completing the dismantling.

According to the World Nuclear Association, the New Safe Confinement allows engineers to remotely dismantle the 1986 structure that has shielded the reactor remains from the weather since the weeks following the accident. This will facilitate the removal of fuel-containing materials at the bottom of the reactor building, their characterization, compaction, and packaging for disposal. This task is considered the most important step in eliminating the nuclear hazard at the site and marks the real beginning of the dismantling.

Features of the New Safe Confinement

The New Safe Confinement (NSC) is the largest movable land-based structure ever built, with a span of 257 meters, a length of 162 meters, a height of 108 meters, and a total weight of 36,000 tonnes. Designed for a lifespan of 100 years, it allows for the eventual dismantling of the 1986 makeshift shelter and the management of radioactive waste. The structure is also designed to withstand temperatures ranging from -43°C to +45°C, a class-three tornado, and an earthquake of magnitude 6 on the Richter scale.

International Collaboration and Technical Expertise

The International Chernobyl Cooperation Account was established in November 2020 by the European Bank for Reconstruction and Development (EBRD) at the request of the Ukrainian government to support a comprehensive plan for Chernobyl.

UTEM-Engineering LLC was selected as the consultant for this project. The work includes revising the criteria and requirements for the NSC infrastructure to support the dismantling of unstable structures in the shelter. This involves developing all necessary technical specifications, including for lifting equipment, systems for processing contaminated dismantled structures, their further transportation, as well as engineering and control systems for the second phase of the project. Additionally, extra radiation monitoring equipment, radiation-protected personnel transfer boxes, and other related documentation are planned.

Emirates Nuclear Energy Company signs two major agreements with Hyundai Engineering & Construction and Westinghouse, strengthening its position in the global civil nuclear market and paving the way for new international industrial opportunities.
First Hydrogen expands its collaboration with the University of Alberta to optimise small modular nuclear reactor design and support green hydrogen development amid the growth of artificial intelligence data centres.
The French and Belgian energy ministers have signed a declaration of intent to strengthen ties between Paris and Brussels on nuclear energy, as Belgium has abandoned its 2003 nuclear phase-out plan.
The United States Nuclear Regulatory Commission has authorised the restart of the Palisades power plant, marking a key milestone for Holtec in reintegrating this reactor into the US energy mix. —
The Genkai nuclear power plant detected the intrusion of three unidentified drones, prompting an immediate investigation by Japanese authorities into this unusual incident with potential national security implications.
KATCO, a joint venture between Orano and Kazatomprom, has started operations at the South Tortkuduk site, backed by a $190mn investment, targeting a production capacity of 4,000 tonnes per year by 2026.
Tehran agrees to host experts from the International Atomic Energy Agency in the coming weeks, excluding any visit to sensitive sites as diplomatic tensions persist with European nations and the United States.
Standard Uranium announces the results of a high-resolution electromagnetic survey at the Corvo project, confirming 29 kilometres of conductive corridors and launching the planning of an inaugural drilling programme for 2026.
Hungary reaffirms its intent to double the capacity of its Paks nuclear power plant in partnership with Rosatom, with concrete works expected to begin in the autumn.
Arabelle Solutions, a subsidiary of EDF, will provide turbine island equipment for the first BWRX-300 small modular reactor project in Canada, marking a milestone for the industrialisation of SMRs in North America.
Framatome will supply nuclear fuel and technical services to ENEC, strengthening the United Arab Emirates’ energy supply chain for the Barakah nuclear plant.
French start-up Stellaria secures €23mn ($25.2mn) in funding to accelerate the design of its fast neutron nuclear reactor, with first fission expected in 2029 and commercial deployment targeted for 2035.
The Bulgarian National Audit Office report highlights persistent delays and contractual irregularities in the implementation of the national repository for low- and intermediate-level radioactive waste.
Bahrain has concluded a civil nuclear agreement with the United States and formalised a commitment of $17bn in public investments in the US market, further strengthening bilateral cooperation.
Kairos Power has installed the vessel for its third test prototype in Oak Ridge, aiming to validate manufacturing methods for its future Hermes reactor supported by the US Department of Energy.
London and Prague formalise a strategic partnership to develop the nuclear sector, focusing on small modular reactors and industrial cooperation on supply chains.
Experts have broadly approved France’s Cigéo deep nuclear waste repository project, highlighting technical uncertainties that demand stronger guarantees for long-term safety.
Uzbekistan advances its nuclear project by signing a protocol with Hungary for the supply and local assembly of dry cooling systems, expanding its industrial partnerships in the region.
Polskie Elektrownie Jądrowe is asking the European Commission to review its $49bn investment to build Poland’s first nuclear power plant, a step required under the Euratom Treaty before any construction permit can be issued.
The International Atomic Energy Agency mission completed on July 11 warns that the National Nuclear Safety Administration must hire staff to oversee a fleet of 59 reactors in operation and 32 more under construction.