EDF cuts construction time for EPR2 reactors to 70 months

EDF aims to reduce the construction time for EPR2 reactors to less than six years, a central objective of France's nuclear stimulus program.

Share:

Comprehensive energy news coverage, updated nonstop

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access • Archives included • Professional invoice

OTHER ACCESS OPTIONS

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

FREE ACCOUNT

3 articles offered per month

FREE

*Prices are excluding VAT, which may vary depending on your location or professional status

Since 2021: 35,000 articles • 150+ analyses per week

EDF has announced a significant reduction in construction times for its EPR2 reactors, aiming to reach 70 months.
This ambitious program, supported by President Emmanuel Macron, calls for the construction of six EPR2 reactors, with an option for a further eight.
Luc Rémont, CEO of EDF, stresses the importance of re-establishing an industrial cadence in nuclear construction, a sector that has slowed considerably in recent decades.
The French nuclear sector has declined sharply, from producing five reactors a year to building them over two decades. The Flamanville EPR reactor, for example, is 12 years behind schedule.
EDF is seeking to remedy this situation by optimizing its construction processes and enhancing the skills of its teams.

Strategies for achieving objectives

To achieve this time reduction, EDF is implementing measures to improve construction efficiency and quality.
The company relies on repetition and practice of construction processes to hone the skills of its engineers and technicians.
The first reactors in this series may not benefit immediately from these efficiency gains, but subsequent projects should.
Building an EPR2 reactor in 70 months represents a considerable challenge, especially after the experience of the Flamanville EPR reactor, which took almost 17 years to build.
Adjustments to processes and improvements to construction methods are essential if we are to meet our targets.

Impact on the French energy sector

The success of this program could have significant implications for the nuclear industry in France.
By reducing construction times, EDF aims to boost nuclear power generation capacity, thereby contributing to the stability of the country’s energy supply.
This initiative is part of a wider strategy to revitalize the nuclear sector and improve its competitiveness on the global market.
Implementing these reactors more quickly and efficiently could also influence the international perception of the nuclear industry.
The results of current projects will determine EDF’s ability to maintain a leading position in the sector.

Implications for the future of energy

Reducing construction times is a key step towards revitalizing the French nuclear industry.
Achieving the targets set by EDF could redefine the framework for nuclear power generation in the country and provide a solid foundation for future projects.
Future developments will be closely monitored, as they will determine the impact of this revival on the French energy sector.

Endesa, Iberdrola and Naturgy have officially requested the Spanish government to delay the closure of the Almaraz nuclear power plant, originally scheduled for 2028, reigniting the debate on nuclear power's role in the national energy mix.
The reactor vessel for Unit 1 at Egypt’s El Dabaa nuclear plant has been delivered following a 20-day maritime transport from Saint Petersburg, marking a critical milestone in the country’s energy project.
Ontario Power Generation secures CAD3bn ($2.1bn) in public equity financing to construct four modular reactors at Darlington, aiming to ease private sector entry into next-generation nuclear infrastructure.
French developer Newcleo launches a joint venture with Nextchem through a EUR70 mn contract to design the conventional island of its upcoming 200 MW modular nuclear reactors.
NANO Nuclear strengthens its North American strategy by acquiring Global First Power in Canada, securing regulatory rights for its KRONOS MMR™ project at Chalk River.
South Korea becomes the first country to submit a safeguards technical report to the IAEA for a small modular reactor, setting a precedent for early integration of non-proliferation requirements in nuclear design.
The Environmental Authority criticises the lack of key data on health risks, chemical discharges and construction safety for EDF's two upcoming EPR2 reactors in Seine-Maritime.
Brazil and China have concluded a three-year agreement to secure access to essential radioisotopes for the medical, industrial and scientific sectors, with no financial exchange between the parties.
US-based developer Last Energy will deploy its first domestic microreactor at Texas A&M-RELLIS, marking a strategic step in the advanced modular reactor race.
PGE acquires ZE PAK's stake in the joint venture responsible for developing Poland’s second nuclear site, consolidating a strategic asset within its energy portfolio.
Amazon unveils new visuals of its upcoming nuclear site, marking a key step in its partnership with X-energy to deploy up to 960 MW of modular nuclear capacity in Washington state.
Canadian uranium producer NexGen Energy has completed a A$1bn ($639mn) equity raise split between North American and Australian markets to support the development of its Rook I project.
Tokyo Electric Power Company Holdings is examining the permanent closure of units 1 and 2 at the Kashiwazaki-Kariwa nuclear power plant, the oldest at the site, while continuing efforts to restart unit 6.
The formal expiration of the 2015 nuclear deal with Iran comes as international sanctions have already been reinstated and diplomatic negotiations remain stalled.
Oklo, newcleo and Blykalla partner to develop advanced nuclear fuel infrastructure in the United States, backed by a planned $2bn investment.
enCore Energy has identified three new uranium roll fronts at its Alta Mesa project, with ongoing drilling aimed at defining their extent and accelerating development work.
California-based Radiant will build its first microreactor production facility in Oak Ridge, on a former Manhattan Project site, with production targeted at 50 units per year by 2028.
EDF restarted the Flamanville EPR reactor after repairing non-compliant valves, delaying the target of reaching full power output of 1,620 MW until the end of autumn.
Nano Nuclear and the University of Illinois will begin drilling operations for the KRONOS MMR™ reactor on October 24, marking a key step toward commercialisation of the nuclear project on the Urbana-Champaign campus.
Natura Resources is finalising construction of the MSR-1, an advanced liquid-fuel nuclear reactor, with a planned launch in 2026 on the Abilene Christian University campus.

All the latest energy news, all the time

Annual subscription

8.25$/month*

*billed annually at 99$/year for the first year then 149,00$/year ​

Unlimited access - Archives included - Pro invoice

Monthly subscription

Unlimited access • Archives included

5.2$/month*
then 14.90$ per month thereafter

*Prices shown are exclusive of VAT, which may vary according to your location or professional status.

Since 2021: 30,000 articles - +150 analyses/week.