popular articles

Slovakian nuclear power plant: Mochovce 3 reaches 90% capacity

The Mochovce nuclear power plant in Slovakia is gradually increasing the output of its third reactor unit to 90%, with a view to reaching 100%. This marks the end of the energy start-up phase, strengthening the country's energy supply and paving the way for Slovakia to become a net energy exporter.

Please share:

After methodically carrying out a series of ramp-up tests, the Mochovce nuclear power plant in Slovakia has increased the capacity of its third reactor unit to 90%, bringing it closer to the final target of 100% total power, which will mark the end of the energy start-up phase and make a significant contribution to the country’s energy supply.

Energy progress at Slovakia’s Mochovce nuclear power plant: Gradual power increase for third reactor unit

The start-up process involves gradual increases in power, with tests carried out before increasing the level. The unit’s output was increased to 55% in March and to 75% in July.

“After successfully completing all energy start-up tests at a power level of up to 75% of the reactor’s rated power and submitting the test report to the Slovak Nuclear Regulatory Authority, Slovenské elektrárne has increased the reactor power of the third unit of the Mochovce nuclear power plant to 90%,” said the company.

To date, the unit has supplied around 650,000 MWh of electricity to the grid, which, according to Slovenské elektrárne, corresponds to the annual consumption of 260,000 households.

“Testing at 75% power level was completed without delay, bringing us closer to full power at Reactor 3,” said Mochovce plant manager Martin Mráz.

On the road to full power: Mochovce nuclear power plant nears final commissioning stage

Once testing has been completed at 90%, the reactor’s power will be increased to 100%.

“Full functionality of the third unit and achievement of the project parameters will be confirmed by a 144-hour demonstration at 100% power, which will end the energy start-up phase,” said Slovenské elektrárne. “This milestone should be reached between September and October.”

Construction of the first two VVER-440 units at the four-unit Mochovce power plant began in 1982. Work on units 3 and 4 began in 1986, but stopped in 1992. The first two reactors were completed and went into service in 1998 and 1999 respectively, and a project to complete units 3 and 4 was launched ten years later. The schedule for unit 4 was drawn up one or two years later than for unit 3.

Each unit will be able to supply 13% of Slovakia’s electricity needs when operating at full capacity. Slovakia hopes to become a net energy exporter once the two new Mochovce units are both operational.

Register free of charge for uninterrupted access.

Publicite

Recently published in

TerraPower has informed the UK regulator of its intention to submit the Natrium reactor design for evaluation under the Generic Design Assessment (GDA) process, the first step toward international deployment of this nuclear technology.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Framatome and Sizewell C have signed a contract for the supply, qualification, and pre-assembly of conventional instrumentation for the EPR reactors under construction at Sizewell, strengthening their collaboration on this large-scale project.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Uzbekistan has launched the construction of auxiliary buildings for its future modular nuclear reactor, the first export project for the Russian RITM-200N technology.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
Holtec International has submitted its final proposal to Great British Nuclear as part of the competition to deploy several small modular reactors in the UK, joining GE Hitachi and Rolls-Royce SMR in the decisive phase.
The restart of the Flamanville EPR reactor, initially scheduled for 17 April, has now been postponed to 21 April following extended maintenance operations, according to a statement from Électricité de France.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
EDF announced on April 10 the extension of the shutdown of the Flamanville EPR nuclear reactor, initially scheduled to restart on April 12, due to new maintenance operations within its nuclear zone.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
The French National Assembly has launched a mission to analyse nuclear pricing and anticipate the effects of the 2026 tariff reform amid heightened tensions over energy costs.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
GE Hitachi and Rolls-Royce SMR have submitted their final offer as part of the modular reactor selection process led by Great British Nuclear in the United Kingdom.
Washington and Abu Dhabi pave the way for renewed civil nuclear cooperation, aiming to strengthen Emirati technological and energy capabilities within a complex regional strategic context.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
Duke Energy has submitted a request to the US Nuclear Regulatory Commission to extend the operation of its Robinson plant by 20 years, supporting energy stability in the Carolinas.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
India's largest power producer, NTPC, paves the way for small modular reactors to modernize its aging energy infrastructure and strengthen energy security through significant international partnerships.
EDF has delayed the restart of the Flamanville EPR to 11 April, citing a new maintenance operation, while keeping its 2025 production forecast unchanged.
EDF has delayed the restart of the Flamanville EPR to 11 April, citing a new maintenance operation, while keeping its 2025 production forecast unchanged.
EDF's plan to build a facility for recycling low-level radioactive metals in Fessenheim is raising significant concerns over health, economics and regulation.
enCore Energy extracted 50,000 pounds of uranium in March from its Alta Mesa site in Texas, while consolidating its operations through strategic leadership appointments.
enCore Energy extracted 50,000 pounds of uranium in March from its Alta Mesa site in Texas, while consolidating its operations through strategic leadership appointments.
Canada's nuclear regulator has issued Ontario Power Generation a construction licence for a BWRX-300 small modular reactor at the Darlington site, marking a key step in the province’s nuclear development.
Canada's nuclear regulator has issued Ontario Power Generation a construction licence for a BWRX-300 small modular reactor at the Darlington site, marking a key step in the province’s nuclear development.
Despite severe Western sanctions targeting Russian energy, Rosatom continues its international nuclear projects and maintains a steady flow of enriched uranium to Europe and the United States, thus supporting the Russian economy through an effective diversification strategy.
Despite severe Western sanctions targeting Russian energy, Rosatom continues its international nuclear projects and maintains a steady flow of enriched uranium to Europe and the United States, thus supporting the Russian economy through an effective diversification strategy.
The agreement between NANO Nuclear Energy and the University of Illinois launches the first university-based installation of the KRONOS MMR reactor, marking the beginning of construction and certification procedures.
Polskie Elektrownie Jądrowe has signed a development agreement with the Westinghouse-Bechtel consortium, ensuring continuity of Poland's first nuclear plant project after a previous contract expired.
Polskie Elektrownie Jądrowe has signed a development agreement with the Westinghouse-Bechtel consortium, ensuring continuity of Poland's first nuclear plant project after a previous contract expired.
Fermi Energia has signed a strategic agreement with Samsung C&T to develop two small modular reactors in Estonia, targeting commercial operation by 2035.
Fermi Energia has signed a strategic agreement with Samsung C&T to develop two small modular reactors in Estonia, targeting commercial operation by 2035.
China National Nuclear Corporation mobilizes international investors and financial partners for a unique nuclear project combining two distinct technologies to simultaneously supply industrial heat and electricity, marking a new strategic step for China's energy industry.
China National Nuclear Corporation mobilizes international investors and financial partners for a unique nuclear project combining two distinct technologies to simultaneously supply industrial heat and electricity, marking a new strategic step for China's energy industry.
The United States Nuclear Regulatory Commission has approved a 20-year extension for the operating licences of Oconee Nuclear Station, reinforcing energy supply in the Carolinas amid growing regional demand.
A radioactive steam leak detected in the reactor building of Flamanville unit 1 forces EDF to postpone its restart by one month, according to the Nuclear Safety and Radiation Protection Authority.
A radioactive steam leak detected in the reactor building of Flamanville unit 1 forces EDF to postpone its restart by one month, according to the Nuclear Safety and Radiation Protection Authority.
French firm Framatome has been selected to modernise control systems at Switzerland’s Leibstadt nuclear plant, as part of a strategic investment aiming to extend its operation through 2045.
French firm Framatome has been selected to modernise control systems at Switzerland’s Leibstadt nuclear plant, as part of a strategic investment aiming to extend its operation through 2045.
The U.S. Department of Energy reopens a $900M envelope to finance the construction of third-generation small modular reactors, aiming to rapidly expand national power capacity.
The U.S. Department of Energy reopens a $900M envelope to finance the construction of third-generation small modular reactors, aiming to rapidly expand national power capacity.

Advertising