Skip to content

Poland extends agreement with Westinghouse and Bechtel for first nuclear power plant

Polskie Elektrownie Jądrowe has extended its engineering contract with the American consortium, securing continued technical studies and maintaining the timeline for the Lubiatowo-Kopalino nuclear plant.

Poland extends agreement with Westinghouse and Bechtel for first nuclear power plant

Sectors Nuclear Energy
Themes Investments & Transactions
Companies Bechtel
Countries Poland, United States

Polskie Elektrownie Jądrowe (PEJ), a company 100% owned by the Polish State Treasury, has signed an amendment to its Engineering Development Agreement with the Westinghouse-Bechtel consortium. This extension allows for the continuation of design work for the nuclear power plant planned at Lubiatowo-Kopalino, in the Pomeranian region.

Technical work remains on schedule

The revised agreement covers ongoing design of the nuclear and turbine islands, as well as the balance of plant. It also includes additional in-depth geological survey campaigns. These works are essential to maintain the initial schedule, while enabling progress in negotiations for the future Engineering, Procurement and Construction (EPC) contract.

According to PEJ, certain tasks initially planned under the EPC contract have been brought forward into this amendment to prevent delays. Field work continues while technical documentation required for upcoming regulatory phases is being finalised.

Public funding and EU approval

On December 30, PEJ received state treasury bonds with a nominal value of PLN4.6bn ($1.27bn), enabling a capital increase. This funding is part of public support approved by the European Commission in early December. The funds will cover preparatory works, technical studies, and internal site infrastructure.

In parallel, discussions are ongoing with financial institutions, primarily foreign ones, to secure the loans necessary for the project’s next stages. The Polish government plans to allocate PLN60.2bn ($16.7bn) in public funds to the project by 2030. Additional funding is expected to come from export credit agencies, including the Export-Import Bank of the United States.

2033 target for commissioning

The Polish-American consortium is currently developing a site-specific design for three AP1000 reactors, a technology from Westinghouse Electric Company. Initial earthworks are scheduled for the first half of 2026, alongside more than 1,000 geotechnical drillings totalling 15 kilometres in depth and 7,000 laboratory tests.

The target date for commercial operation of the first reactor remains set for 2033. PEJ is also preparing the documentation needed to apply for the required administrative permits to begin construction.

Also read

Akkuyu: Rosatom installs 282-tonne polar crane bridge on unit 2

At Akkuyu, in Turkey's Mersin province, Rosatom has installed the metallic structures of the polar crane bridge on unit 2. The 282-tonne crane prepares for closure of the reactor's

Akkuyu: Rosatom installs 282-tonne polar crane bridge on unit 2

New Hampshire Issues Executive Order to Assess Advanced Nuclear Reactor Deployment

New Hampshire's governor has signed an executive order directing the state's Department of Energy to assess conditions for deploying next-generation nuclear reactors, with a roadma

New Hampshire Issues Executive Order to Assess Advanced Nuclear Reactor Deployment

Bulgaria finalizes 138,200 m³ radioactive waste repository near Kozloduy plant

Bulgaria's national construction authority has confirmed completion of the Radiana radioactive waste repository, with a capacity of 138,200 m³. SE RAW now awaits an operating permi

Bulgaria finalizes 138,200 m³ radioactive waste repository near Kozloduy plant