In Galatini, Iberdrola inaugurates Askio III

In Galatini, Greece, Iberdrola has just commissioned the Askio III onshore wind farm after 6 months of construction.

Share:

In Galatini, Greece, Iberdrola has just commissioned the Askio III onshore wind farm after 6 months of construction.

A complex geography

In Galatini, the wind farm has 12 installations with blades of 70 meters long each. Their capacity amounts to 50MW. They will be able to supply more than 54,000 homes with electricity each year.

In addition, their commissioning required the deployment of 30 kilometers of cable between internal medium-voltage circuits and an evacuation line. This construction has led to the expansion of the Lygeri substation. In Galatini, the completion of Askio III in just 6 months is quite spectacular considering the geographical location of the plant.

The region of Western Macedonia is indeed very mountainous with an altitude of 1500 meters above sea level. Completion of the project before the onset of winter is timely as snow accumulation would have delayed the project. The team was able to complete the civil works, transport and assembly of the wind turbines simultaneously.

With an average of 75 workers on site, the project will have employed up to 150 people, most of them local. The transport of the blades used the Blade Lifter technology, allowing to reduce the environmental impact. Indeed, its articulated platform allows the blades to be rotated and tilted in order to make them progress in spite of the obstacles present in the mountain.

A recognized company

Thus, no new roads were required for the Askio III project in Galatini. In particular, the facility will be connected to the grid connection point with its predecessor, the Askio II wind farm. Its need for storage space will be minimized thanks to a smaller platform area.

With this new wind farm in Galatini, Greece, the Iberdrola Group is expanding its installed capacity to 365MW in the country. It is currently building a third project, the 18MW Rokani project. In addition, it is also located in Greece, near Athens.

Iberdrola has an international reach with 39,000 MW of installed renewable capacity worldwide. Its commitment to the energy transition goes back some twenty years. The company is specialized in wind energy.

Iberdrola continues to build on this momentum and announces a global investment of €17 billion in renewable energy by 2025. 24% of its future projects will be deployed in the European Union. Finally, the company will allocate more than €4.2 billion to onshore wind projects.

Energiekontor AG has secured contracts for four wind projects with a total capacity of 125 megawatts, following the Federal Network Agency's May 2025 tender in Germany.
Ecopetrol S.A. finalises the acquisition of Wind Autogeneración from Enel S.A.S., thereby taking over the Windpeshi wind project in Colombia, with a planned capacity of 205 MW, aimed at the Colombian oil group's energy self-consumption.
Oceanic Wind Energy Inc. and Coast Tsimshian Enterprises Ltd. secured an exclusive investigative use permit in the Hecate Strait, paving the way for Canada's first major offshore wind project, targeting capacity of up to 700 MW.
German manufacturer Nordex will supply 13 N163/6.X wind turbines to developer SAB WindTeam for a 91 MW wind farm in Brandenburg, with commissioning scheduled for early 2027 and an extended 20-year service agreement.
German company NeXtWind signs historic €1.4 billion debt financing to accelerate expansion and modernisation of its onshore wind farms and reach a total capacity of 3 GW by 2028.
Energy company TGS has won a major high-resolution geophysical imaging contract for offshore wind site characterization in Norway, strengthening its position in this rapidly growing market.
Iberdrola Australia secures crucial approval from Australian authorities to begin metocean studies for its 3GW Aurora Green offshore project off the coast of Victoria, marking a decisive stage in its development.
ENGIE begins full operation of the Red Sea Wind Energy wind farm in Egypt, increasing its capacity to 650 MW, four months ahead of schedule, now powering over one million homes in the region.
Tokyo Gas, through TOWII Renewables, a joint venture with EWII, purchases two onshore wind projects developed by Finnish company Puhuri, totalling 74.4 MW, marking its expansion beyond the Danish market.
The European Investment Bank grants EWE AG historic €450mn financing for the installation of 2,600 km of underground power lines and the upgrade of over 1,100 substations in Lower Saxony.
Japan’s Ministry of Industry and Siemens Gamesa Renewable Energy launch a strategic partnership to develop local offshore wind supply chains and strengthen the country's industrial competitiveness in this energy sector.
Energiekontor AG confirms financial close for the Nartum wind farm, adding 23 megawatts to its owned portfolio and starting the construction phase in the Rotenburg district, Lower Saxony.
Airloom Energy begins construction of a pilot site in Wyoming to test an innovative turbine aimed at enhancing American energy security in the face of anticipated growth in electricity demand.
ACCIONA Energía transfers the San Juan de Marcona wind farm to Luz del Sur S.A.A., a major player in Peru's energy sector, for up to USD 253 million, pending necessary regulatory approvals.
German operator Encavis AG strengthens its portfolio by acquiring two wind farms in Lower Saxony and Saxony, totalling 59 MW, in a transaction with Energiequelle GmbH, thereby expanding its renewable energy assets.
Ocergy officially launches an industrial project aiming to install by 2028 a new-generation floating wind turbine of over 15 MW, in partnership with EnBW, Kyuden Mirai, and TEPCO Renewable Power.
France officially commissions its first floating wind farm, consisting of three turbines with a combined capacity of 25 megawatts, introducing strategic technology in the Mediterranean, vital for national energy goals.
Inaugurated on 20 June, the five-turbine plant of wpd onshore France feeds 18 MW into the grid and unlocks new tax revenue for four Côtes-d’Armor municipalities.
Statkraft refocuses investments on flexible Nordic hydropower and reduces commitments in offshore wind and hydrogen to lower operating costs, amid an uncertain economic environment and pressured profitability.
Suzlon Group receives third consecutive order from AMPIN Energy Transition to supply 170.1 MW of wind turbines for a project in India's Andhra Pradesh state, strengthening their strategic industrial partnership.