The administrative court of appeal of Lyon has authorized the opening of a hydroelectric power plant in Haute-Savoie. This decision was welcomed by the mayor of the town and criticized by the association France Nature Environnement Auvergne-Rhône-Alpes, which deplores an attack on biodiversity.

Share:

A hydroelectric power station, recently built on the river Sallanche in Haute-Savoie and suspended last year by the justice, will be able to open while waiting for a judgement on the merits, the mayor of the concerned commune told AFP on Saturday.

This opening, scheduled for the next few days, was made possible by an order issued Thursday by the Lyon administrative court of appeal, which overturned a previous ruling issued last December by the Grenoble administrative court. The case was brought by the France Nature Environnement Auvergne-Rhône-Alpes association, which blocked the project and ordered “the site to be restored within 12 months”.

However, “it does not appear that the disputed structure (…) could be considered as an obstacle to ecological continuity,” the Lyon Court of Appeal ruled. “The execution of the judgment of the administrative court of Grenoble is thus suspended until the administrative court of appeal of Lyon decides on the merits of the case,” she continued. The mayor of Sallanches, Georges Morand, welcomed the decision, saying that the appeal by FNE was “ecological nonsense”, and recalling that the company had invested 6 million euros in this brand new plant. It should now open as soon as possible, he added: “We will have no problem because we had already tested before. So this week, if there is water, we’ll go.

Xavier Roseren, Member of Parliament for Haute-Savoie, also said he was pleased with “this decision, which makes sense in the context of energy sovereignty, inflation and the reduction of greenhouse gas emissions”. The plant “will supply the equivalent of the consumption of 20% of the households in Sallanches with renewable energy,” he wrote on Facebook.

Conversely, the FNE deplored in a statement “a serious mistake for biodiversity”, ensuring that it does not “give up (in the face of a) temporary decision”. “The construction of the power plant on a site identified as a biological reservoir is detrimental to the health of the rivers and the survival of biodiversity. This river was however identified as a torrent that could not be developed,” she said. Judgment on the merits is expected late this year or early next year, according to the mayor.

Minesto has completed a reorganization that led to a 35% reduction in fixed costs and a focus on its future commercial projects. This reorganization includes geographical streamlining, a new management team, and a realignment of product development priorities.
Eco Wave Power shareholders approve renewed authorization to repurchase American Depositary Shares representing up to 10% of the company's total share capital, during the 2025 Annual General Meeting held in Stockholm, Sweden.
Proteus Marine Renewables' AR1100 tidal turbine, with a capacity of 1.1MW, obtains official Japanese certification and starts supplying electricity to the national grid after meeting stringent safety and reliability standards.
Swedish company Minesto will lead a consortium awarded €2.1 million funding to install an autonomous tidal-powered microgrid in the Faroe Islands aimed at off-grid communities.
Eco Wave Power Global AB will officially launch the first U.S. pilot wave energy project at the Port of Los Angeles on September 9, in partnership with AltaSea, an organization specializing in innovative maritime solutions.
The Burundian government officially launches the first phase of the Jiji-Mulembwe hydroelectric complex, a strategic 49.5 MW capacity project aimed at enhancing national energy supply through substantial international financing.
The Russian company InterRAO anticipates a 4% annual reduction in electricity exports, primarily impacted by a significant decrease in shipments to China due to limited hydroelectric production and rising domestic demand.
The global hydropower plants market is projected to reach USD 318.3 billion by 2032, driven by growing demand for renewable energy, increased adoption of micro-hydropower plants, and heightened government support, according to a recent report.
Port-au-Prince is without electricity after residents of Mirebalais forcibly shut down a hydroelectric plant protesting government inaction amid escalating gang-related violence.
Globeleq acquires a majority stake in Lunsemfwa Hydro Power Company, marking its entry into the Zambian energy market with two hydropower plants and a solar project.
The Asian Development Bank provides nearly a million dollars for improving Kyrgyzstan's energy system and considers an additional $150 million for the strategic Kambarata-1 hydroelectric dam.
Ukraine’s national operator Ukrhydroenergo announces an ambitious two-phase reconstruction plan to swiftly restore the Kakhovka hydroelectric dam, destroyed during the conflict, at an estimated cost of up to one billion dollars.
Swedish energy developer Minesto confirmed a 25% increase in output from its Dragon 12 tidal system, marking a key step towards commercial deployment in the Faroe Islands.
Axpo will start major works in May around its Beznau hydropower plant to meet the requirements of its new operating permit valid until 2052, including the creation of new ecological habitats.
Norwegian group Orkla announces the sale of its hydropower portfolio through two separate transactions, valuing the assets at NOK 6.1 billion. A strategic decision aimed at streamlining operations and refocusing priorities.
Eastern Kazakhstan plans to construct five hydropower plants with a total capacity of 74.3 MW, consolidating its position as a national leader in hydropower despite challenges related to land allocation.
Adani Group, a leader in renewable energy, plans to develop 10 GW of hydroelectric capacity in several Asian and African countries, including Bhutan, Nepal, Kenya, and Vietnam, to strengthen its green portfolio and achieve carbon neutrality by 2050.
The international technology group ANDRITZ has been selected to upgrade one of the units of Norway's largest run-of-river hydropower plant, Vamma, increasing its capacity by 22% while improving its energy efficiency.
Eco Wave Power and Lian Tat Sign a Historic Agreement to Develop the First Onshore Marine Energy Installation in Asia, Starting with a 100KW Pilot Project in Taiwan.
Uganda is undertaking the construction of three hydropower plants on the Nile to add 1,632 MW to its electricity capacity while exploring nuclear initiatives to diversify its energy mix in response to growing demand.