Pipeline between Barcelona and Marseille: an ambitious but risky project

The hydrogen pipeline project between Barcelona and Marseille, which was discussed today on the sidelines of a summit in Spain of southern EU countries, is considered essential for Europe's energy sovereignty, but is based on a risky bet.

Partagez:

The ambitious “green” hydrogen pipeline project between Barcelona and Marseille H2Med, officially launched Friday in Alicante, Spain, will be operational in 2030 and cost about 2.5 billion euros, French and Spanish leaders announced. This project should be “completed by 2030,” said French President Emmanuel Macron after a meeting with the heads of government of Spain and Portugal, Pedro Sanchez and Antonio Costa.

For his part, Mr. Sanchez said that the cost of construction of H2Med should “approach 2.5 billion euros. This pipe will transport by 2030 some two million tons of hydrogen per year, he also said.

This project will be submitted by December 15 to the European Commission in order to benefit from the status of “project of common interest” and therefore European funding, added Macron. Present at the meeting between the Spanish, French and Portuguese leaders, the President of the European Commission, Ursula von der Leyen, “warmly welcomed” this agreement between the three countries, which “goes in the right direction”.

This undersea pipeline is designed to transport so-called “green” hydrogen, produced from renewable electricity, from the Iberian Peninsula, which aims to become a champion of this energy of the future, to France and the north of the EU.

This project replaces the “MidCat”, launched in 2003 to link the French and Spanish gas networks via the Pyrenees, but finally abandoned due to its lack of economic interest, the opposition of environmentalists and that of Paris.

Schedule, cost, route… Here is what we know at this stage about this initiative launched jointly by Madrid, Lisbon and Paris. What does this project consist of? Called “H2Med” or “BarMar” (a contraction of Barcelona-Marseille), this undersea pipeline is intended to transport gas and then so-called “green” hydrogen – because it is made from renewable electricity – from Spain to France and the north of the EU.

 

This project, announced on October 20 at a European summit, replaces the “MidCat”, launched in 2003 to link the French and Spanish gas networks via the Pyrenees, but finally abandoned because of its lack of economic interest, the opposition of environmentalists and that of Paris.

What are the objectives of the “Corridor”?

The H2Med aims first of all to reduce Europe’s dependence on Russian gas by improving gas interconnections between the Iberian Peninsula and its neighbors. Spain and Portugal have 40% of the EU’s regasification capacity, but are poorly connected to the rest of the EU member states.

Above all, this pipeline will ultimately accelerate the decarbonization of European industry by giving it access to clean energy produced on a large scale, as Spain and Portugal prepare to become world leaders in green hydrogen, thanks to their numerous wind and photovoltaic farms.

 

Why Marseille and Barcelona?

According to the promoters of the project, this connection is “the most direct and efficient option to connect the Iberian Peninsula to Central Europe”. In fact, Barcelona hosts “one of the largest LNG terminals” in the EU and occupies “a place of choice in the Spanish gas network”, said to AFP José Ignacio Linares, professor at the Pontificia Comillas University in Madrid. Marseille is well connected to the French network. It is also an interesting gateway to serve the Rhone Valley, Germany and even northern Italy, industrial regions that will become major consumers of green hydrogen.

Which route?

The exact route of the pipeline has not yet been communicated, but “the most logical” would be that it “follows the coast”, in order to avoid underwater areas that are too deep, according to Linares.
In this case, the H2Med would make about 450 kilometers. But a slightly different route is not excluded, the persons in charge of the project having to find “the most stable grounds possible”, even if it means to move away a little from the coast, specifies the researcher.

What obstacles?

H2Med faces several technical difficulties, partly related to its novelty. “A submarine hydrocarbon pipeline at this depth, at this distance, has never been done”, underlines Gonzalo Escribano, expert of the Spanish study center “Real Instituto Elcano”.

For José Ignacio Linares, one of the main problems is the nature of hydrogen, a gas made up of small molecules that can escape through the joints of the pipeline and are also extremely aggressive, which can lead to corrosion problems. But these problems “are not insurmountable”, underlines this engineer of formation. “All you have to do is install a membrane inside the pipe, some kind of plastic, to prevent the hydrogen from escaping or attacking” the metal, he adds.

What future?

The real risk, for the experts, is the economic viability of the project. Since the technology is still in its infancy, “we don’t know when the green hydrogen market will take off, when we will be able to produce enough to export it,” says Escribano.

 

This will turn the construction of the H2Med into an industrial bet. “The problem is that the construction time for a pipeline is so long that we can’t afford to wait. Otherwise, we’ll end up with a lot of hydrogen production that we won’t be able to export,” says Linares. Linares.

Lhyfe becomes the first French producer to obtain European RFNBO certification, delivering the first batches of certified hydrogen and opening access to new support mechanisms for the industrial sector.
Tree Energy Solutions and CPC Finland will produce 125,000 tonnes annually of e-NG at the Finnish port of Rauma, targeting European and international markets with a significant investment.
The European Commission grants €3.5mn to support preparatory work for a Franco-German cross-border network aimed at transporting hydrogen between the Grand Est region and Baden-Württemberg starting in 2029.
French company McPhy Energy awaits a court decision regarding offers submitted during its judicial reorganization, paving the way for probable liquidation and potential delisting of its shares.
The majority-Indigenous-owned Canadian manufacturer HyVera Distributed Energy is introducing an eCat pellet that instantly produces ultra-pure green hydrogen without external electricity and is counting on two pilot plants to simplify industrial supply.
Underground hydrogen storage, essential to support its growth, continues to face significantly higher costs than natural gas storage, along with major technical challenges hindering its competitiveness against conventional energies.
Singapore-based hydrogen specialist Hydrexia seals a protocol with Indonesian gas giant Samator to deploy purification, transport and storage of hydrogen, betting on rapidly growing local demand and export outlets to the Asia-Pacific region.
Cadiz Inc. signs a memorandum of understanding with British company Hoku Energy for a large-scale energy project including green hydrogen, solar power, and digital infrastructure in the Californian desert, projecting annual revenues of up to $10mn.
BP indefinitely halts its blue hydrogen project at the Whiting refinery in Indiana, raising questions about the future of federal funding and the impact on regional plans for a decarbonized hydrogen sector in the United States.
The Polish energy group ORLEN receives a non-repayable grant of €382 million from the National Recovery Plan to finance its renewable and low-emission hydrogen production initiatives.
Georgia Power and Mitsubishi Power announce successful completion of an unprecedented test incorporating 50% hydrogen into an advanced gas turbine, reducing CO2 emissions by 22% compared to natural gas alone.
Neoenergia has begun construction of one of Brazil's first green hydrogen plants, aimed at supplying heavy and light vehicles, with an investment exceeding 30 million Brazilian reais ($5.99mn).
The SA-H2 fund, supported by international partnerships and local institutional backing, mobilises 37 million USD to develop export-oriented green hydrogen from South Africa, with an initial concrete project announced.
Turbotech reports successful combustion testing of a hydrogen turboprop, developed through digital simulation with Ansys, marking an industrial milestone in light aircraft using alternative fuel.
France Hydrogène responds to the Cour des Comptes report published on June 5, criticising an incomplete reading of updated targets and the economic impacts of decarbonised hydrogen development.
The Belfort Commercial Court has opened a judicial reorganisation procedure for McPhy, while a renewed call for tenders for its asset sale is now set to close on 13 June.
Plug Power CFO Paul Middleton acquired 650,000 shares on the market, affirming his support for the long-term strategy of the hydrogen-focused company.
The Canadian government is funding an initiative to support 40 SMEs in British Columbia’s hydrogen sector, aiming to increase foreign investment and expand international market share.
Developer CWP Global has paused its $40 billion AMAN project in Mauritania due to a lack of buyers for green ammonia despite favourable local conditions.